AHPP - Chapter 9 - Design Project Delivery Flashcards

1
Q

key risk considerations for the owner:

A
  • can the project accomplish its goals withing the contraints of time and budget?
  • does the owner have the capability to understand the project and support the decisions necesart ti complete it?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

key risk considerations for the architect and archtiect’s consultants:

A

-can the project be accompleished within the standard for care at an acceptable level of quality, within the onwer’s parameters, the architect’s own capabilities and skill, and the strictures of the fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

key risk considerations for the contractor and contractor’s subcontrators:

A

-is ti possible to complete the project within a contracturally stipulated time frame and/or cost, given market cosiderations, availability of subcontractor, and the contractor’s experience and capabilites

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Primary players in the project delivery method:

A
  • the owner
  • the architect
  • design team consultants
  • the contractor
  • subcontractors, fabricators, and suppliers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

key variables affecting delivery choice

A
  • construction cost
  • schedule
  • building quality
  • project scope
  • risk
  • client capabilities
  • project team capabilites
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The characteristics that identify a delivery method can be defined by answering questions for the following issues:

A

1) driving factor: what is the most important outcome driving the rpoject for the owner – cost, risk , quality, or schedule?
2) architect’s role: what are the responsibilities of the architect, and how do ethese apply to each successive design and consruction phase of the project
3) contractor’s role: who is responsible for building the project, adn when in the process is that player selected
4) establishment of construction cost: when is the actual cost of construction definitely established contractually between owner and contractor
5) number and type of design and contruction contracts: ho wmany individual contracts for design and construction are necessary to accomplish the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

negotiated select team approach

A
  • variation of design-bid-build
  • contractor is selected early in the design process and certain contract terms (such as overhead and profit multipliers) for the contractor are determined prior to completion of construction documents
  • subcontractors are then selected and final constrcution team is assembled once construction docs are complete
  • final amount for construction is based on the final documents and calculated using pre-negotiated terms
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

cost plus fee

A
  • variation of design-bid-build
  • contractor is paid actual labor and material costs plus overhead for construction for coordination of trades on the site plus a fee that represents a fixed amount of profit that does of profit that does not vary according tot he total project cost, disconnecting the contractor’s profit from any increase in project cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

the construction manager (CM) can play one of three roles:

A

1) CM adviser
2) CM agent
3) CM Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

CM adviser

A
  • acts only as a constructablity and cost management consultant to the owner during the design and construction process
  • will not build anything
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

CM Agent

A

provides early consulting and may act on behalf of the owner in assembling and coordinating the construction trades prior tp and during construction

-CM agents typically provide services for a fixed fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

CM contractor

A
  • acts as constructability and cost adviser during design phase
  • at a pre-determined time, transistions to a traditional design-bid-build contractor
  • usually uses guaranteed maximum price (GMP)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

outline specifications

A
  • simple way to define building components at the schematic level
  • generlaly organized by CSI divisions
  • should include material descriptions and quality level
  • actual product data where possible
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

performance specs

A
  • describe products by how they perform tather than narrowly defining a manufacturer or material
  • works weel for techincally driven contractors (air handlers, chillers, transformers)
  • CMc can obtain pricing from contractors who specialize in the work described
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

narrative specifications

A
  • describe work in words rather than in drawings or in the more technical language of the CSI format
  • can describe finishes in the various rooms of the building without providing a complete room schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

true or false. Like a traditional GC, a CMc has no input on the design project schedule.

A

false

-CMc has the responsibility for developing and coordinating the overall project schedule, including design phases, owner decision milestones, and work periods that include design and drawing time