Chapter 11: Progress Flashcards
Progress: the measure of the achievement of the ________s of a plan
Progress: the measure of the achievement of the objectives of a plan
Forecast: a prediction made by studying historical _____ and ______ patterns.
Forecast: a prediction made by studying historical data and past patterns.
Exception: a situation where it can be _______ that there will be a deviation beyond the tolerance levels agreed between the _______ ________ and the project board (or between the project board and business layer).
Exception: a situation where it can be forecast that there will be a deviation beyond the tolerance levels agreed between the project manager and the project board (or between the project board and business layer).
What does effective progress management include (7items)?
Effective progress management includes:
● defining management levels and tolerances for progress control
● applying two types of control (event-driven and time-driven)
● reviewing progress and lessons
● reporting progress and lessons
● forecasting remaining work
● escalating
● using data.
Table 11.1 The seven tolerance types by layer
Open book and ask each other questions
What is the difference of an event driven and a time driven control?
Event-driven control: a control that occurs when a specific event occurs. For example, this could be the end of a stage, the completion of the project initiation documentation, or the creation of an exception report. It could also include organizational events that may affect the project, such as the end of the financial year.
Time-driven control: a management control that occurs at predefined periodic intervals. For example, this could be producing highlight reports for the project board or checkpoint reports showing the progress of a work package.
Definition: lesson
A lesson is information to facilitate the future of the ______ or other projects and actively promote ________ from experience. The experience may be positive, as in a successful test or outcome, or negative, as in a mishap or failure.
Definition: lesson
A lesson is information to facilitate the future of the project or other projects and actively promote learning from experience. The experience may be positive, as in a successful test or outcome, or negative, as in a mishap or failure.
Which 5 questions should the analysis of a lesson answer?
The analysis of a lesson should answer five questions in the following order:
● what did we expect to occur?
● what actually happened?
● what worked well and why?
● what did not work and why?
● what needs to be done differently or what needs to be repeated?
Is the checkpoint report time-driven or event-driven?
It is time-driven
Exception report: it is provided from the _____ ______ to the _____ _____ and it is _____-driven.
It is provided by the project manager to the project board and it is event-driven.
is the highlight report time or event-driven?
What is its use?
It is time-driven.
It is use is to provide a progress and status
update of the project and stage
How many steps is the PRINCE 2 technique for exception management?
SIX
If a different to the PRINCE2 exception management technique is decided to be used, where shall this be documented?
The use of an alternative procedure should be documented as part of the tailoring decisions in the project initiation documentation.
On the exception management technique, on step 1, when does a team manager raise an issue to the project manager?
STEP 1: Product takes work package outside of its tolerances - issue mentioned at issue register by team manager
If the issue can be resolved by the project manager within the stage tolerances, is an exception report still required?
NO, If the issue can be resolved by the project manager within the stage tolerances, the resolution will not require an exception report to be created. However, the issue will be reported in the next highlight to the project board, and a note may be made in the lessons log.