13. Stakeholders Flashcards
What are the process of stakeholders management?
- Identify stakeholders
- Plan stakeholder mgt
- Manage stakeholder engagement
- Control stakeholder engagement
What is the key output of the identify stakeholders process?
Stakeholder register
What is the key output of the plan stakeholders mgt process?
stakeholder mgt plan
What are the key outputs of the mange stakeholder engagement process?
- Issue log
- Change requests
- Updates to project mgt plan and project documents
- Lessons learned (part of updates to organizational process assets)
What are the key outputs of the control stakeholder engagement process?
- Change request
- Work performance information
- Updates to project mgt plan and project documents
- Lessons learned (part of updates to organizational process assets)
What should the project manager do with stakeholders throughout the project?
- Identify all of them
- Determine their requirements
- Determine their expectations
- Determine their interest and influence
- Plan how to manage them
- Plan how to communicate with them
- Manage their expectations, influence, and engagement
- Communicate with them
- Control the communications and stakeholder engagement
What are stakeholder expectations?
- Beliefs (or mental picture of) the future
- Some expectations will become requirements
Why it’s important to identify all the stakeholders as early as possible on a project?
Stakeholders discovered late in the project will likely request change, which can lead to delays
What does stake holders analysis involve?
Identifying stakeholders, analyzing their impact and influence on the project, and identifying ways to mange those impacts
What informations about stakeholders might be included in a stakeholders register?
- Name and title
- Contact information
- Department and supervisor
- Roles and responsibilities
- Major requirements and expectations
- Impact and influence
- Classifications
Why is it important to build good relationships with stakeholders?
Close relationships with stakeholders can provide an early warning system for problems on the project
Describe the different level of stakeholders engagements
- Unaware
- Resistant
- Neutral
- Supportive
- Leading
What might be documented in stakeholder mgt plan?
- Existing and desired levels of engagement for stakeholders
- Details about how stakeholders will be involved in the project
- How and why specific projects information will be distributed to stakeholders
- Guidelines for evaluating how well the plan is meeting the needs of stakeholders and the project
- How communications will be used to help manage stakeholder engagement and expectations
How does the stakeholder mgt pan differ from the communications mgt plan when it comes to documenting communication requirements?
The communications mgt plan emphasizes the details about the technology, methods, and models of communication - the how of communication
The stakeholder mgt plan explains the why of communications– why stakeholder need to receive certain information, and how the sharing of the information will help in stakeholder mgt.