Chapter 6 Flashcards
Building the Project Plan
Project Scope Management Plan
Defines how the project scope in a predictive project will be defined by the project management team in terms of the project requirements, how the scope will be monitored and controlled throughout the project, and how the work of the project to be considered complete, and its based on the requirements of the project stakeholders.
Change requests for the project scope for four reasons
Errors and omissions
Value-added changes
External events
Risk events
Configuration Management System
Examines the “scope” change requests effect on the features and functions of the projects product.
Integrated Change Control
All change request, scope or otherwise, pass through this to assess the effect of the change on the entire project.
Scope Verification
The work results must be examined by the project stakeholders to verify that the results are acceptable to them. This usually happens at the end of project phases and always at the end of the project. The goal is for the project customer to accept the deliverables that the project team has created.
Project Schedule Management Plan
A project schedule should be a reflection of the WBS, the accumulation of all the work packages within the project, and the assignment of resources for each task.
Gantt Chart
Is ideal for simple, short-term projects. It is a timeline of the events with consideration given to tasks that can be completed concurrently within a projects life span.
Project Network Diagram
Are fluid mappings of the work to be completed. It visualizes the flow of work from conception to completion. You can use a PND to determine the flow of work to predict the earliest completion date.
Ideal for:
Detailed project planning
Implementation tracking
Contingency plans
Resource control
Precedence Diagramming Method (PDM)
PDM requires the project manager to evaluate each project activity and determine the order in which the activities should be completed. You’ll determine which activities are successors and which are predecessors. Each unit of work in a network diagram using PDM is represented by a rectangle called an “activity node”.
The most common method of creating a network diagram is PDM
Types of Dependencies
Finish-to-start (FS) - It simply requires the predecessor task to complete before the successor task can begin.
Start-to-start (SS) - These tasks are usually closely related in nature and should be started, but not necessarily completed, at the same time.
Finish-to-finish (FF) - These tasks require that the predecessor task and the successor task be completed at nearly the same time.
Start-to-finish (SF) - These tasks require that the predecessor not begin until the successor finishes
Constraint
Is a boundary or limit based on the project. Constraints are any factors that can limit your options.
Ex. Time, cost, scope, quality expectations, security rules, and resource availability.
Hard Logic (AKA Mandatory Logic)
Describes the matter-of-fact order of activities.
Soft Logic (AKA Discretionary Logic)
Is when the project manager decides to do tasks in a particular order based on experience, conditions in the project, time, or other reasons.
Lag Time
Means that you’re adding time to the activity’s start date. Lag time is always positive time or waiting time.
Lead Time
When you’re moving the activity’s start date backward to allow it to overlap with other activities. Lead time is always negative time and often overlaps with other activities.
Types of Constraints
ASAP - As soon as possible
ALAP - As late as possible
SNET - Start no earlier than
SNLT - Start no later than
FNET - Finish no earlier than
FNLT - Finish no later than
MSO - Must start on
MFO - Must finish on
Discretionary Constraints
The constraints allow the project manager to change the relationship between activities based on educated guesses.
Resource Constraints
A project manager may elect to schedule two task as FS rather than SS because of a limitation of a particular resource.
Governance Gate
Governs how the project is allowed to move from one phase of the project into the next phase of the project. A governance gate defines the conditions that must exist for the project to move forward.
Quality Gate
Requires an inspection of the work your team has completed to confirm that it meets the quality requirements of your organization, PMO, customer, or even laws and regulations.
Legislative Approval Gate
Legislative approval would review the work and either cancel the project or continue to invest in the project based on its merit and success.
For projects in the public domain that is gov’t sponsored.
Critical Chain Method (CCM)
Accounts for the availability of project resources.
Type of PND