Chapter 7: Project Schedule Management Flashcards
This is the process of documenting how to manage the schedule.
Plan Schedule Management
This plan documents how to define, sequence, estimate, develop and control the schedule.
Schedule Management Plan
This is the process of taking the work packages from the WBSand breaking them down into activities.
Define activities
The specific work that will need to get done by the project team to create project deliverables.
Activities
The output where the activities are stored.
Activities List
The process of taking the list of activities and putting them in the order they will be performed.
Sequence Activities
A diagram that shows the order in which you will do each activity.
Project Schedule Network Diagram
A technique that is used to build a sequence using the activitites.
Precedence Diagramming Method (PDM)
A precedence diagramming method that relates activities based on their status as a predecessor or successor.
Activity on Node (AON)
A type of dependency in which one activity must be finished before starting another activity.
Mandatory Dependency (AKA hard logic, hard dependency)
A type of dependency in which activities do not need to be performed in a specific order.
Discretionary Dependency (AKA soft logic)
A type of dependency in which activities are dependent on activities outside the control of the project team.
External Dependency
A type of dependency in which activities are dependent on activities within the control of the project team.
Internal Dependencies
An overlap between activities.
Lead
Delays between activities.
Lag
The process of analyzing each activity to determine how long it will take.
Estimate Activity Duration
An input that lists all all of the identified project risks as well as their impact and response.
Risk Register
A hierarchical breakdown of resources by their categories and types.
Risk Breakdown Structure
A listing of all the lessons learned so far on the project.
Lessons learned register
The listing of the project team that will be assigned to work on the project.
Project Team Assignment
An estimating technique that relies on historical information to assign the current duration to the activities.
Analogous Estimating (AKA Top Down)
An estimating technique that uses a mathematical algorithm based on historical data and variables to calculate duration or cost.
Parametric Estimating
An estimating technique that uses optimistic, most likely and pessimistic scenarios to calculate duration or cost.
Program Evaluation and Review Technique (PERT)
(AKA Three Point Estimating)
The normal PERT formula that places more weight on the realistic estimate.
(Optimistic + 4 * Realistic + Pessimistic)/6
Beta Distribution
The formula used to give a range of an estimate.
(Pessimistic - Optimistic)/6
Standard Deviation
The formula used to give an average based on pessimistic, optimistic and realistic:
(Optimistic + Realistic + Pessimistic)/3
Triangular Distribution
The most accurate method of estimating achieved by breaking down work to the lowest levels and aggregating the work back up to find an overall duration.
Bottom Up Estimating
A data analysis technique that adds extra time to an activity to account for risk.
Reserve Analysis