CH8 Flashcards
1.Managing quality includes all of the quality assurance activities plus product design and process improvements.
a.
TRUE
b.
FALSE
TRUE
2.Change requests and verified deliverables are the outputs of the controlling quality process.
a.
TRUE
b.
FALSE
TRUE
3.The design of experiments technique cannot be applied to project management issues such as cost and schedule trade-offs.
a.
TRUE
b.
FALSE
FALSE
4.Customer requirements are an important aspect of the quality planning process.
a.
TRUE
b.
FALSE
TRUE
5.Reliability is the ability of a product or service to perform as expected under unusual conditions.
a.
TRUE
b.
FALSE
FALSE
6.Project managers are ultimately responsible for quality management on their projects.
a.
TRUE
b.
FALSE
TRUE
7.Only in-house auditors can perform quality audits.
a.
TRUE
b.
FALSE
FALSE
8.Products that are accepted by project stakeholders are considered to be validated deliverables.
a.
TRUE
b.
FALSE
TRUE
9.A run chart is a bar graph that depicts data points and their order of occurrence.
a.
TRUE
b.
FALSE
FALSE
10.Using Six Sigma principles is an organization-wide commitment and all employees must embrace its principles.
a.
TRUE
b.
FALSE
TRUE
11.The Six Sigma approach works best for a project where a quality problem is identified between the current and desired performance.
a.
TRUE
b.
FALSE
TRUE
12.The term sigma means median.
a.
TRUE
b.
FALSE
FALSE
13.Testing as a stage is important only at the end of an information technology product development.
a.
TRUE
b.
FALSE
FALSE
14.Integration testing involves testing of each individual component to ensure that it is as defect-free as possible.
a.
TRUE
b.
FALSE
FALSE
15.In TQC, product quality is more important than production rates, and workers are allowed to stop production whenever a quality problem occurs.
a.
TRUE
b.
FALSE
TRUE
16.DeMarco and Lister’s study on organizations and productivity found direct correlations between productivity and programming language, years of experience, and salary.
a.
TRUE
b.
FALSE
FALSE
17.Frameworks for helping organizations improve their processes and systems are called Six Sigma charts.
a.
TRUE
b.
FALSE
FALSE
18.Gantt charts cannot be used to aid project quality management.
a.
TRUE
b.
FALSE
FALSE
19.Which term is used when the project’s processes and products meet written specifications?
a.
conformance to requirements
b.
fitness for use
c.
project feasibility
d.
benchmarking
a.
conformance to requirements
20.Which term is used for the ability of aproduct to be used as it was intended?
a.
conformance to requirements
b.
fitness for use
c.
critical chain scheduling
d.
free slack
b.
fitness for use
21.The main outputs of which process are a quality management plan, quality metrics, project management plan updates,and project documents updates?
a.
controlling quality
b.
planning quality management
c.
quality certification
d.
performing quality assurance
b.
planning quality management