Ch.6 Time management Flashcards

1
Q

What is the process of time management?

A
  • Plan Schedule management
  • Define activities
  • Sequence activities
  • Estimate activity resources
  • Estimate activity duration
  • Develop schedule
  • Control schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the key output of the plan schedule management process?

A

Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key outputs of the define activities process?

A
  • Activity list
  • Activity attributes
  • Milestone list
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the key outputs of the sequence activities process?

A
  • Network diagrams

- Update to the project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are some of the key outputs of the estimate activity resources process?

A
  • Activity resources requirements

- Resource breakdown structure (RBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key outputs of the estimate activity durations process?

A
  • Activity duration estimates

- Updates to project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does the develop schedule process involve?

What are some of its key outputs?

A

Creating a project schedule that is bought into, approved, realistic, and formal.

  • Project Schedule
  • Schedule baseline
  • Updates to the project management plan and project documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the key outputs of the control schedule process?

A
  • Work performance information
  • Schedule forecasts
  • Change requests
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the four types of logical relationships between activities in the precedence diagramming method?

A
  • Finish-to-start (FS): an activity must finish before the successor can start
  • Start-to-start (SS): An activity must start before the successor can start.
  • Finish-to-finish (FF): An activity must finish before the successor can finish.
  • Start-to-finish (SF): An activity must start before the successor can finish.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are mandatory dependencies?

What are discretionary dependencies?

A

Mandatory: The order in which acivites must be done, due to the inherent nature of the work; also called “hard logic”.

Discretionary: The order in which the organization has chosen that activities be performed also called “preferred,” “preferential,” or “soft logic”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are external dependencies?

What are internal dependencies?

A

External: dependencies based on the need of a party OUTSIDE the project.

Internal: dependencies based on the needs of the project may be under the control of the project team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is lag?

What is lead?

A

Lag: Waiting time inserted between activities.

Lead: How soon an activity can start before its predecessor activity is completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is resource breakdown structure?

A

An organizational chart or table showing identified resources, organized by category and type.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How does a schedule modal differ from a schedule?

A

The schedule modal consists of all the project data that will be used to calculate the schedule, such as the activities, dependencies, leads and lags, etc.

The project schedule is the output of the schedule model– this refers to the final, printed dates that make up the schedule that becomes the baseline and part of the project management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is critical path?

What is the near-critical path?

A

Critical: The longest path through the network diagram.

Near-critical: The path closest in length to the critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How does the critical path help us to manage project?

A

It shows the project manager the shortest time in which the project can be completed.

It shows the project manager where to focus his or her time.

It is used in compressing or adjusting the schedule.

17
Q

Define total float, and project float.

A

Total Float: the amount of time and activity can be delayed without delaying the project end date or an intermediary milestone.

Free float: The amount of time an activity can be delayed without delaying the early start date of its successor(s)

Project float: The amount of time the project can be delayed without affecting the project’s required end date.

18
Q

What are the two formulas for calculating float?

A

LS - ES

OR

LF - EF

19
Q

What are the methods that can be used to compress a schedule?

A
  • Crashing

- Fast tracking

20
Q

What is crashing?

A

Adding or adjusting resources in order to compress the schedule while maintaining the original project scope

21
Q

What is fast tracking?

A

Compressing the schedule by doing more critical path activities in parallel

22
Q

What is the critical chain method?

A

A schedule network analysis tool that builds in buffers at critical milestones.

23
Q

What is re estimating?

A

Estimating the project again after planning to make sure you can still meet the end date, budget, or other objectives, and adjusting the project if you cannot

24
Q

What is resources optimization?

A

Finding ways to adjust the use of resources

25
Q

What is resources levelling?

A

A resource optimization technique that keeps that amount of resources used for each time period constant, resulting a more stable level of resources and a longer project duration.

26
Q

What is resource smoothing?

A

A modified form of resource leveling, where resources are leveled only within limits of the float of their activities, so that the completion of activities are not delayed.

27
Q

What is the schedule baseline?

A

The approved version of the schedule model, along with any approved changes, used to measure project schedule performance.

28
Q

What are the main presentation formats for a schedule?

A
  • Network diagrams
  • Bar charts
  • Milestone charts
29
Q

What do network diagrams show?

A

Dependencies (logical relationships) between activities

How project activities will flow from beginning to end.

Network diagrams may also be used to determine the critical path.

30
Q

What do simple bar charts show?

A

Project schedule or project status

31
Q

What do milestones chart show?

A

High-level project status

32
Q

What is Monte Carlo analysis?

A

A schedule network analysis technique used to simulate the project to determine the likelihood that the project will be completed by a specific date or for a specific cost.

Also used to perform quantitative risk analysis to determine the overall level of risk on the project.