There shall not be less than one boring or exploration shaft for each ______sq.ft of building area at the foundation level with a minimum of ____ provided for any one building.

A

5,000 sqft

2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A subsurface solid investigation shall be performed to determine whether the existing ground-water table is above or within ___ feet below the elevation of the lowest floor where such floor is located below the finished ground level adjacent to the foundation.

A

5 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Ground immediately adjacent to the foundation shall be sloped away from the building at a slope of NOT LESS than 1 unit (vertical) in 20 units ( horizontal) from a minimum distance of 10 feet. What percentage is the slope ?

A

5% slope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Swales used to provide an alternative method of diverting water away from the foundation shall be sloped NOT LESS than ___% where located within 10 feet of the building foundation.

A

2%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Where climatic or soil conditions warrant , the slope of the ground away from the building foundation shall be permitted to be reduced to not less than 1 unit vertical in 48 units horizontal ,which is how much in percents sloped ?

A

2%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Compacted fill material ____ inches in-depth or less need NOT comply with an approved report, provided that the in place dry density is not less than 90% of the maximum dry density at optimum moisture

A

12”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When water-proofing , it shall be applied from the bottom of the wall to not less than _____ inches

A

12 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is an example of a Class 1 (A) soil and it’s pressure ?

A

Crystalline bedrock

12,000 psf

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are Class 2 (B) soils and it’s pressure ?

A

Sedimentary and Foliated rock

4,000 psf

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are Class 3 materials and it’s pressure ?

A

Sandy Gravel and Gravel ( GW and GP)

3,000 psf

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Class 4 soil and its pressure ?

A

Sand, silty sand, clayey sand, silty gravel.

2,000 psf

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are class 5 soils and it’s pressure ?

A

Clay, sandy clay, silty clay, clayey. Silt, silt and sandy silt.

1,500 psf

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Foundation walls of rough or random rubble stone shall not be less than ______

A

16 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Retaining walls supporting more than ____ feet of backfill height shall incorporate additional seismic lateral earth pressure.

A

6 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Retaining walls shall be designed to resist the lateral action of soil to produce sliding and overturning with a minimum safety factor of ____ in each case.

A

1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

https://cdn-codes-pdf.iccsafe.org/bundles/document/new_document_images/3164/FIGURE%201808.7.1.jpg

A

Top of slope:

17
Q

What is a KEY ?

A

Compacted fill placed in a trench excavated in earth material beneath the toe of a slope.

18
Q

Benching shall be provided when the existing grande is at a slope steeper than ____ unit vertical in _____ units horizontal . Or what percent slope ?

A

1:5

20%

( 10w x 3d )

19
Q

Property line to toe of slope distance shall have a minimum setback distance of :

A

H/5 but 2ft minimum AND not to exceed 20 ft maximum.

20
Q

Terraces NOT less than 6 feet in width shall be establish at not more than ____-foot intervals on all cut or fill slopes to control surface drainage and debris

A

30-foot

21
Q

Where more than TWO terraces are required, one terrace located at approximately mid-height, shall be NOT less ____ feet in width

A

12

22
Q

Walking surface slope surfaces cannot exceed what slope ? But other components of accessible routes, such as ramps and curb ramps can be more steeply sloped.

A

1:20 or 5%

23
Q

Cross slopes must be a what slope max?

A

1:48 or 2%