Chapter 2 - Earthmoving materials & operations Flashcards

1
Q

Describe the process of earthmoving

A

Excavation -> Loading -> Hauling(moving) -> Placing(Dumping) -> compaction -> Grading & Finishing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Describe how efficiently manage earthmoving

A

1) Accurate estimation of job quantity & conditions
2) Proper selection of equipment
3) Competent job management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the criteria to select equipment?

A

1) The ability of it to perform the work
2) Out of the options available, the one maximizing profit
3) Possible future use
4) Availability of the equipment, parts and service
5) The effect of equipment downtime on other construction operations
* Equipment downtime - The amount of time that equipment isn’t operating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the basic relationship of production?

A

Volume per cycle x cycles per hour = production

Volume per cycle - Nominal capacity of the equipment
Cyles per hour - including efficiency. 60(min/hr)/ cycle time (min)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the cost per unit production formula

A

Equipment cost ($/hr) / Equipment (production/hr)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What characteristics of soil and rock the constructor should know about?

A

1) Volume-change characteristics
2) Methods of classification
3) Field identification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Describe the different volume-change characteristics (Bank, loose compacted and their units)

A

Bank: Material in its natural state before disturbance(“in-place”). BCY/BCM
Loose: Excavated or loaded material. LCY/LCM
Compacted: Material after compaction. CCY/CCM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the formulas for swell and shrinkage

A

Swell (%) = ((Soil density in bank/Soil density in loose) -1) x 100
Shrinkage (%) - (1- (Soil density in bank/Soil density in compaction)) x 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the volume of:
1) Spoil bank
2) Spoil pile

A

1) Bank - Section area X length
2) Pile - 1/3 x base area x height

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the height of:
1) Spoil bank - also what is the base formula
2) Spoil pile - also what is the diameter formula

A

1) Bank - H=(B x tanR)/2 while B = square root (4V/(L x tanR))
2) Spoil - H=(DxTanR)/2 while D = cube root ((7.64V)/tanR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What Mass diagram provides CMs with?

A
  • The length and direction of the haul
  • Location and amount of borrow and waste
    -The average length of the haul
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is stripping?

A

The upper layer of organic material

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the meaning of negative mass ordinate? (The last column in the mass diagram table)

A

Negative means- More fill than cut up to this point in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the most economical haul distance for each machine type (Dozer, Scraper, Trucks)

A

Dozers - 0<x<300
Scarper 300<x<5000
Trucks x>5000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Mass diagram: If the curve is above the balance line, in which direction is the haul?

A

The direction of haul is from left to right—lower station value to a higher station value.

  • When the curve is below the balance line the haul is from right to left—down stationing.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly