Chapter 2: Principles Flashcards

1
Q

What is the definition of the PRINCE2 Principles?

A

The PRINCE2 principles are the guiding obligations that determine whether the project is genuinely being managed using PRINCE2 and ensure effective application and
tailoring of PRINCE2 to any project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How many are the PRINCE 2 Principles?

A

SEVEN (7)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the SEVEN (7) PRINCE 2 Principles?

A
  1. Ensure continued Business justification
  2. Learn from experience
  3. Define roles, responsibilities and relationships
  4. Manage by stages
  5. Manage by exception
  6. Focus on products
  7. Tailor to suit the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Do the 7 PRINCE2 principles offer flexibility?

A

YES

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What should happen to the project if the business justification is not any more sufficient after project initiation?

A

The project should be stopped

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When does learning from experience occur?

A
  1. When starting a project
  2. As the project progresses
  3. As the project closes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which primary stakeholders do all projects have?

A

All projects have the following primary stakeholders: the business, users, and suppliers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The assignment of roles to individuals throughout the life of the project and their responsibilities must be clear, unambiguous, and accepted. True or False?

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the definition of Manage by stages principle?

A

The section of a project that the project manager is managing on behalf of the project board at any one time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Definition of manage by stages:

The section of a project that the _____ _______is managing on behalf of the project board at any one time.

A

Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A PRINCE2 project is planned, _______, and controlled on a stage-by-stage basis.

A

A PRINCE2 project is planned, monitored, and controlled on a stage-by-stage basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The ________ ________ authorizes one stage of the project at a time and delegates the authority for day-to-day control of the stage, within agreed tolerances, to the project manager

A

The project board authorizes one stage of the project at a time and delegates the authority for day-to-day control of the stage, within agreed tolerances, to the project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How many are the aspects of a plan’s performance requiring tolerances to be defined?

A

SEVEN (7)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the seven aspects of a plan’s performance requiring tolerances to be defined

A
  1. Benefits
  2. Costs
  3. Time
  4. Quality
  5. Scope
  6. Sustainability
  7. Risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How many are the types of products included in PRINCE?

A

FOUR (4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the four types of products in PRINCE 2?

A
  1. Management Products
  2. Specialist Products
  3. Project Product
  4. External Product
17
Q

When tailoring PRINCE2, it is important to remember that effective _______ _______ requires _______ (but not necessarily documents) and decisions (but not necessarily meetings).

A

When tailoring PRINCE2, it is important to remember that effective project management requires information (but not necessarily documents) and decisions (but not necessarily meetings).

18
Q

What is/are the purpose/s of tailoring PRINCE 2?

A
  1. The project management method used is appropriate to the project
  2. Project controls are appropriate to the project’s scale, complexity, importance, delivery method, team capability, and risk
19
Q

Who is responsible for tailoring a PRINCE 2 project?

A

The project manager

20
Q

Where are the tailoring information captured?

A

PID (project initiation documentation)

21
Q
A