Chapter 11 Fire-Resistive Construction Flashcards

1
Q

Aggregates

A

Any of a variety of materials, such as sand and gravel, added to a cement mixture to make concrete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cables

A

Special high strength, cold-drawn steel cables. Also referred to as strands or tendons.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cast in place concrete

A

Includes plain concrete, reinforced concrete, and post tensioned concrete. This concrete is molded in the location in which it is expected to remain.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Casting

A

A process of placing fluid concrete into molds, generally called forms, in which the concrete is permitted to harden to a certain shape.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Chairs

A

Small devices designed to keep the rods up off the surface of the form so concrete will flow underneath.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Composite and combination columns

A

Columns that use steel and concrete combined into one unit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Composite construction

A

Buildings in which different loadbearing materials are used in different areas of the building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Continuous casting

A

Process for casting or pouring concrete without interruption from start to finish.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Continuous slipforming

A

Pouring concrete continuously as forms move upward so that continuous casting may be accomplished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Drop panel

A

Thicker section of floor on top of columns to assist in resisting the natural tendency of the floor to shear off at the column.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Excess flow valve

A

Valve that senses a sudden increased flow, as from a broken line, and shuts off flammable gas.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Falsework

A

Temporary shoring, formwork, beams, or lateral bracing to support the concrete work in the process of construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Flat plate structural system (continuous beam)

A

Cast in place floor in which there are no beams supported by columns; the floor plate itself rests directly on the columns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Footing

A

Typically thick concrete pads, blocks, or strips of concrete below the surface of the surrounding soil, sometimes heavily reinforced, that transfer the loads of walls, piers, or columns to the ground. Footings attempt to minimize building settlement by spreading the load over the large soil/concrete interface.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Formwork

A

Mold that shapes the concrete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Hollow tile

A

Tile unit composed of vertical hollow cells, utilized in early efforts to lighten concrete floors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Lally columns

A

Steel pipes filled with concrete to increase their load-carrying capacity.

18
Q

Left-in-place form

A

Concrete floors that are cast onto corrugated steel.

19
Q

Lift slab

A

Type of building construction where concrete slabs are cast on the ground and lifted into place.

20
Q

Monolithic construction

A

Method in which all the concrete in a building is properly bonded together and acts as one.

21
Q

Mudsills

A

Planks on which formwork shores rest.

22
Q

Mushroom cap

A

Tapered extension at the tops of columns that assists in the transfer of loads from floor to column.

23
Q

One-way structural system

A

System that incorporates floors that have beams running in one direction only.

24
Q

Plain concrete

A

Concrete that has no reinforcement, except possibly light reinforcement to resist temperature changes.

25
Q

Precast concrete

A

Concrete that has been cast at a location other than the place where it is to remain.

26
Q

Prestressing

A

Engineered stresses placed in architectural and structural concrete to offset the stressors that occur in the concrete when it is placed under load.

27
Q

Pretensioning and post tensioning

A

Processes by which steel tendons or rods are placed under tension, drawing the anchors together. Tensioned steel places the concrete in compression.

28
Q

Reinforced concrete

A

In concrete masonry structure, steel reinforcement that is embedded in such a manner that the two materials actor together in resisting forces.

29
Q

Reinforcing bars or rods

A

Steel rods or bars used to reinforce concrete.

30
Q

Reshoring

A

Shores that are put back into concrete to help carry the load of the still curing concrete.

31
Q

Skewbacks

A

Tiles shaped to fit around steel.

32
Q

Slipforming

A

Technique by which forms are moved upward as the concrete is poured.

33
Q

Spalling

A

Loss of surface material when concrete is subjected to heat.

34
Q

Strands

A

Special high strength, cold-drawn steel cables. Also referred to as cables or tendons.

35
Q

Stressing the tendons

A

After concrete is poured and reaches its specified strength, steel tendons are stretched and anchored at the ends of the unit. Also referred to as “jacking the cables.”

36
Q

Temperature rods

A

Thin rods installed near the surface of concrete, usually at right angles to the main reinforcing rods, to help the concrete resist cracking due to temperature changes.

37
Q

Tendons

A

Special high strength, cold-drawn steel cables. Also referred to as strands or cables.

38
Q

Two-way structural system

A

System that incorporates floors that have beams running in two directions.

39
Q

Underwriters blocks

A

Concrete blocks poured per Underwriters Laboratories, Inc.’s classifications.

40
Q

Waffle concrete

A

Two way structural system with closely spaced beams set a tight angles to one another in which unnecessary concrete is formed out; lower side resembles a waffle.