Ch.13 JIT & Lean Production Flashcards
Mfg based on planned wastes elimination & improve productivity.
Just-in-Time
JIT
syn LEAN
Simplified Production that
min. amt of resources
& identifies/eliminates
non-value-adding
activities in enterprise
Lean
syn JIT
In APICS JIT/Lean methods, activity that is NOT Value-Adding to G/S for Cx is
Waste
Defect
Overproduction
Waiting
Non-Utilized EE
Transportation
Inventory
Motion
Extra-Processing
An Extension of Lean to SC beyond prod which min. level of resources for all SC activities
Lean Supply Chain Mngt
An Approach using containers/ cards/ visual cues to ctrl goods prod and mvmt thru SC
Kanban System
Calculate # of Kanban
or Production Cards
. DT(1+x)
y = ————-
. C
y # of Kanbans
D DD of DnS
T Time to fill & move to DnS
C Container Size
x Safety Factor