Q

What is the most preferred method of contract financing?

A

Performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why are performance based payments preferred over progress based payments?

A

Progress payments are administratively burdensome!

Using performance-based payments should result in lower administrative costs than progress payments based on cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the required customary progress payment NTE rates for DoD contracts, including contracts that contain foreign military sales (FMS)?

A

80 percent for large businesses
90 percent for small businesses
95 percent for small and disadvantaged businesses