Conflict Avoidance, Management & Dispute Resolution Procedures Flashcards
What guidance notes are relevant to Conflict Avoidance?
Conflict Avoidance and Dispute Resolution in Construction
What do you know about the HGCR Act?
- This is the Housing Grants, Construction and Regeneration Act 1996
- It introduced a statutory right to adjudication
- Commonly referred to as the ‘Construction Act’
What else does the construction act do?
It introduced a timeline for valuations and payments, stipulating that payment notices should be issued no later than 5 days after the due date.
In your submission you state that you work collaboratively to avoid conflicts, can you just elaborate a bit on that?
I work proactively to avoid a dispute evolving to the point where adjudication is required, I do this by;
- Keeping close communication with the Contractor and build a rapport
- Keep formal written records in the form of meeting minutes
- Adhere to the change control procedure so both parties know where they stand
In your submission you include a couple of points regarding actions that can be taken to avoid conflicts in the first place, what are these?
- Drafting unambiguous contract documentation
- Agreeing change control procedures
- Collectively reviewing risk registers with clear assignment of risk owners (to those best able to manage the risk)
- Effective communication
Your submission states you have experience with JCT contracts, can you just tell me how the JCT deals with collaborative working?
The contract includes a Supplemental Provision called “collaborative working”
You mention a risk register as a way of pre-empting disputes, what typically goes into a risk register?
- Any perceived risk that has a likelihood of occurring on a project which could impact on the programme and introduce additional costs
- Typically includes the risk, a risk rating system, risk owner ship, and mitigation measures.
Are there any more common risks included within risk registers?
- Insolvency of the contractor / failure to perform
- Discovery of unknown asbestos
- Also; Works undertaken by statutory undertakers, Changes in Law, Budget shortfall
You mention assigning risk owners / clearly allocating risks - why is that important?
- To ensure the party best able to manage that risk is responsible for it
- As the varying level of risk from project to project will influence the Contractors tender price i.e., will risks associated with the ground sit with the contractor or client?
You mention below ground risks, be that obstructions or contamination - who typically takes the risk with below ground in a traditional standard form
The client
Does that vary on a design and build contract?
Yes, the Contractor would take the risk for ground conditions
With regards to provisional sums - do you know who takes the risk on a provisional sum under the contract?
In terms of cost, the Client takes the risk
What is the distinction between an undefined and defined provisional sum?
- Defined = Contractor allows to undertake the works within their contract programme + pricing of Preliminaries
- Undefined = Not allowed for within the programme or pricing of preliminaries
If a conflict arises, how would you deal with it initially?
Try to resolve the conflict through communication and negotiation
What would you do if an attempt to resolve a dispute through communication is unsuccessful?
Refer the matter to an alternative dispute resolution (ADR)