CH6 Flashcards
56.Whichtechnique involvesnetwork diagramming and is used primarily to predict total project duration?
a.
Gantt chart
b.
critical path analysis
c.
resource breakdown structure
d.
arrow diagramming method
b.
critical path analysis
14.A merge occurs when one node precedes multiple nodes.
a.
TRUE
b.
FALSE
FALSE
38.Which document is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?
a.
resource breakdown structure
b.
milestones list
c.
organizational process assets update
d.
project charter
d.
project charter
15.Start-to-finish relationships are the most frequently used dependencies between activities.
a.
TRUE
b.
FALSE
FALSE
51.Which is true of dummy activities?
a.
They have long durations.
b.
They show logical relationships between activities.
c.
They have a large range of resources.
d.
They have limited time periods.
a.
They have long durations.
36.In project schedule management,which process primarily involves checking and managing changes to the project schedule?
a.
estimating activity durations
b.
developing the schedule
c.
controlling the schedule
d.
estimating activity resources
c.
controlling the schedule
62.Whichtechnique is usedfor making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost?
a.
dependency
b.
crashing
c.
critical chain scheduling
d.
feeding buffers
b.
crashing
25.The technique of fast tracking can result in lengthening the project schedule.
a.
TRUE
b.
FALSE
TRUE
11.Network diagrams are the preferred technique for showing activity sequencing.
a.
TRUE
b.
FALSE
TRUE
24.The main disadvantage of crashing is that it lengthens the time needed to finish a project.
a.
TRUE
b.
FALSE
FALSE
35.In project schedule management, which process involves analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?
a.
planning schedule management
b.
developing the schedule
c.
controlling the schedule
d.
defining activities
b.
developing the schedule
26.Critical chain scheduling assumes that resources multitask and maximizes multitasking.
a.
TRUE
b.
FALSE
FALSE
6.To define activities, the project team should start with reviewing the schedule management plan, scope baseline, enterprise environmental factors, and organizational processes.
a.
TRUE
b.
FALSE
TRUE
12.The arrows in a network diagram represent missed milestones in a project.
a.
TRUE
b.
FALSE
FALSE
4.Project schedules grow out of basic documents such as the project charter.
a.
TRUE
b.
FALSE
TRUE
57.The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.
a.
longest; longest
b.
longest; shortest
c.
shortest; longest
d.
shortest; shortest
b.
longest; shortest
19.A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.
a.
TRUE
b.
FALSE
FALSE
27.One of PERT’s main disadvantages is that it does not address the risk associated with duration estimates.
a.
TRUE
b.
FALSE
FALSE
43.Which type of dependencies are inherent in the nature of work being performed on a project?
a.
mandatory
b.
discretionary
c.
external
d.
random
a.
mandatory
32.In project schedule management, which process generates the main outputs of an activity list, activity attributes, and a milestone list?
a.
sequencing activities
b.
defining activities
c.
resource estimating activities
d.
estimating activity durations
b.
defining activities
28.The final process in project schedule management is developing the schedule.
a.
TRUE
b.
FALSE
FALSE
10.A dependency pertains to the sequencing of project activities or tasks.
a.
TRUE
b.
FALSE
TRUE
39.Whichstatement best describes thedifference between an activity list and an activity attribute?
a.
As opposed to an activity attribute, an activity list provides resource requirements and constraints related to activities.
b.
An activity list provides a more concrete list of milestones for a project than an activity attribute.
c.
An activity attribute is a tabulation of activities to be included on a project schedule whereas an activity list is not.
d.
An activity attribute provides more schedule-related information about each activity than an activity list.
d.
An activity attribute provides more schedule-related information about each activity than an activity list.
44.Which dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options?
a.
mandatory
b.
discretionary
c.
external
d.
inherent
b.
discretionary
52.Which is one of the main outputs of estimating activity resources process?
a.
project documents update
b.
milestone list
c.
breakdown structure
d.
activity duration estimate
a.
project documents update
23.Knowing the amount of float allows project managers to know whether a project schedule is flexible.
a.
TRUE
b.
FALSE
TRUE
61.Which technique involves doing activities in parallel that one would normally do in sequence?
a.
Critical chain scheduling
b.
Crashing
c.
Fast tracking
d.
PERT analysis
c.
Fast tracking