Chapter 23 - Facility Design, Layout, and Org Flashcards
1
Q
First step in planning a new SC facility
A
forming a comittee
2
Q
Phases of Facility Development
A
Predesign Phase
Design Phase
Construction Phase
Preoperation Phase
3
Q
Predesign Phase
A
25% of the total project time
Create need analysis or assessment
Feasibility study conducted: costs, location, etc
4
Q
Design Phase
A
10-12% of total time
Bluprints; work with architect, equipment specification, spacing
5
Q
Construction Phase
A
50% of the total time
6
Q
Preoperation Phase
A
Start up phase
15% of total project time
Focused on staff consideration