Building Pathology Flashcards
45 Cullen St. What are obligations under building regulations when replacing roofs?
- Building control application required if more than 50% of the surface of the individual thermal element is renovated.
- Ensure thermal insulation is sufficient by upgrading.
45 Cullen St. Why did you advise replacing the cold roof with a warm roof?
Reduced risk of condensation and improved energy efficiency and energy bills.
45 Cullen St. What additional benefits did you mention about implementing the warm roof system?
Reduced risk of condensation and improved energy efficiency and energy bills.
45 Cullen St. How did you explain that the proposed warm roof system would satisfy Part L?
Insulation placed
between and over
joists as required to
achieve the target
U-value
45 Cullen St. What U-Value did you need to achieve?
0.16 W/m2K as per Appendix C Table C1 AD L.
What is a U-Value?
A measure of the ability of a building
element or component to conduct heat from a warmer environment to a cooler environment. It is expressed as the quantity of heat (in watts) that will
flow through 1m2 of area divided by the difference in temperature (in degrees K) between the internal and external environment. The unit is W/(m2K).
45 Cullen St. Did you take a core sample of the roof?
I asked a roofing contractor to carry out this task and it was confirm there was no insulation and timber roof deck.
45 Cullen St. Why was a liquid applied system not applicable?
The roof replacement was simple with no plant or penetrations. Felt was the favoured option and generally more cost effective, especially on a domestic property.
18 Noel St. Explain the rationale behind advising the use of lime in the mortar mix.
Due to being Victorian soft bricks specified 1:3 / NHL 3.5.
18 Noel St. What internal recommendations were made to address the dampness issue?
Ready mixed lime mortar at a ratio 1:3. Lime puty:Sharp Sand.
18 Noel St. How did you Identify the DPC?
Wider mortar joint at the base of the wall.
18 Noel St. What type of DPC was It?
Slate
18 Noel St. If they continued to report damp issues despite implementing your advice, what additional steps would you recommend?
Advice that it can take many months for the wall to dry out. Heat the property.
18 Noel St. Why did you recommend a French drain as well as guttering?
To allow rainwater to be directed away from the bay effectively and for water to evaporate from the ground.
67 Holmes - How were moisture readings recorded and mapped?
Sketch of the wall including skirting, readings taking from moisture meter at different levels using a rule.