Chapter 3 - Mechanics Lien Law Flashcards
A Mechanics Lien is limited to _________ works project
Private
A ____________ bond is also known as a labor and materials bond.
Payment
Saturdays, Sundays and any day when the county recorded office is closed are considered ____________
Holidays
________________ must be in writing
Notices
When mailing, You must have a receipt and tracking information as well as a ___________ ___ ___________ __________ to show proof that a notice was served
“ Proof of Notice Declaration”
If a notice must be posted, it is considered ____________ when it is displayed
Served
A ___________________ tells the recipient that you are improving the property
Preliminary Notice
Direct contractors must send a preliminary notice to ________________ ____________
Construction Lenders
Payment bonds are also referred to as ?
Labor and materials bonds
All deadlines for Mechanics Lien Law are given in what kind of days ?
Calendar days
What months of the year have 30 days ?
June, April, November, September
( JuANS)
If you mail the notice, when is it considered to be “served” ?
When deposited in the mail
For public works, serve the preliminary notice if you do not have contract with who ?
Direct Contractor
A preliminary notice must be served within how many days of starting work ?
20 days
Subcontractor are required by law to file a preliminary notice if their share of the contract is more than _____
$400