AIA Document A701-2018 Exam Flashcards

1
Q
  1. Written or graphic instruments used by the architect prior to the execution of the contract
    which modify
    or interpret the bidding documents by additions, deletions, clarifications or corrections are
    referred to as
    .
    A. Amendment
    B. Change order
    C. Change directive
    D. Addenda
A
  1. D 1.3
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. A bidder by making a bid represents that .
    A. The bid is based on materials required by the bidding documents with exceptions
    B. Bidder has posted a letter of credit
    C. The bidder has visited the site
    D. Bidder has general liability insurance
A
  1. C 2.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. A deposit may be required from a bidder who obtains complete sets of bidding documents from the
    issuing office. The deposit will be refunded to bidders who submit a bona fide bid and return the
    bidding documents in good condition within days after receipt of bids.
    A. 5
    B. 10
    C. 15
    D. 30
A
  1. B 3.1.2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Bidders and sub-bidders requiring clarification or interpretation of the bidding documents shall make a
    written request which shall reach the architect at least days prior to the date for receipt
    of bids.
    A. 7
    B. 14
    C. 21
    D. 30
A
  1. A 3.2.2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Interpretations, corrections and changes of the bidding documents will be made by .
    A. Addendum
    B. Change directive
    C. Change order
    D. Amendment
A
  1. A 3.2.3
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. No substitution for materials, products or equipment will be considered prior to receipt of bids unless
    written request for approval has been received by the architect at least days prior to the
    date for receipt of bids.
    A. 30
    B. 15
    C. 10
    D. 5
A
  1. C 3.3.2.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. All copies of the bid, the bid security, if any, and other documents required to be submitted with the bid
    shall be enclosed in a sealed, envelope.
    A. Transparent
    B. Opaque
    C. Red
    D. Blue
A
  1. B 4.3.2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. Oral, telephonic or telegraphic bids are and will not receive consideration.
    A. Invalid after 3 days
    B. Valid for 24 hours
    C. Invalid after 5 days
    D. Invalid
A
  1. D 4.3.5
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. At the discretion of the owner, if stipulated in the advertisement or invitation to bid, the properly
    identified bids received on time will be opened and will be read aloud.
    A. Publicly
    B. Privately
    C. After 3 days
    D. After 24 hours
A
  1. A 5.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. The owner shall, at the request of the bidder to whom award of a contract is under
    consideration and no later than days prior to the expiration of the time for withdrawal of bids, furnish to the bidder reasonable evidence that financial arrangements have been made to fulfill the owners
    obligations under the contract.

A. 30
B. 21
C. 14
D. 7

A
  1. D 6.2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. If the bidding documents require either a performance bond or a payment bond, the cost shall
    .

A. Not be included in the change order
B. Be included in the change order
C. Be added later to the bid in determining the contract sum
D. Be included in the bid

A
  1. D 7.1.2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. The bidder making a bid represents that he or she .
    A. Is familiar with local conditions under which the work is to be performed
    B. Is making a bid contingent on standard codes and conditions
    C. Will adjust accordingly if the bid is accepted as long as an addendum is made
    D. Will provide specifications for all materials
A
  1. A 2.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. The proposed contract documents consist of .
    A. The form of agreement between the owner and the contractor and instruction to bidders
    B. The conditions of the contract (general, supplementary and other conditions), drawings,
    specifications and all addenda
    C. Advertisement or invitation to bid, instructions to bidders, the bid form, and other sample
    bidding and contract forms
    D. All addenda or written, graphic instruments issued by the Architect prior to the execution of
    the
    contract
A
  1. B 1.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. A contractor furnished a bid on a project according to the provisions of AIA Document A701. The bid
    was received and accepted by the owner after the designated time and date required on the bidding
    documents for the receipt of all bids. The bidding documents required that the contractor furnish a
    performance bond and a payment bond. The contractor did not furnish a performance bond and a
    payment bond and, also refused to enter into a contract with the owner and withdrew the bid. The
    damages, if any, that can be assessed against the contractor by the owner are .

A. No penalty. A contractor can withdraw a bid at any time he/she chooses
B. The amount of bid security shall be forfeited to the owner as liquidated damages, as a penalty
C. A penalty equal to 2.0% of the bid price
D. The amount of bid security shall be forfeited to the owner as liquidated damages, not as a
penalty

A
  1. D 4.2.2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. An architect has issued addenda prior to bid due date. According to AIA Document A701, the architect
    must issue all addenda at least days prior to date for receiving all bids.
    A. 4
    B. 6
    C. 8
    D. 10
A
  1. A 3.4.3
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. The burden of proof of the merit for any proposed substitution of materials, equipment or
    products in the bidding documents is upon the
    .
    A. Architect
    B. owner
    C. Proposer
    D. Supplier
17
Q
  1. During the bidding process, where there is a discrepancy in the drawings or specifications, any
    corrections shall be made by .
    A. Instructions to bidders
    B. Addendum
    C. Change order
    D. Change directive
18
Q
  1. A bidder discovers that there is a discrepancy between the plans and the specifications. The
    bidder
    should .

A. Report it to the owner within seven days written notice
B. Talk to the other bidders
C. Ignore it
D. Report it to the architect immediately

19
Q
  1. Any performance bond or payment bond required in the bidding documents shall be delivered by
    the bidder to the owner not later than days following the date of execution of the contract.

A. 3
B. 5
C. 7
D. 10

20
Q
  1. The owner must prove financial capability no later than days prior to the expiration of
    the time for withdrawal of bids.

A. 3
B. 5
C. 7
D. 30

21
Q
  1. Any changes or corrections of the bidding documents must be made by the .
    A. General contractor
    B. Addendum
    C. Certified mail
    D. Phone call
22
Q
  1. AIA bids are received .
    A. In a sealed envelope
    B. By phone — bidder to contractor
    C. In a legal-size envelope
    D. All of the above
23
Q
  1. The bidder shall deliver the required bonds to the owner not later than days following
    the
    date of the execution of the contract.
    A. 1
    B. 3
    C. 5
    D. 7
24
Q
  1. The owner shall, at the request of the bidder to whom the award of a contract is under
    consideration,
    furnish reasonable evidence that financial arrangements have been made to fulfill the contract
    within
    days prior to expiration of the time for withdrawal of bids.
    A. 3
    B. 4
    C. 7
    D. 10
25
Q
  1. Bidders and sub-bidders requiring clarification of the bidding documents shall make a written
    request to
    the architect at least days prior to the date for receipt of bids.
    A. 3
    B. 5
    C. 7
    D. 10