Q

A Mechanics Lien is limited to _________ works project

A

Private

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A ____________ bond is also known as a labor and materials bond.

A

Payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Saturdays, Sundays and any day when the county recorded office is closed are considered ____________

A

Holidays

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

________________ must be in writing

A

Notices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When mailing, You must have a receipt and tracking information as well as a ___________ ___ ___________ __________ to show proof that a notice was served

A

“ Proof of Notice Declaration”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If a notice must be posted, it is considered ____________ when it is displayed

A

Served

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A ___________________ tells the recipient that you are improving the property

A

Preliminary Notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Direct contractors must send a preliminary notice to ________________ ____________

A

Construction Lenders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Payment bonds are also referred to as ?

A

Labor and materials bonds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

All deadlines for Mechanics Lien Law are given in what kind of days ?

A

Calendar days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What months of the year have 30 days ?

A

June, April, November, September

( JuANS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If you mail the notice, when is it considered to be “served” ?

A

When deposited in the mail

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

For public works, serve the preliminary notice if you do not have contract with who ?

A

Direct Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A preliminary notice must be served within how many days of starting work ?

A

20 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Subcontractor are required by law to file a preliminary notice if their share of the contract is more than _____

A

$400

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A preliminary notice for public works contract must be sent to the ____________ AND the public agency

A

Direct Contractor

17
Q

To enforce a mechanics lien, a contractor who has still not been paid for labor and/or materials must file a __________________

A

Foreclosure Lawsuit

18
Q

Can material suppliers file a mechanics lien ?

19
Q

Can manufactures of materials file a mechanics lien ?

20
Q

When does the mechanics lien take effect ?

A

When filed with county recorder

21
Q

An owner may file a _______, to free the property from the lien

22
Q

The amount of the stop payment notice bond needs to be how much of the amount claimed in the stop notice payment ?

A

125% or 1-1/4 times

23
Q

What is the purpose of a stop payment notice ?

A

Require the recipient to set aside money

24
Q

A direct contractor may file a stop payment notice to who ?

A

The lender

25
On a private works job, the owner must record a copy of the bond as well as what, before work begins ?
Original contract
26
If you do not send a preliminary notice, you may still file a claim against a payment bond within how many days after a notice of completion is filed?
15 days
27
A notice of _______ is an official declaration that work has stopped
Cessation
28
You would sign an ______ release when you have cash in hand
Unconditional
29
After a job has finished, an owner can file a notice of _______ to shorten the time claimants have to file a mechanics lien or serve a stop payment notice
Completion
30
A mechanics lien will ________ unless a lawsuit to foreclose the lien is filed.
Expire
31
You must also file a _________ ________ after filing a lien foreclosure lawsuit
Lis Pendes
32
A payment-bond lawsuit is filed against the ______________
Bonding company
33
A notice of cessation is only effective if labor has ceased for at least how many days prior to recording ?
30 days
34
When a notice of completion has been filed, the original contractor has how many days to record a lien ?
60
35
Generally, work is considered ceased if no work is performed for how many days?
60 days
36
A notice of cessation may only be recorded after work has stopped for how many consecutive days ?
30 consecutive days