5th week / estimating cost Flashcards
Factors influencing the quality of estimates
95 % probability meeting time and cost
past experience is a good starting point to for developing time and cost estimates
Factors related with the uniqueness of the project
Project, people, and external factors
PLANNING HORIZON
Quality depends on
PROJECT DURATION
long-duration increase uncertainty of estimates
PEOPLE
People skills
whether people have worked before already influences the time to become effective team
PROJECT STRUCTURE AND ORGANIZATION
PADDING STIMATES
increase probability and reduce risk
ORGANIZATION CULTURE
OTHER FACTORS
Estimating guidelines for time and costs and resources
7 guidelines to develop useful work packages estimates
- Responsibility
Draw on Most familiar with the task
Build communication channels earlier - use several people to estimate
- Normal conditions
should be based on normal conditions, efficient
methods, and normal level of resources - Time units
All time estimates need consistent time units
calendar
days, workdays, workweeks, person days, single
shift, hours, minutes, etc.
5.Independence
Estimators should treat each task as independent of other task in the WBS
- Contingencies
Work package should not include allowances for
contingencies - Adding risk assesment to the estimate helps to avoid surprises to stakeholders
Top Down vs Bottom up estimating
Top down estimates
derived from someone whose uses expertise to determine project duration and total cost
Bottom up approach
Work package level
Rolling up the work packages
later///time phased networks
methods for estimating Project time and cost
Top-down approaches for estimating project time and cost
- Consensus method
director experience.. Delphi method - Ratio methods
i.e contactor square feet to stimate cost and time
build a house - Apportion methods
extension ratio.. - Function Point methods for software and simple
Projects - Learning curves
Each time the output quantity doubles, the unit labour hours are reduced at a constant rate
methods for estimating Project time and cost
Bottom-up approaches or estimating project time and cost
- Template methods
Use other past projects - Parametric procedures applied to specific task
- Range estimation
using a person most familiar with the package is the
best approach - Hybrid Phase estimation
Type of costs
Direct cost
- labour
- material
- Equipment
- Other
Direct Project Overhead costs
Advertising, accounting, senior manager above the prject
General and administrative overhead costs
Refining estimates
interaction costs are hidden in estimates
Normal conditions do not apply
Things go wrong in projects
Changes in project scope and plans