1534-Contract Closeout Flashcards
1
Q
What does timely contract closeout allow?
A
Deobligating excess funds
Identifies need for additional funds
Allows affected activities to concentrate on current and future requirements
2
Q
What are the Basic Contract Closeout Steps?
A
Government accepts final delivery
Government inputs final DD250 or SF1449
Validation of quantity ordered & delivered
Reconciliation between ordered and delivered items
Perform initial review and remove excess funds
Initiate DD Form 1597 and accomplish actions
3
Q
What is a contract closeout checklist?
A
DD Form 1597
4
Q
What is the DD 1594?
A
Contract Completion Statement