Capitulo: 9. PROJECT RESOURCE MANAGEMENT Flashcards
What is the process of resource
management?
Plan Resource Management
Estimate Activity Resources
Acquire Resources
Develop Team
Manage Team
Control Resources
What are the key outputs of the Plan
Resource Management process?
Resource management plan
Team charter
Project documents updates
What are the key outputs of Estimate
Activity Resources?
Resource requirements
Resource breakdown structure
What are the key outputs of the Acquire
Resources process?
Physical resource assignments
Project or work assignments
Resource calendars
What are the key outputs of the Develop
Team process?
Team performance assessments
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
What are the key outputs of the Manage
Team process?
Change requests
Project management plan updates
Project document updates
Enterprise environmental factors
updates
What are the key outputs of the Control
Resources process?
Work performance information
Updates to project documents and
project management plan
Change requests
What are the resource responsibilities for
project managers?
Determine human and physical
resources needed
Negotiate with resource managers and
confirm availability of assigned resources
Create a project team directory and job
descriptions for team members
Make sure all roles and responsibilities
are clearly assigned
Create a resource management plan
What does RAM stand for?
The Responsibility Assignment Matrix
(RAM) chart cross-references team
members with the activities or work
packages they are to accomplish
What does RACI stand for?
The RACI chart defines role assignments
more clearly by noting how team
members are to be involved with four
categories: Responsible, Accountable,
Consulted, Informed (RACI)
What is the purpose of an organizational
breakdown structure?
To assign project responsibilities to
divisions or departments within the
organization, such as marketing, product
development, or IT
What are the key elements of a resource
management plan?
Human resources
* Identification of human resource
requirements
* Roles and responsibilities
* Project organizational charts
* Process for acquiring human
resources
* Training, team development, and
recognition
* Project team management
* Compliance
* Safety
* Release of human resources
Physical resources
* Identification of physical resource
requirements
* Process for acquiring physical
resources
* Inventory management
* Release of resources
What is the purpose of a team charter?
A working agreement developed by the
members of the project team; it describes
the approach the team will take
regarding communications, decision-
making, and conflict resolution, as well
as ground rules for team meetings
What is preassignment?
Preassignment: Resources, both physical
and team, that are assigned before the
project begins
What is multicriteria decision analysis?
Using a set of criteria (such as
availability, cost, experience, location,
skill set, knowledge, or training) to
evaluate potential team members