Chapter 10 Flashcards
1
Q
planning
A
what activities should take place
when
what resources
2
Q
control
A
the process of coping with any changes that affect the plan
- understanding what is actually happening
- if there is a significant deviation from what should be happening
- if there is changing resources
long, medium or short-term
3
Q
activities of planning and control
A
scheduling
sequencing
loading: how much, and who
monitoring and control
4
Q
finite loading
A
calculates the start and finish dates, very detailed, taking into account existing resource load
5
Q
infinite loading
A
without taking into account the existing resource, possible for resource overloads to occur
6
Q
push system
A
where material is moved on the next stage as soon as it has been processed
7
Q
pull system
A
where material is moved only when the next stage wants it