1 : PRINCE2 Introduction Flashcards

This is the Introduction to the Learn Thru Questions podcast. There are about 25 general questions and answers in this podcast. Please note that it is not important that you can answers each question exactly with the exact terms used in this podcast. What is more important is that you understand each answer and will be able understand and answer the multiple-choice questions in the Foundation exam.

1
Q

Who is the Manual “Managing Successful Projects with PRINCE2” designed for? Name 2 types of readers.

A

The Manual “Managing Successful Projects with PRINCE2” is designed for:
• People who wish to learn about project management and PRINCE2
• Experienced Project Managers who want to learn about PRINCE2
• And for PRINCE2 practitioners to use as a reference manual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Wikipedia provides a useful definition of a project. Try to complete this sentence. “A project is a unique series of actions designed to accomplish a _______.”

A

“A project is a unique series of actions designed to accomplish a unique goal within a specific time and cost. It is good to know this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Complete the following definition of PRINCE2 in your own words: “A project is a temporary organization that is created for the purpose of _______.”

A

A project is a temporary organization that is created for the purpose of delivering one or more business products according to an agreed business case.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In the PRINCE2 definition of a project what do you think is meant by the term “A temporary organization”?

A

Projects are temporary by nature. They have a certain start and end date. A project team is put together for the duration of the project and is dissolved at the end of the project. You can also refer to this project team as a Temporary Organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name some of the tasks that Project Management Deal with.

A

Project Management deals with planning, delegating, monitoring and control of the project; in other words the administration of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Finish the sentence: “Project Management is the planning, delegating, monitoring and control of all aspects of the project to achieve the project objectives within the expected performance target for ____.” (Tip: think of the 6 project variables)

A

Project Management is the planning, delegating, monitoring and control of all aspects of the project to achieve the project objectives within the expected performance target for time, costs, quality, scope, benefits and risks. These are known as the 6 project variables, which are managed throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is meant by the following sentence: “PRINCE2 separates the management layer from the specialist work.”? Explain with an example.

A

PRINCE2 provides a management layer to take care of decision making like approving the business plan and the project plan and giving authorization for a new stage to start. It does not matter if the project involves designing a new car, building an airport or it is a software project. The management structure will work in a similar way. See the process model for more information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is meant by the following statement: “PRINCE2 is principle based”?

A

This means that each project should be based on the 7 principles, so you should find the 7 principles in each project. If one of these is not there, it cannot be considered a PRINCE2 project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Try to list some of the 7 principles. Don’t worry about the exact names as you just have to recognize the names in the exam.

A
The 7 principles are:
• Continued business justification
• Learn from experience or Lessons Learned
• Defined roles and responsibilities
• Manage by stages
• Manage by exception
• Focus on Products – clear product descriptions
• Tailor to suit the project environment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Name some of the 6 variables that must be controlled in any project.

A

These are Cost, Timescale, Quality, Scope, Benefits and Risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Explain the variable Cost and why it needs to be controlled.

A

Projects have to give a return on investment, therefore costs need to be controlled and going over budget must be avoided.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Explain the variable Scope and why it needs to be controlled.

A

The project scope needs to be well defined and clear to all stakeholders. Care must be taken by the Project Manager to avoid scope-creep, which is to allow new requirements to be added during the project as this can kill a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Complete the following sentence: “PRINCE2 is a method that deals with the planning, delegation, monitoring and control of _____.”

A

PRINCE2 is a method that deals with the planning, delegation, monitoring and control of all six-project variables, which are Costs, Timescales, Quality, Scope, Risk and Benefits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Name the four elements of PRINCE2.

A

PRINCE2 has four integrated elements. These are Principles, Themes, Processes and Tailoring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which PRINCE2 element is referred to in the following sentence: “They are the 7 best practices that should exist in each PRINCE2 project.”

A

Principles.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which PRINCE2 element is referred to in the following sentence: “They are the items must be continually addressed during each project. E.g.: Business Case, Organization and Quality”

A

These are the PRINCE2 Themes elements.

17
Q

Which PRINCE2 element is referred to in the following sentence: “This element lists the activities that are done during the project. It lists the products that will be created and when they will be created.”

A

This is the PRINCE2 Processes element.

18
Q

What do you think is meant by the statement, “PRINCE2 does not provide Detailed Techniques”?

A

There are many techniques that can be used like Critically Path Analysis or how best to run a brainstorm workshop. PRINCE2 advises to use the techniques which suit your kind of project environment and it only describes a few such as Product based planning and Quality Review techniques.

19
Q

What do you think is meant by the statement, “PRINCE2 does not provide Leadership Capability”?

A

Leadership, Motivational and other soft skills are important for good project management, but there are many different kinds of leadership skills and styles. PRINCE2 advises to choose the best training that suits your environment. So PRINCE2 does not provide Leadership Capability.

20
Q

List 4 advantages of using a Project Management method like PRINCE2.

A

I will list 8 advantages here:

  1. Best Practice meaning that PRINCE2 has been used for over 30 years in many thousands of projects and PRINCE2 keeps learning from these projects.
  2. PRINCE2 can be applied to any kind of project, from running an election, organizing a conference, constructing a bridge, to an IT project and so on.
  3. PRINCE2 provides a structure for roles and accountability.
  4. PRINCE2 is product focused; meaning that the product is well defined at the start of the project and this is made known to all stakeholders.
  5. PRINCE2 uses Management By Exception, for example, it allows the project manager to handle certain project issues but once an issue goes beyond a certain tolerance it can be escalated to the project board.
  6. PRINCE2 continues to look at the viability of the project from a business case point of view throughout the project.
  7. PRINCE2 has a well defined structure for reports.
  8. PRINCE2 promotes learning and a continual improvement mindset. And there are more.
21
Q

Name one of the first plans that the Project Manager creates in the project which are based on the plan product description found in the Appendix A.16 of the PRINCE2 manual.

A

The first plans are:
1) The Initiation Stage Plan for the Initiation Stage,
2) The Project Plan for the whole project,
3) The Next Stage Plan for the first stage after the Initiation Stage and these are all based on the Plan product description.
The Benefits Review Plan is also created in the IP stage but it is based on the Benefits Review Plan Product description.

22
Q

Describe in your own words what the main objective of the Project Manager is.

A

The main objective of the project manager is to see that the project goes according to the project plan. They constantly monitor how well the work is going according to the project plan. The Project Manager will also monitor the 6 variables that are part of the any project which are Timescales, Costs, Quality, Scope, Benefits and Risk.

23
Q

Should the Project Manager also try to look for opportunities to speed up the project and reduce costs or ignore these opportunities and just focus on getting the project to run according to the plan?

A

They should look for opportunities to reduce costs and speed up the project.