Chapter 9 Flashcards
Implementing the Project Plan
Generalizing Specialists
This means the people on the team can do more than one type of work no matter what their role in the team is.
This term is sometimes used for adaptive project teams
Corrective Actions (aka Defect Repair)
Allow you to direct the project team to fix an error to get the project back in alignment with the project objectives.
Preventive Actions
Are steps you and the team take to prevent a possible error from ever entering the project - or learning a lesson and not repeating an error again.
Work Authorization System
This system requires project team members to report activities completed with given metrics so that downstream activities can begin.
Schedule Duration Compression
A fancy way of saying “hurry up”.
Fast Tracking
Allows phases to overlap slightly so that all of the activities in the subsequent phase can finish sooner than what was planned if the phase didn’t start until after the previous phase had finished.
Fast tracking is considered risky
Crashing
Allows you to add more effort to an activity or phase to get the work done faster. Crashing a project increases the labor to complete effort-driven activities, but this approach can also increase the cost of the project because someone is paying for the labor you’ve added.
Cost Variance Report
This report explains the variance, the cause of the variance, and its impact on the projects success.
Committed Cost
Is the amount of money approved and assigned to a portion or the entirety of a project.
Expenditure
The actual spending of project money.
Earned Value Management (EVM)
EV (Earned Value) - Representative of the work completed.
PV (Planned Value) - How much the project should cost to get to a specific point in the schedule.
AC (Actual Costs) - The actual amount of monies the project has required to date.
CV (Cost Variance) - Occurs when the actual cost of the project work is more or less than the EV.
SV (Schedule Variance) - Occurs when the EVE is more or less than the PV.
Cost Performance Index (CPI)
Is a reflection of the amount of actual cumulative dollars on a projects work and how close that value is to the predicted budgeted amount.
Scheduled Performance Index (SPI)
Is a formula to calculate the ratio of the actual work performed versus the work planned.
Estimate at Completion (EAC)
Is a prediction of what the total cost of the project will be, given current performance factors.
EAC = BAC / CPI
Estimate to Completion (ETC)
ETC = EAC - AC