What is a protest?

A

A written objection by an interested party to any of the following:

(1) A solicitation or other request by an agency for
offers for a contract for the procurement of property or
services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Where is protest found in the FAR?

A

FAR part 33

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the three forums an interested party can file a protest?

A

Agency
Government Accountability Office (GAO)
US Court of Federal Claims

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the deadline for filing a protest to an agency?

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the deadline for filing a protest to the Government Accountability Office (GAO)?

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How long does an agency have to resolve a protest?

A

35 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How long does the Government Accountability Office (GAO) have to resolve a protest?

A

100 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How many days the contractor have to request a debriefing?

A

3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How many days does the government have to respond to a request for debriefing?

A

5 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is contract administration?

A

Activities performed by government officials after a contract has been awarded to determine how well the government and the contractor performed to meet the requirements of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Are post award orientations always necessary?

A

No, it depends on the requirement and the complexity of the requirement

Not needed for supplies

Encouraged to assist small business

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Alternative Dispute Resolution (ADR) also known as?

A

Partnering

Both parties need to agree

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is past performance information used for?

A

Future source selection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the excusable delays?

A

(1) acts of God or of the public enemy,
(2) acts of the Government in either its sovereign or contractual capacity
(3) fires
(4) floods
(5) epidemics
(6) quarantine restrictions
(7) strikes
(8) freight embargoes
(9) unusually severe
weather.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the objective of ADR procedures?

A

Involves the government and the contractor management staff mutually developing a “plan for success”

To increase the opportunity for inexpensive and timely resolutions of issues in contraversy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the time a contractor has to file a claim?

A

6 years

17
Q

What is the time a contracting officer has to render a final decision on a claim?

A

60 days