BMT 14 - Critical Path Analysis (HL - Unit 4) Flashcards
1
Q
Critical Path Analysis
A
A visual timeline management system for organizing and optimizing task sequences.
Shows:
- Tasks
- Order of tasks
- Dependent tasks
- Simultaneous tasks
- Ideal scheduling
2
Q
Construction of the diagram
A
3
Q
Earliest Start Time (EST)
A
4
Q
Latest Finish Time (LFT)
A
5
Q
Total (Free) Float
A
Amount of time a task can be delayed without the project being delayed
Float (A) = 0 days
Float (C) = 3 days
6
Q
Critical Path
A
Path through the diagram for tasks which float equal to zero
i.e. these tasks cannot be delayed without delaying the whole project
7
Q
Advantages of Critical Path Analysis
A
- A visual representation of a complex project which may be easier to interpret.
- It minimizes task delays and optimizes project workflow for maximum efficiency.
- Encourages forward planning in business organizations.
8
Q
Disadvantages of Critical Path Analysis
A
- Delays and unexpected events can impact project timelines.
- Large projects can make diagrams complex and difficult to manage.
- Network analysis requires accurate and complete data to be effective.