7 : Plans Flashcards
There is a good deal of information in this theme and the questions are a good way to help you remember this. Like other themes, don’t worry about getting the answers exactly correct.
The Plans theme provides a framework to design, develop and maintain the project plans. Name 3 types of plan.
The three types of plans are the Project Plan, Stage Plan and Team Plans. There can also be an exception plan and a Benefits Review Plan.
The Plans theme provides a framework to design, develop and maintain what?
The Plans theme provides a framework to design, develop and maintain the project plans such as the Project, Stage & Team plans.
What is a plan? Answer in your own words.
A plan is a document that describes how, when and by whom a specific target or set of targets is to be achieved. You many think the target is just to create the project product but there will also be targets for time, cost, quality and benefits. So a plan is more than a Gantt chart.
What is considered to be the backbone of the project? It is created at the start of the project and continually updated during the project to show what has been done and what still needs to be done. It can be compared with the original document to see how well the project is progressing.
This is the project plan.
Fill in the blanks: Planning is the act or the process of ________ and _________ the plan.
Planning is the act or the process of making and maintaining the plan. You can also say creating and maintaining the plan. The Project Plan is created at the start of the project and is regularly updated during the project to show what has been done to date. The Stage Plans are created before the stage and updated to show what has been done during the stage.
Name the six project variables/six performance targets that planning helps to manage. (Tip: Think TeCQula SoBeR or BC QRST)
Planning helps to manage the six project variables, which are Time, Cost, Quality, Scope, Benefits and Risk.
Why cannot all plans be created at the start of the project? What does PRINCE2 recommend as a solution? Answer in your own words.
It is impossible to plan an entire project from the start unless it’s a very small project and it has a lot in common with a very small project that has been done before. It is only possible to accurately plan a short time in advance, e.g.: 0 to 8 weeks. This is known as the planning horizon. So PRINCE2 recommends having different levels of plan, which are linked, to the management levels in a project organization.
Name the three levels of management in a project team. Note: There is a plan type for each level.
The three management levels are: 1) Directing, 2) Managing and 3) Delivering.
Name the type of plan in each of the management levels of Directing, Managing and Delivering and mention when this plan is created.
Answer:
• The Directing Level used the Project Plan
• The Managing Level uses the Stage Plan
• The Delivery level used the Team Plan
• The Project Plan is created during the Initiating a Project process and is a high level plan for the whole project. It will show the major products of the project, when they will be delivered and the associated cost. It is a major control document for the Project Board.
• The Stage Plan is created for and before each stage and is used by the Project Manager. It is much more detailed than the Project Plan and just focuses on one stage.
• The Team Plans are created by the Team Manager in the Managing Product Delivery process.
Name one of the other plans that are created in the project besides the Project Plan, the Stage Plan and the Team Plan.
The other plan created during the project are the Benefits Review Plan which covers activities during the after the project and the exception plan.
Which plan is mainly used by the Project Board?
The Project Plan is a high level plan and mainly used by the Project Board.
What do the Project Board use to check how the project is progressing?
The Project Plan is always baselined at the start of the project, so the Project Board can compare this baselined plan to the current Project Plan at the end of each stage to see how the project is going compared to the original plan.
How does the Stage Plan differ from the Project Plan?
The Stage Plan is just for one Stage and it’s a lot more detailed that the Project Plan. The Stage Plan is used by the Project Manager on a day-to-day basis.
Who creates the Team Plans? Are they necessary?
The team plans are created by the Team Manager to plan the execution of one or more Work Packages. Team Plans and Team Managers are optional depending on the project’s size, complexity and the number of resources involved in creating the products. The Team Managers may create their Team Plans in parallel with the Project Manager when they create the Stage Plan.
How can a Project Manager be involved in the development of a Team Plan?
A project manager can ask to review the Team Plan and it is up to the Team Manager to decide to allow this.
Which plan is used to recover from the effect of tolerance deviation and if approved replaces the current plan? In other words it picks up from where the current plan had stopped.
This is the Exception Plan.
Is an Exception Plan created to replace a Work Package that goes out of tolerance?
There is no Exception Plan at the delivery management level. If a Team Manager forecasts that the work package will exceed tolerances they will raise an issue to the Project Manager. The Project Manager can take corrective action by updating the Work Package or creating a new Work Package to complete the work.