Ch.6 Time management Flashcards
What is the process of time management?
- Plan Schedule management
- Define activities
- Sequence activities
- Estimate activity resources
- Estimate activity duration
- Develop schedule
- Control schedule
What are the key output of the plan schedule management process?
Schedule management plan
What are the key outputs of the define activities process?
- Activity list
- Activity attributes
- Milestone list
What are the key outputs of the sequence activities process?
- Network diagrams
- Update to the project documents
What are some of the key outputs of the estimate activity resources process?
- Activity resources requirements
- Resource breakdown structure (RBS)
What are the key outputs of the estimate activity durations process?
- Activity duration estimates
- Updates to project documents
What does the develop schedule process involve?
What are some of its key outputs?
Creating a project schedule that is bought into, approved, realistic, and formal.
- Project Schedule
- Schedule baseline
- Updates to the project management plan and project documents
What are the key outputs of the control schedule process?
- Work performance information
- Schedule forecasts
- Change requests
What are the four types of logical relationships between activities in the precedence diagramming method?
- Finish-to-start (FS): an activity must finish before the successor can start
- Start-to-start (SS): An activity must start before the successor can start.
- Finish-to-finish (FF): An activity must finish before the successor can finish.
- Start-to-finish (SF): An activity must start before the successor can finish.
What are mandatory dependencies?
What are discretionary dependencies?
Mandatory: The order in which acivites must be done, due to the inherent nature of the work; also called “hard logic”.
Discretionary: The order in which the organization has chosen that activities be performed also called “preferred,” “preferential,” or “soft logic”
What are external dependencies?
What are internal dependencies?
External: dependencies based on the need of a party OUTSIDE the project.
Internal: dependencies based on the needs of the project may be under the control of the project team.
What is lag?
What is lead?
Lag: Waiting time inserted between activities.
Lead: How soon an activity can start before its predecessor activity is completed.
What is resource breakdown structure?
An organizational chart or table showing identified resources, organized by category and type.
How does a schedule modal differ from a schedule?
The schedule modal consists of all the project data that will be used to calculate the schedule, such as the activities, dependencies, leads and lags, etc.
The project schedule is the output of the schedule model– this refers to the final, printed dates that make up the schedule that becomes the baseline and part of the project management plan.
What is critical path?
What is the near-critical path?
Critical: The longest path through the network diagram.
Near-critical: The path closest in length to the critical path.