Chapter 9 Flashcards

Implementing the Project Plan

1
Q

Generalizing Specialists

A

This means the people on the team can do more than one type of work no matter what their role in the team is.

This term is sometimes used for adaptive project teams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Corrective Actions (aka Defect Repair)

A

Allow you to direct the project team to fix an error to get the project back in alignment with the project objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Preventive Actions

A

Are steps you and the team take to prevent a possible error from ever entering the project - or learning a lesson and not repeating an error again.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Work Authorization System

A

This system requires project team members to report activities completed with given metrics so that downstream activities can begin.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Schedule Duration Compression

A

A fancy way of saying “hurry up”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Fast Tracking

A

Allows phases to overlap slightly so that all of the activities in the subsequent phase can finish sooner than what was planned if the phase didn’t start until after the previous phase had finished.

Fast tracking is considered risky

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Crashing

A

Allows you to add more effort to an activity or phase to get the work done faster. Crashing a project increases the labor to complete effort-driven activities, but this approach can also increase the cost of the project because someone is paying for the labor you’ve added.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Variance Report

A

This report explains the variance, the cause of the variance, and its impact on the projects success.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Committed Cost

A

Is the amount of money approved and assigned to a portion or the entirety of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Expenditure

A

The actual spending of project money.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Earned Value Management (EVM)

A

EV (Earned Value) - Representative of the work completed.

PV (Planned Value) - How much the project should cost to get to a specific point in the schedule.

AC (Actual Costs) - The actual amount of monies the project has required to date.

CV (Cost Variance) - Occurs when the actual cost of the project work is more or less than the EV.

SV (Schedule Variance) - Occurs when the EVE is more or less than the PV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost Performance Index (CPI)

A

Is a reflection of the amount of actual cumulative dollars on a projects work and how close that value is to the predicted budgeted amount.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Scheduled Performance Index (SPI)

A

Is a formula to calculate the ratio of the actual work performed versus the work planned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimate at Completion (EAC)

A

Is a prediction of what the total cost of the project will be, given current performance factors.

EAC = BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Estimate to Completion (ETC)

A

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

To-complete Performance Index (TCPI)

A

If you want to see if your project can meet the budget at completion use this:
TCPI = (BAC - EV) / (BAC - AC)

If you want to see if your project can meet the newly created estimate at completion use this:
TCPI = (BAC - AC) / (EAC - AC)

17
Q

Burn Rate

A

describes how quickly you’re burning through the project budget. The burn rate shows the consumption of funds by the project and the anticipated costs of the remainder of the budget.