Chapter 3: Project Management Processes and Role of the Project Manager Flashcards
What are the 5 process groups?
1 - Initiating
2 - Planning
3 - Executing
4 - Monitoring & Controlling
5 - Closing
What are the 10 Knowledge Areas?
1 - Project Integration Management
2 - Project Scope Management
3 - Project Schedule Management
4 - Project Cost Management
5 - Project Quality Management
6 - Project Resource Management
7 - Project Communications Management
8 - Project Risk Management
9 - Project Procurement Management
10 - Project Stakeholder Management
Name the Process Group and Knowledge area for the process(es) listed:
- Develop Project Charter
Initiating/Integration Management
Name the Process Group and Knowledge area for the process(es) listed:
- Identify Stakeholders
Initiating/Stakeholder Management
Name the Process Group and Knowledge area for the process(es) listed:
- Develop Project Management Plan
Planning/Integration Management
Name the Process Group and Knowledge area for the process(es) listed:
- Plan Scope Management
- Collect Requirements
- Define Scope
- Create Work Breakdown Schedule
Planning/Scope Management
Name the Process Group and Knowledge area for the process(es) listed:
- Plan Schedule Management
- Define Activities
- Sequence Activities
- Estimate Activity Durations
- Develop Schedule
Planning/Schedule Management
Name the Process Group and Knowledge area for the process(es) listed:
- Plan Cost Management
- Estimate Costs
- Determine Budget
Planning/Cost Management
Name the Process Group and Knowledge area for the process(es) listed:
- Plan Quality Management
Planning/Quality Management
Name the Process Group and Knowledge area for the process(es) listed:
- Plan Resource Management
- Estimate Activity Resources
Planning/Resource Management
Name the Process Group and Knowledge area for the process(es) listed:
- Plan Communications Management
Planning/Communications Management
Name the Process Group and Knowledge area for the process(es) listed:
- Plan Risk Management
- Identify Risks
- Perform Qualitative Risk Analysis
- Perform Quantitative Risk Analysis
- Plan Risk Responses
Planning/Risk Management
Name the Process Group and Knowledge area for the process(es) listed:
- Plan Procurement Management
Planning/Procurement Management
Name the Process Group and Knowledge area for the process(es) listed:
- Plan Stakeholder Management
Planning/Stakeholder Management
Name the Process Group and Knowledge area for the process(es) listed:
- Direct and manage project work
- Manage project knowledge
Executing/Integration Management
Name the Process Group and Knowledge area for the process(es) listed:
- Manage quality
Executing/Quality Management
Name the Process Group and Knowledge area for the process(es) listed:
- Acquire resources
- Develop team
- Manage team
Executing/Resource Management
Name the Process Group and Knowledge area for the process(es) listed:
- Manage communications
Executing/Communication Management
Name the Process Group and Knowledge area for the process(es) listed:
- Implement risk responses
Executing/Risk Management
Name the Process Group and Knowledge area for the process(es) listed:
- Conduct procurements
Executing/Procurement Management
Name the Process Group and Knowledge area for the process(es) listed:
- Manage stakeholder engagement
Executing/Stakeholder Management
Name the Process Group and Knowledge area for the process(es) listed:
- Monitor and control project work
- Perform integrated change control
Monitoring & Controlling/Integration Management
Name the Process Group and Knowledge area for the process(es) listed:
- Validate Scope
- Control Scope
Monitoring & Controlling/Scope Management
Name the Process Group and Knowledge area for the process(es) listed:
- Control schedule
Monitoring & Controlling/Schedule Management
Name the Process Group and Knowledge area for the process(es) listed:
- Control costs
Monitoring & Controlling/Cost Management
Name the Process Group and Knowledge area for the process(es) listed:
- Control quality
Monitoring & Controlling/Quality Management
Name the Process Group and Knowledge area for the process(es) listed:
- Control resources
Monitoring & Controlling/Resource Management
Name the Process Group and Knowledge area for the process(es) listed:
- Monitor communications
Monitoring & Controlling/Communications Management
Name the Process Group and Knowledge area for the process(es) listed:
- Control procurements
Monitoring & Controlling/Procurement Management
Name the Process Group and Knowledge area for the process(es) listed:
- Monitor stakeholder engagement
Monitoring & Controlling/Stakeholder Management
Name the Process Group and Knowledge area for the process(es) listed:
- Close project or phase
Closing/Integration Management
The process group concerned with getting authorization to start a project or phase.
Initiating