2 : Principles Flashcards
It is more important that you understand each of the seven principles and recognize them when taking the exam.
What does the following statement mean: “PRINCE2 is principle based”?
This means that each PRINCE2 project should include the 7 principles and even if just one of the principles is missing, it can still be a project but it cannot be considered a PRINCE2 Project.
List about 3 or 4 of the 7 Principles. Don’t worry about getting the names 100% correct. I will list all 7 principles so you can compare.
The 7 principles are:
- Continue business justification – business case must exist throughout the project.
- Learn from experience – learn from lessons.
- Defined roles and responsibilities – everyone knows what is expected from them.
- Manage by stages – break projects into stages – easier to manage.
- Manage by exception – Allows the level below to get on with their work and inform above level if work will go out of tolerance.
- Focus on products – be clear and specific from the beginning of the project of what the project will deliver – so all stakeholders know what to expect from the project.
- Tailor to suit the project environment – don’t overload your projects with unnecessary administration.
How would you explain principles from a PRINCE2 point of view to another person? Answer in your own words.
I like to explain principles in the following way:
• Normally we say People have good principles like honesty, sincerity, trustworthy and we may like our friends or bank managers to have these principles.
• We can demand certain principles in our projects, like business case and defined product descriptions.
Other things we can say about principles are:
• Principles provide a framework of good project practice for those involved in a project.
• A Principle is a core value that must always exist in a PRINCE2 project.
• Principles are guides for good practice.
What is the name of the principle that deals with business reasons behind the project (in other words the business case)? Tip: First word begins with C.
This principle is Continued Business Justification.
In which document will you find Business Justification to start the project? This document becomes part of the Project Initiation Documentation.
In the Business Case document, this document is created in the Initiation Stage and it becomes part of the Project Initiation Documentation.
What should happen if during the project the business justification is no longer valid?
The project should be shut down, so the Project Board will instruct the Project Manager to close this project. This is also known as a Premature Close.
What does the principle Continued Business Justification prevent at the start of a project?
This principle prevents projects that have few real benefits for the company from starting.
When does the Project Manager check for Business Justification in the project, for example, that the business case is still valid?
The business justification is checked throughout the lifetime of the project. This is done first at the start of the project to make sure the project is worth doing and then at the end of every stage. The end of every stage is a good time as the Project Manager provides the End Stage Report, overview of Risk and information that affects the business case to the Project Board.
What is the name of the principle that deals with Lessons Learned?
Learn from Experience. So learn from previous projects and other information that is available.
As projects are unique by nature, what should the people involved at the start of a project do to reduce risks and unknowns and not make the same mistakes as previous projects?
PRINCE2 says that all stakeholders should take the initiative to seek lessons learned. This will help to decrease the unknowns and provide more information on risks. So it is not just up to the Project Manager but all the stakeholders.
According to PRINCE2, who has the responsibility to seek lessons learned?
PRINCE2 states that seeking lessons learned is a responsibility for everybody involved in the project.
What do you think should happen if there were no or insufficient similar projects that the project team can learn from within their organization?
They should then look for outside help, e.g.: consulting, reports, trade information, visit other companies that may have done similar projects, etc…
PRINCE2 states that Lesson Learned covers the complete lifecycle of the Project. There are 3 phases for lessons – at the start of the project, during the project and at the end of the project. Can you list what the Project Manager & Stakeholders may do in these parts?
- Starting Up a Project, Looking outside for useful Lessons Learned and the Project Manager adds them to the Lessons Log
- As the Project Progresses: identify new lessons learned to the Lesson Log
- As the Project Closes, you can pass on lessons to the next project in the Lesson Report
What is the name of the principle that deals with Roles & Responsibilities?
The principle name is “Defined Roles & Responsibilities”.
What is the key question that this principle “Defined Roles and Responsibilities answers”?
It answers the question “What is expected from me” or “What is expected from everybody in the project”. Everyone connected to the project should know their role and this should be decided at the start of the project.