2013 Flashcards

1
Q

Given the following conditions:
• The BOP operator reports a degrading vacuum in the main condenser.
• The CRS has entered 40AO-9ZZ07, Loss of Condenser Vacuum.
Subsequently
• The Reactor is tripped due to the degrading vacuum.
• Alarm window 6A16B, SBCS COND INTLK, has annunciated.
• Alarm window 6A16D, COND VAC LO has annunciated.
• Condenser backpressure is 14.0” HgA (all shells).
What actions are required to control the listed secondary parameters?
Steam Generator level can be maintained by (1)
RCS temperature can be maintained by (2)

A. (1) AFW only (2) ADVs only
B. (1) AFW or MFW (2) ADVs only
C. (1) AFW only (2) ADVs or SBCVs
D. (1) AFW or MFW (2) ADVs or SBCVs

A

A Wrong AFW is correct but SBCVs 7 and 8 are not effected by the interlock since they go to
atmosphere
B Wrong MFW trips at 13.5 inches
C Correct MFW turbine trips at 13.5 inches and Tcold can be controlled by either SBCVs 7 & 8
or ADVs.
D Wrong MFW pump turbine trips at 13.5 inches.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Given the following conditions:
• PZR pressure is 1345 psia and slowly lowering.
• PZR level is 60% and slowly rising.
• RCS temperature is 562°F and stable.
• SIAS/CIAS/MSIS have been manually actuated on trend.
• RCPs 1A and 2A were stopped as directed by the Standard Post Trip Actions.
• Containment pressure is 2.8 psig and slowly rising.
• Containment temperature is 140°F and slowly rising.
• HPSI train “A” valves have been throttled.
• RDT pressure is 2.8 psig and rising.
The event in progress is a (1) and the crew must (2) .

A. (1) RCS cold leg break
(2) stop the 1B and 2B RCPs and raise HPSI flow
B. (1) RCS cold leg break
(2) throttle HPSI train “B” valves to control pressurizer level
C. (1) Pressurizer steam space leak
(2) stop the 1B and 2B RCPs and raise HPSI flow
D. (1) Pressurizer steam space leak
(2) throttle HPSI train “B” valves to control pressurizer level

A

A Wrong A LOCA is occurring but it is through the Pzr not a cold leg. Stopping the RCPs
and raising HPSI flow is correct for the loss of subcooling margin, ~21°F. RCS
cold leg break is credible because lowering PZR pressure (1st bullet), manual
initiation of SIAS/CIAS/MSIS (4th bullet), increasing CNTMT pressure (6th bullet),
and increasing CNTMT temperature (7th bullet) support this diagnosis.

B Wrong A LOCA is occurring but it is through the Pzr not a cold leg. May think that
throttling HPSI is correct since Pzr level is raising. RCS cold leg break is credible
because lowering PZR pressure (1st bullet), manual initiation of SIAS/CIAS/MSIS
(4th bullet), increasing CNTMT pressure (6th bullet), and increasing CNTMT
temperature (7th bullet) support this diagnosis.

C Correct The event in progress is a Pzr Steam space leak as indicated by increasing
Pzr and RDT levels with increasing containment temps and pressure.
Stopping the RCPs and raising HPSI flow is correct for the loss of
subcooling margin, ~21°F.

D Wrong The event in progress is a Pzr Steam space leak as indicated by increasing Pzr
and RDT levels with increasing containment temps and pressure. May think that
throttling HPSI is correct since Pzr level is raising.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Given the following conditions:
• Unit 1 is operating 100% power.
• A 5.0 gpm RCS leak has developed.
When using the ERFDADS Leakrate Program to monitor leakrate, indicated leakrate will be….
A. less than actual leakrate for at least 7.5 minutes.
B. less than actual leakrate for at least 15 minutes.
C. greater than actual leakrate for at least 7.5 minutes.
D. greater than actual leakrate for at least 15 minutes.

A

A Correct Leakrate will take 7.5 minutes to reach and stabilize at the current leakrate if
examinee does not understand the process they may think it works like the
algorithm which goes high then comes down to the actual leakrate.
C Wrong Leakrate will take 7.5 minutes to reach and stabilize at the current leakrate
B Wrong Examinee may choose the 15 minute distracter since is the procedural guidance
D Wrong on how long to let the program run before reporting leakrate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Given the following conditions:
• Unit 1 automatically tripped from 100% power.
• RCS T-cold is 558°F and slowly lowering.
1. Which ONE of the following would be the first to satisfy an Entry Condition for 40EP-9EO03,
Loss of Coolant Accident?
2. Given those conditions, identify the required action(s).
A. 1. Pressurizer pressure is 1820 psia.
2. Immediately trip all 4 RCPs if not already secured.
B. 1. Pressurizer pressure is 1847 psia.
2. Immediately trip all 4 RCPs if not already secured.
C. 1. Pressurizer pressure is 1820 psia.
2. Check that SIAS is actuated.
D. 1. Pressurizer pressure is 1847 psia.
2. Check that SIAS is actuated.

A

A Wrong Part 2 is wrong the trip 2/ Leave 2 should be used but the requirements to trip 4
RCPS (< 24°F or CS flow) have not been met. Plausible because part 1 is
correct and securing 4 RCPs criteria is identified in the LOCA procedure.
B Wrong Part 1 is wrong because this is above the automatic SIAS setpoint of 1837 psia.
Part 2 is wrong the trip 2/ Leave 2 should be used but the requirements to trip 4
RCPS (< 24°F or CS flow) have not been met. Plausible because part 1 is
similar to the actual SIAS setpoint of 1837 psia and securing 4 RCPs criteria is
identified in the LOCA procedure.
C Correct 1820 psia is below the SIAS automatic setpoint of 1837 psia for LOCA
entry.
Per 40EP-9EO03:
1.0 ENTRY CONDITIONS
1. The Standard Post Trip Actions have been performed. or
BOTH of the following conditions exist:
• A LOCA initiated from Mode 3 or Mode 4
• LTOP is NOT in service and
2. Plant conditions indicate that a Loss of Coolant Accident has occurred. ANY
or all of the following may be present:
• Pressurizer level low (for a break in the pressurizer, the level may be high)
• SIAS automatically actuated
• Rise in containment pressure, temperature, radiation, humidity, and level
• High Reactor Drain Tank level, temperature, or pressure
D Wrong Part 1 is wrong because this is above the automatic SIAS setpoint of 1837 psia.
Plausible because part 1 is similar to the actual SIAS setpoint of 1837 psia.
Also plausible because Part 2 is correct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Given the following conditions:
• Unit 1 was manually tripped from 100% power
• All 4 RCPs were secured due to a loss of Nuclear Cooling Water.
Assuming no additional Operator actions, which one of the following represents the operational
implications of this condition?
A. Low Tave will require manual control of SBCS due to Quick Open block being
generated
B. High Tave will require manual control of the SBCS due to overcooling if left in
automatic control
C. Low Tave will require manual Feedwater control due to the low Refill demand
while in Reactor Trip Override
D. High Tave will require manual Feedwater control due to the high Refill demand
while in Reactor Trip Override

A

A Wrong Group X QO block would be generated if Tave is < 573.5 degrees. Quick Open is
blocked on low Tave. Both parts are wrong.
B Wrong Tave will go high but SBCS operates on Tcold which will be maintained on
program
C Wrong Low temp would cause low refill demand but in this case Tave goes high
D Correct
With a constant Tcold, Thot will elevate when Natl Circ is being established.
higher than normal Tave will cause RTO to feed excessively requiring Opera
to take manual control of Downcomers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Given the following conditions:
Initial Conditions:
• Unit 1 is in Mode 5.
• RCS level is 103 feet 6 inches.
• RCS temperature is 140ºF.
• LPSI pump B is providing Shutdown Cooling flow at 4500 gpm.
Current Conditions:
• RCS level has slowly dropped to 102 feet 8 inches.
• LPSI pump B amps are oscillating.
• Shutdown Cooling flow is oscillating.
Which ONE of the following actions is directed by the Lower Mode Functional Recovery
Procedure?
A. Run LPSI and CS pumps in parallel to lower RCS temperature.
B. Reduce LPSI pump B flow to minimize vortexing at the pump suction.
C. Shift SDC to CS pump B due to its lower suction pressure requirements.
D. Place LPSI pump A in service and vent the B SDC train to remove entrapped
gases.

A

A Wrong This may help lower temperature eventually but would further lower LPSI pump
suction pressure
B Correct Reducing flow would increase LPSI pump suction pressure and reduce
vortexing and is directed by HR-2
C Wrong CS pump B has higher pressure and temperature requirements when placed on S
Examinee may confuse this with lower suction pressure requirements
D Wrong This may be done eventually but with lowering level it is not directed to swap train
the reason for the lowering level is determined

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Given the following conditions:
• Unit 1 had been operating at 100% power.
• A manual reactor trip was initiated due to lowering pressurizer level and pressure.
• Standard Post Trip Actions are being performed.
• No manual operator actions have been taken.
• All 8 RCP “LO NCW FLOW” alarm windows on B04 have actuated.
Which ONE of the following conditions would have caused these alarms?
A. 8.5 psig in containment.
B. 1837 psia in the pressurizer.
C. Refueling Water Tank level has lowered to 9.4%.
D. High alarm on RU-6 (Nuclear Cooling Water radiation monitor).

A

A Correct NCW valves isolate on CSAS signal 8.5 psig in containment
B Wrong 1837 psia initiates a SIAS/CIAS – starting SI pumps and closing Containment
Isolation valves
C Wrong 9.4 % initiates RAS which stops LPSI pumps and closes SI miniflow valves
D Wrong This alarm is associated with RCS leakage into the NCW system via RCP
Cooling. Examinee could believe that this RU has auto actions as some others
like RU-29/30 (CREFAS), RU-31/145 (FBEVAS) and RU-141 (thru filter mode).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Given the following initial conditions:
• Unit 1 is operating at 100% power.
• Pressurizer pressure is 2250 psia and stable.
• Pressure Master Controller, RCN-PIC-100, output is currently 16%
Subsequently:
• Pressure Master Controller, RCN-PIC-100, slowly fails to 100% output.
Main spray valves, RC-100E and RC-100F will respond by going from full…
A. closed at 33% output to full open at 50% output.
B. open at 33% output to full closed at 50% output.
C. closed at 50% output to full open at 100% output.
D. open at 50% output to full closed at 100% output.

A

A Correct PPCS operates from 33 to 50% output for spray control 􀍲􀍲 closed to open
B Wrong This controller is reverse acting such that more output lowers RCS pressure. Because it
controls both the spray and heater output, it is plausible that with a greater output
spray valves could be going closed
C Wrong Controller range is 0 – 50% output but the controller output uses the entire range of 0
D Wrong – 100% making C and D plausible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
• RCP 1A has tripped.
• All 4 PPS channels SG-1 “LO FLOW” have actuated.
• Leg 1-3 phase current lights are extinguished.
• Leg 2-4 phase current lights are illuminated.
Which ONE of the following is correct regarding the status of the Reactor Trip Switchgear (RTSG)
breakers and actions to trip the reactor?
A. At least one RTSG breaker has opened and only NGN-L10 must be tripped to
de-energize the CEDMCS bus.
B. At least one RTSG breaker has opened and both NGN-L03 and L10 must be
tripped to de-energize the CEDMCS bus.
C. At least two RTSG breakers have opened and only NGN-L10 must be tripped to
de-energize the CEDMCS bus.
D. At least two RTSG breakers have opened and both NGN-L03 and L10 must be
tripped to de-energize the CEDMCS bus.

A

A Wrong One RTSG breaker is correct but if the examinee applies electric bus logic they
may believe that L03 supplies the A/C train and L10 supplies the B/D train.
B Correct This light would be out with either the B or D RTSG being tripped and both
L03 and L10 must be tripped to de-energize the CEDMCS bus.
C/D Wrong Due to the setup of the RTSG breakers one phase current light out only ensures
that one RTSG breaker has opened in the extinguished loop. The examinee may
associate the phase light with both breakers being tripped.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Following a reactor trip Unit 1 has the following conditions:
• Pressurizer pressure is 1600 psia and increasing.
• PZR level is 28% and increasing.
• Containment pressure is 0.3 psig and stable.
• SG #1 pressure is 1090 psia and stable.
• SG #2 pressure is 1100 psia and stable.
• SG #1 level is 70% WR and rising.
• SG #2 level is 60% WR and stable.
• RCS T-cold is 560°F and slowly lowering.
• Containment temperature is 90°F and stable.
• HPSI flow is 150 gpm to each loop.
• SIAS/CIAS have initiated.
The CRS has come to the step in the Emergency Operating Procedure regarding throttling HPSI
flow and finds the following:
CAUTION
Throttling HPSI injection valves will cause erosion damage to downstream piping
The correct mitigating EOP for these conditions is (1) and throttling HPSI injection valves to
lower HPSI flow (2) .
A. (1) LOCA (2) is permitted but should be avoided.
B. (1) SGTR (2) is permitted but should be avoided.
C. (1) LOCA (2) is only permitted by fully closing the HPSI valves.
D. (1) SGTR (2) is only permitted by fully closing the HPSI valves.

A

A Wrong NO change in Cntmt parameters = not a LOCA
B Correct Full closed is preferred but throttling is permitted based on plant conditions
C Wrong NO change in Cntmt parameters = not a LOCA
D Wrong The tech guide states that throttling is permitted based on plant conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Given the following conditions:
• Unit 1 tripped from 100% power.
• SIAS/CIAS and AFAS-1 have automatically initiated.
• Steam Generator #1 pressure is 745 psia and lowering.
• Steam Generator #1 level is 8% WR and lowering.
• Steam Generator #2 pressure is 760 psia and lowering.
• Steam Generator #2 level is 30% WR and lowering.
• Auxiliary feedwater flow is 1800 gpm to steam generator #1.
• Auxiliary feedwater flow is 0 gpm to steam generator #2.
Which ONE of the following is the correct condition and proper Operator actions?
A. MSIS has failed. Initiate a manual MSIS immediately.
B. AFAS-2 has failed. Initiate a manual AFAS-2 immediately.
C. MSIS has failed. Obtain CRS permission, then immediately initiate an MSIS.
D. AFAS-2 has failed. Obtain CRS permission, then immediately initiate an AFAS-2.

A

A Correct MSIS setpoint of 955 psia has been exceeded the operator is required to
initiate ESFAS actions that have failed. Initiation of failed automatic
emergency systems is a license requirement for Reactor Operators.
B Wrong AFAS setpoint of 25% WR has not been exceeded
C Wrong MSIS setpoint of 955 psia has been exceeded the operator is required to initiate
ESFAS actions that have failed not wait for CRS permission.
D Wrong AFAS setpoint of 25% WR has not been exceeded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Given the following conditions:
• Unit 1 has tripped from 100% power.
• An inadvertent “A” train SIAS occurred following the trip.
• The CRS has diagnosed a LOAF (Loss of all Feed).
• The CRS directs you to start AFN-P01, Start-Up Aux Feedpump.
• AFN-P01 suction valves CTN-HV-1 and 4 are both open.
• You have gone to “START” one time using its handswitch (AFN-HS-11).).
Which ONE of the following is correct, AFN-P01 is …
A. running and feeding both Steam Generators.
B. running but not feeding either Steam Generator.
C. not running, AFN-P01 can be started by going to “STOP” then “START”.
D. not running, AFN-P01 can be started by going to “START” one more time.

A

A Wrong This would be the option normally; this pump has no auto start feature so going to
start is plausible answer. Will not start due to the SIAS actuation blocking the starting
circuit.
B Wrong
C Correct Going to stop will pick up the SIAS OR then going to start again will start the pump.
D Wrong This would be the correct action for resetting an 86 lockout condition so the examinee
may choose this option.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Given the following conditions:
• Unit 1 tripped from 100% power due to a loss of offsite power.
• DG “A” is under clearance for planned maintenance.
• The RO reports that Essential Spray Pond Pump “B” has both a white and blue light
illuminated on the SESS panel.
1. What is the appropriate EOP to enter?
2. What is the required action and reason for that action?
A. 1. 40EP-9EO07, LOOP/LOFC
2. Place all the charging pump handswitches in Pull to Lock to prevent an
uncontrolled restoration of RCP seal injection.
B. 1. 40EP-9EO07, LOOP/LOFC
2. Isolate Seal Injection to prevent a rapid cooldown of the RCP seals.
C. 1. 40EP-9EO08, Blackout
2. Place all the charging pump handswitches in Pull to Lock to prevent an
uncontrolled restoration of RCP seal injection.
D. 1. 40EP-9EO08, Blackout
2. Isolate Seal Injection to prevent a rapid cooldown of the RCP seals.

A

A Wrong Candidate is given the Loss of Offsite power, if they do not recognize that the
SESS panel is telling them that DG ‘B must be secured they may stay in
LOOP/LOFC procedure. LOOP is a credible choice.
B Wrong
C Correct Candidate must determine that the Blackout procedure must be entered
due the loss of Spray Pond flow to DG “B”. Charging pumps are placed in
PTL to prevent the uncontrolled restoration of RCP seals as stated in the
BO tech guide.
D Wrong Blackout is correct but the reason given is a correct action and condition from
the LOOP procedure making this a credible distracter.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Referring to the provided picture of Board 1, which ONE of the following describes the status of the
electric plant? (No operator actions have been taken)
A. Normal full power lineup.
B. DG “B” is in test run paralleled with offsite power.
C. DG “B” is in emergency run providing power to PBB-S04.
D. DG “B” is running due to only an AFAS, SIAS or CSAS actuation.

A

A Wrong The breaker from NBN􀍲X04 is open this is the normal power supply to PBB􀍲S04.
B Wrong DG is tied to PBB􀍲S04 but it is not connected to offsite power.
C Correct With offsite power disconnected, DG “B” is in emergency run to energize PBB􀍲S04
D Wrong AFAS/SIAS/CSAS start the DG but do not energize the PBB􀍲S04

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
• A fault occurs on PKA-M41 and the Class DC bus is de-energized.
With no operator action, which ONE of the following describes the expected condition of the “A”
train Instrument Inverter, PNA-N11 and Instrument Bus, PNA-D25?
The AC output breaker on PNA-N11 is (1) and PNA-D25 is (2) ?
A. (1) open (2) energized
B. (1) closed (2) energized
C. (1) open (2) de-energized
D. (1) closed (2) de-energized

A

A Wrong PNA-D25 would be energized in Units 2 and 3 but not U-1
B Wrong
C/D Wrong PNA-D25 will be de-energized due to NO auto transfer capability in U-1 but
the AC output breaker opens on high amp output not on a DC low voltage
supply

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Given the following conditions:
• Unit 1 has tripped from 100% power due to a Loss of Offsite Power (LOOP) event.
• The crew has cross connected Essential Cooling Water (EW) system “A” to Nuclear Cooling
Water per Standard Appendix 63.
Which ONE of the following describes the reason for throttling closed EWA-HCV-53 (SDCHX ‘A’
Outlet Isolation) to a minimum EW system flow of 8500 gpm or until the RCP LO NC FLOW alarms
are clear?
A. Maintain operability of the EW “A” system.
B. Provide the NCW priority loads with adequate flow.
C. Ensure adequate flow to the Fuel Pool Heat Exchangers.
D. Prevent EW pump damage due to operating in a runout condition.

A

A Wrong EW is INOP when cross tied. Examinee may think throttling flow will maintain
operability
B Correct This is to ensure adequate flow to NCW priority loads.
C Wrong One train of EW not sized to provide both NCW and Fuel Pool cooling; this would
require aligning the other train.
D Wrong Not for runout but examinee could believe this to be true when taking systems out
of normal alignment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
• A grid disturbance has caused grid voltage to drop.
• Grid frequency is stable at 60 Hz.
• The Main Generator is responding per design.
Which ONE of the following would be an operational implication of this condition?
The Main Generator…
A. could lose synchronism (pole slippage). The Maximum Excitation Limit (MEL)
circuit will act to mitigate the over-excitation condition.
B. field could be damaged due to overheating. The Maximum Excitation Limit (MEL)
circuit will act to mitigate the over-excitation condition.
C. field could be damaged due to overheating. The Underexcited Reactive Ampere
Limit (URAL) will act to mitigate the under-excitation condition.
D. could lose synchronism (pole slippage). The Underexcited Reactive Ampere
Limit (URAL) will act to mitigate the under-excitation condition.

A

A Wrong Pole slippage is indicative of under􀍲excitation in this case the generator will act to raise
voltage and cause over􀍲excitation
B Correct With a low voltage the AC regulator will attempt to raise voltage the MEL circuits will
act to limit the increase and activate a trip timing circuit if voltage goes beyond limits
C Wrong Part one is correct but URAL is for under􀍲excited conditions
D Wrong Both parts are wrong but these are plausible conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Given the following conditions:
• Unit 1 was at 15% power.
• Reg Groups 4 and 5 CEAs began moving OUT uncontrollably.
• The CRS implemented 40AO-9ZZ11, CEA Malfunctions.
• CEDMCS was placed in “STANDBY.”
• The cause of the malfunction has been corrected and CEAs can be moved..
• THREE (3) CEAs in Reg Group 4 are now deviating from other CEAs in the group by less
than 6.6 inches.
• The CRS directs the RO to align the CEAs to the group.
Referring to the attached MCB picture, which ONE of the following identifies the switch
manipulations required by the RO to realign the CEAs?
A. INDIVIDUAL CEA SELECTION switch ONLY.
B. GROUP SELECT and MODE SELECT switches ONLY.
C. GROUP SELECT, MODE SELECT, and INDIVIDUAL CEA SELECTION
switches ONLY.
D. GROUP SELECT, PS GROUP SELECT, MODE SELECT, and INDIVIDUAL
CEA SELECTION switches.

A

A Wrong Must also manipulate MODE SELECT, and INDIVIDUAL CEA SELECTION
switches. Plausible because this is one of the switches required to realign the
CEAs.
B Wrong Must also manipulate INDIVIDUAL CEA SELECTION switch. Plausible
because these two switches are required to realign the CEAs.
C Correct GROUP SELECT must be changed from 5 to 4.
MODE SELECT must be changed from SB to MI.
INDIVIDUAL CEA SELECTION must be changed to the three different CEAs
to maintain a maximum of 2 step overlap.
D Wrong PS GROUP SELECT is NOT required to be manipulated. Plausible because
this is one of the four switches used to manipulate CEAs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Given the following plant conditions:
• An event has occurred that requires an emergency boration.
• The crew has established a boration through CHN-UV-514, Boric Acid Makeup to
Charging Pumps, with a Boric Acid Makeup pump running.
Subsequently
• NHN-M1528, power to CHN-UV-514, trips open.
• CHN-LT-227, VCT level transmitter, fails LOW.
• CHN-LI-226, VCT Level, reads 48%.
Which ONE of the following describes the impact of these conditions on the emergency boration
flowpath?
A. The crew must manually open CHE-UV-514 to establish an emergency boration
flowpath.
B. The crew must manually open CHE-HV-536 to establish an emergency boration
flowpath.
C. The emergency boration flowpath will be maintained through a single suction
flowpath (via CHN-UV-514) to the charging pumps.
D. The emergency boration flowpath will be maintained through two suction
flowpaths (via CHN-UV-514 and CHN-HV-536) to the charging pumps.

A

A Wrong Incorrect because CHE-HV-536 will automatically open on a Low-Low VCT
level, coincident with a loss of power to CHN-UV-514, to maintain an
emergency boration flowpath. See Page 77 of the PVNGS Operator
Information Manual. Plausible because CHE-UV-514 is a “fail-close” valve
B Wrong Incorrect because CHE-HV-536 does not need to be manually opened. It will
automatically open on a Low-Low VCT level, coincident with a loss of power to
CHN-UV-514. Plausible because CHE-HV-536 may be manually opened under
certain conditions in 40AO-9ZZ01.
C Wrong Incorrect because when CHE-HV-536 opens, there will be a parallel suction
path to the charging pumps since CHN-UV-514 is already open per 40AO-
9ZZ01. Plausible because, under most circumstances in 40AO-9ZZ01, there is
a single suction source to the charging pumps.
D Correct CHN-UV-514 is open per the given conditions. When power is lost to
CHN-UV-514, it will remain open since it is an MOV. Also, CHE-HV-536 will
automatically open on a Low-Low VCT level, coincident with a loss of
power to CHN-UV-514. This will result in parallel suction flowpaths to the
charging pumps.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

The Functional Recovery Procedure directs feeding a ruptured and faulted Steam Generator at
1360 - 1600 gpm.
Which ONE of the following describes the primary purpose of this action?
A. Rapidly depressurize the RCS.
B. Rapidly depressurize the affected SG.
C. Reduce the associated radioactive release.
D. Equalize pressure between the SG and the RCS.

A

A Wrong This action would help to depressurize the RCS. Depressurizing the RCS is one
of the actions to help stop the spread of contamination found in the FRP,
making this answer plausible.
B Wrong This action will depressurize the SG making it plausible.
C Correct This action is taken due the loss of Containment Integrity to limit the
radioactive release.
D Wrong Incorrect because equalizing pressure is not the reason for establishing 1360-
1600 gpm AFW flow. Plausible because equalizing pressure is one of the goals
for a SGTR.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Given the following plant conditions:
• Unit 3 is in a Refueling Outage.
• The Containment LSRO is in the process of loading a fuel bundle into the core.
• The count rate on Startup Channel #1 increases by a factor of 5.
• The count rate on Startup Channel #2 increases by a factor of 3.
• No RMS alarms or trends are present in the Control Room.
Which ONE of the following is the correct required response to this event?
A. Withdraw the last inserted fuel assembly and observe Startup Channel response.
B. Stop all fuel movement and order an evacuation of non-essential personnel from
containment.
C. Stop all fuel movement and initiate a CPIAS, Containment Purge Isolation
Actuation Signal.
D. Fuel movement may continue provided that the Operability of Startup Channel #2
is confirmed.

A

A Correct Per 72IC-9RX03, Core Reloading, Step 6.2.21.4:
IF during insertion of a fuel assembly, the sustained count rate from either
startup channel increases by a factor of five (5) from the last stable counts,
excluding anticipated changes due to spatial effects, THEN withdraw the
fuel assembly immediately.
Lesson Plan NKA02C021601, Refueling Operations, Page 19:
If during insertion of a fuel assembly the neutron count rate from either
startup nuclear channel increases by a factor of five from the last counts
stable value, excluding anticipated changes due to spatial effects (such as
insertion of an irradiated fuel assembly near a detector), immediately
withdraw the fuel assembly and observe the startup channel response.
B Wrong An evacuation is not required in 72IC-9RX03, Core Reloading. Plausible since
evacuate may be called for in other fuel handling procedures, such as
40AO-9ZZ22, Fuel Damage. Also plausible because 40OP-9ZZ23, Outage
GOP, contains evacuation guidance in Appendix G - Containment Evacuation.
40OP-9ZZ23 is applicable under the conditions of the stem.
C Wrong Incorrect since fuel movement is not immediately stopped. The last assembly
must be immediately removed.
D Wrong Incorrect since confirmation on both channels would not mitigate the conditions.
Plausible because confirmation of a similar indication on the other channel is
addressed in Step 6.2.21.6 of 72IC-9RX03 as follows:

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Given the following conditions:
• A lowering vacuum condition has caused the Operating Crew to enter 40AO-9ZZ07, Loss of
Condenser Vacuum.
• The Secondary Operator has transferred load to steam dump valves 1007 and 1008.
• Main Generator output is approximately 600 MWe.
• An Area Operator reports that air is being drawn past the vacuum breaker for the ‘B’ Condenser
Shell and they are unable to fill it with water.
• Vacuum continues to degrade and passes 7” HgA.
Based on these conditions, the Operating Crew should…
A. trip the Reactor.
B. reduce Turbine load to 410 MWe
C. initiate a RPCB to rapidly reduce Turbine load.
D. trip the Turbine and continue efforts to correct the problem.

A

A Correct Per 40AO-9ZZ07, Appendix F, Reactor Trip Criteria:
CONDITION 1
BOTH of the following conditions are met:
• Condenser pressure > 7 inches HgA and rising in any shell
• Main Generator sync’d to the grid
IF ANY of the conditions exist,
THEN trip the Reactor and GO TO 40EP-9EO01, Standard Post Trip Actions.
B Wrong Incorrect because, under these conditions, a Reactor trip is required. Plausible
because lowering load is an action taken in 40AO-9ZZ07 and 410 MWe is part of
Condition 4 Reactor trip criteria in 40AO-9ZZ07, Appendix F; and it is part of
Turbine trip criteria in 40AL-9RK6A, Window 6A16D.
C Wrong Incorrect because, under these conditions, a Reactor trip is required. Plausible
since an RPCB is one method of quickly reducing plant load. Also plausible
since plant load may be reduced via a RPCB during a condenser tube leak.
D Wrong Per 40AO-9ZZ07, Appendix F, Reactor Trip Criteria, the correct action is to trip
the Reactor. Plausible since the Diagnostics page would require a Main Turbine
trip if power was less than 12%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Given the following conditions:
• The Unit 3 Control Room has been evacuated due to a FIRE.
• The CRS is implementing 40AO-9ZZ19, Control Room Fire.
• The RO has been directed to perform Appendix A, Primary Reactor Operator Actions.
Which ONE of the following describes the operational impact after Appendix A is complete?
A. EDG ‘A’ will be running.
B. ALL charging pumps will be secured.
C. Spurious operation of MSIVs will be prevented.
D. Local operation of Train ‘A’ equipment will be isolated from the Control Room.

A

A Wrong The action is to secure, not to start EDG ‘A.’ Plausible because DGs are
evaluated in 40AO-9ZZ19.
B Wrong CCP ‘B’ is to remain in operation to ensure seal injection to the RCP seals.
Plausible because Charging Pumps A & E are secured in Appendix B (Steps 7 &
8) in 40AO-9ZZ19. Additionally, plausibility is established since Charging Pump
B breaker is opened in Appendix E (Step 7) of 40AO-9ZZ19; it is then reclosed in
Step 17. Under the given conditions, Appendix E will not be performed.
C Correct This is accomplished by opening the DC supply breakers on PKA-M41 in
the DC Equipment Room.
D Wrong Train ‘B’ is the train that has disconnect switches installed. Appendices A and B
are used to isolate Train ‘B’ equipment from the control room to prevent fire
related operation while allowing for remote operation as well as
disabling/de-energizing other equipment to prevent fire initiated operations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Given the following plant conditions:
• Unit 1 was at 80% power.
• Due to toxic gas intrusion SM and CRS have directed the evacuation of the Control
Room.
Which ONE of the following describes an action that is completed PRIOR to evacuating the
Control Room and the reason?
A. Ensure that Emergency Boration is established if all full strength CEAs did not
fully insert.
B. Initiate an MSIS to prevent over-pressurizing the Main Condenser in the event
that a loss of vacuum occurs.
C. Initiate an MSIS to prevent an uncontrolled cooldown in the event a steam
bypass control valve fails open once the crew is at the Remote Shutdown
Panel.
D. Check that all full strength CEAs are inserted to determine if charging pump
suction must be aligned to the RWT once the crew is at the Remote Shutdown
Panel.

A

A Wrong Incorrect because the boration will occur after the CR is evacuated. Plausible
because the 1st part is correct. Also plausible because it is the 1st action taken
once the operators are at the RSP.
B Wrong Incorrect because an MSIS is not initiated until after the CR is evacuated. See
Steps 17 and 32 of 40AO-9ZZ18.
C Wrong Incorrect because an MSIS is not initiated until after the CR is evacuated. See
Steps 17 and 32 of 40AO-9ZZ18. Plausible because an MSIS is initiated prior
to leaving the CR in the event of a CR Fire. See Step 3 of 40AO-9ZZ19,
Control Room Fire. The 2nd part is plausible because it could be true.
D Correct CEAs are checked inserted at Step 3 of 40AO-9ZZ18, Shutdown Outside
Control Room. Steps 7 & 8 direct operators to the RSP. Step 9 directs
the CRS to borate to the charging pump suction from the RWT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Given the following conditions:
• The Reactor has tripped due to a LOCA.
• All RCPs are secured due to low RCS subcooling.
• Initial HPSI flow to each cold leg is 300 gpm.
Subsequently
• SIB-P02, HPSI Pump ‘B’ trips.
Which ONE of the following identifies the expected flowrates on the instruments listed below?
FT-331, HPSI TO 1A FLOW (SIA-FI-331)
FT-321, HPSI TO 2B FLOW (SIB-FI-311-1)
FT-331 FT-321
A. Approximately 75 gpm 0 (ZERO) gpm
B. Approximately 150 gpm 0 (ZERO) gpm
C. Approximately 75 gpm Approximately 75 gpm
D. Approximately 150 gpm Approximately 150 gpm

A

A Wrong Incorrect because FT-331 will read approximately 150 gpm, not 75, and
because FT321 will read approximately 150 gpm, not ZERO. Also plausible
because a novice operator may deduce that since a Train B pump tripped, the
“SIB” indicator will not indicate flow. ZERO flow is also possible because the
associated flow indicator would read ZERO gpm if a LPSI pump tripped.
B Wrong Incorrect because FT-321 will read approximately 150 gpm, not ZERO.
Plausible because the 1st part is correct. Also plausible because a novice
operator may deduce that since a Train B pump tripped, the “SIB” indicator will
not indicate flow. ZERO flow is also possible because the associated flow
indicator would read ZERO gpm if a LPSI pump tripped.
C Wrong Incorrect since FT-331 will read approximately 150 gpm, not 75. Plausible
because the 2nd part is correct. Also plausible because a novice operator may
deduce that, since 1 of 2 pumps tripped, the flowrate will be split between SIA
and SIB indicators.
D Correct Each Train of HPSI has redundant indicators which show injection flow to
each of the 4 cold legs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q
Given the following conditions:
• The Reactor has tripped.
• An ESD has occurred on SG #1.
• SG #1 has just reached dryout.
The following indications are available to the Secondary Operator:
• Loop 1 T-cold 392°F
• Loop 1 T-hot 480°F
• Loop 2 T-cold 460°F
• Loop 2 T-hot 488°F
The BOP operator is now manipulating Atmospheric Dump Valves, which one of the following is the
target pressure for SG #2?
A. 225 psia.
B. 465 psia.
C. 565 psia.
D. 610 psia.
A

A Correct 225 psia is the saturation pressure for 392°F. IAW 40EO-9EP05, Excess
Steam Demand, the operating crew is required to stabilize RCS
temperature at the lowest Tcold. This is accomplished by controlling SG
pressure.
Per 40EO-9EP05, Step 14, Page 10:
14. Stabilize RCS temperature using the lowest Tc by performing the
following:
a. Maintain Tc within the P/T limits. REFER TO Appendix 2, Figures
b. Steam the least affected Steam Generator using ANY of the following:
• SBCS
• ADVs from the Control Room
• Appendix 18, Local ADV
Operation
c. Control feedwater to the least affected steam generator.
d. WHEN control is regained, THEN record the following:
Time: ______
RCS Tc: ______
PZR Pressure: ______
B Wrong Incorrect because the required SG pressure is 225 psia, not 465 psia.
Plausible because 465 psia is the saturation pressure for the given Loop 2
Tcold.
C Wrong Incorrect because the required SG pressure is 225 psia, not 565 psia.
Plausible because 565 psia is the saturation pressure for the given Loop 1Thot.
D Wrong Incorrect because the required SG pressure is 225 psia, not 610 psia.
Plausible because 610 psia is the saturation pressure for the given Loop 2Thot.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Given the following conditions:
• Unit 1 was operating at 100% power.
• RCP 1A supply breaker trips.
• On the reactor trip, the DFWCS system fails.
• Operators take manual control of AFW and establish 350 gpm flow to each SG.
Which ONE of the following SG conditions should the Operator expect 10 minutes after the trip?
A. SG #1 will have a higher level than SG #2.
B. SG #2 will have a higher level than SG #1.
C. Loop 1 Tcold will be higher than Loop 2 Tcold.
D. Loop 2 Tcold will be higher than Loop 1 Tcold.

A

A Correct SG #2 will have a lower SG level because it is generating more steam due
to greater RCS flow.
B Wrong Incorrect since SG#1 will have a higher level due to the lower steaming rate.
C/D Wrong There will be no difference in temperature even though there is a difference in the
steaming rate. These are plausible distracters because there is a difference in the
steaming rate of the two loops. Also plausible because there are conditions such
as ESDs where Tcold will diverge after an MSIS is actuated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Given the following conditions:
• Unit 1 is at 100% power.
• Alarm VCT TRBL (3A09A) actuates.
• The RO notes that VCT pressure is 5 psig and lowering slowly.
Which ONE of the following identifies (1) the required action and (2) the reason for that action?
A. (1) raise hydrogen pressure
(2) to prevent water from flashing inside the VCT
B. (1) raise hydrogen pressure
(2) to maintain charging pump NPSH
C. (1) raise nitrogen pressure
(2) to prevent water from flashing inside the VCT
D. (1) raise nitrogen pressure
(2) to maintain charging pump NPSH

A

A Wrong Incorrect because VCT overpressure is not maintained to prevent flashing
within the VCT – it helps prevent flashing in the charging pump suction.
Plausible because there are components within many systems that maintain a
pressure to prevent flashing. For example, in the CVCS, the two letdown
backpressure control valves maintain a backpressure to prevent flashing
upstream of the valves, to help prevent damage to the Letdown Heat
Exchanger. (Refer to L.P. NNI02C141A04, Charging and Letdown Subsystem,
Page 29). Also plausible because the 1st part is correct.
B Correct Per 40AL-9RK3A, Panel BO3A Alarm Responses, Window 3A09A, Group C
(Volume Control Tank Pressure Hi-Lo), if VCT pressure is low, the
operators are directed to raise pressure using either the hydrogen
regulator or the nitrogen regulator. Since the Unit is at power, the
hydrogen regulator should be used since a hydrogen overpressure exists
on the VCT.
Per L.P. NNI02C141A04, Charging and Letdown Subsystem, Page 38, one
function of the VCT is to maintain NPSH to the charging pumps. This is
accomplished by the hydrogen overpressure in the VCT while at power,
the head due to the height of water in the VCT, and VCT/charging pump
suction temperature. If pressure in the VCT drops, available NPSH will
be reduced.
C Wrong Incorrect because VCT overpressure is not maintained to prevent flashing
within the VCT – it helps prevent flashing in the charging pump suction.
Plausible because there are components within many systems that maintain a
pressure to prevent flashing. For example, in the CVCS, the two letdown
backpressure control valves maintain a backpressure to prevent flashing
upstream of the valves, to help prevent damage to the Letdown Heat
Exchanger. (Refer to L.P. NNI02C141A04, Charging and Letdown Subsystem,
Page 29).
Also incorrect because, while at power, nitrogen would not be used to control
VCT pressure. Nitrogen is plausible because it is used to maintain VCT
pressure while the Unit is shutdown.
D Wrong Incorrect because, while at power, nitrogen would not be used to control VCT
pressure. Nitrogen is plausible because it is used to maintain VCT pressure
while the Unit is shutdown. Also plausible because the 2nd part is correct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q
What is the power supply to the Low Pressure Safety Injection pump B, SIB-P01?
A. NBN-S01, 4160 kV bus.
B. NBN-S02, 4160 kV bus.
C. PBA-S03, 4160 kV bus.
D. PBB-S04, 4160 kV bus.
A

A Wrong 4160 kV buses but are not the power supply to LPSI pump B
B Wrong
C Wrong
D Correct Class 4160kV PBB-S04 is the correct source

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

In order to reset a SIAS that was manually initiated from B05, the operator MUST…
A. ONLY press either LOCKOUT RESET pushbutton at each Auxiliary Relay
Cabinet.
B. ONLY press both LOCKOUT RESET pushbuttons at each Auxiliary Relay
Cabinet simultaneously.
C. FIRST press the INITIATION PATH RESET pushbutton at the PPS cabinet; then
press either LOCKOUT RESET pushbutton at each Auxiliary Relay Cabinet.
D. FIRST press the INITIATION PATH RESET pushbutton at the PPS cabinet; then
press both LOCKOUT RESET pushbuttons at each Auxiliary Relay Cabinet
simultaneously.

A

A Wrong Incorrect because the INITIATION PATH RESET pushbutton at the PPS cabinet
must first be depressed. Plausible because it is partially correct in that either
pushbutton will reset the function.
B Wrong Incorrect because both LOCKOUT RESET pushbuttons do not have to be reset.
Plausible because a novice operator may not recall that either pushbutton will
accomplish the reset and conclude that, in many cases, both pushbuttons must
be depressed to reset a function.
C Correct IAW 40AO-9ZZ17, Appendix B, PPS-ESFAS Reset, Steps 5.2 (SIAS Initiation
Relay lamps will not be illuminated), PPS Initiation Path is reset first. Then, in
Appendix B, Step 6.1 (SIAS Actuation Signal lamps will not be illuminated), the
PPS-ESFAS actuation is reset at the Aux Relay Panels.
D Wrong Incorrect because both LOCKOUT RESET pushbuttons do not have to be reset.
Plausible because the first part is correct. Also plausible because a novice
operator may not recall that either pushbutton will accomplish the reset and
conclude that, in many cases, both pushbuttons must be depressed to reset a
function.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Given the following plant conditions:
• Unit 1 is operating at 100% power.
• Diesel Generator ‘B’ is out of service for maintenance.
• Offsite power is lost.
• A LOCA occurs and the crew implements 40EP-9EO03, Loss of Coolant Accident.
• RCS pressure and Pressurizer level are dropping rapidly.
• RCS pressure is 1100 psia.
• The RO notes the following indications for HPSI Pump “A”.
􀂃 150 Amps.
􀂃 Discharge pressure is 1000 psig.
􀂃 Discharge flow is 75 gpm per loop.
Based on these indications, there is a (1) and the operating crew should (2) to establish
HPSI flow.
A. (1) a sheared shaft on HPSI Pump ‘A’
(2) enter 40EP-9EO09, Functional Recovery, and restore power to PBB-S04
B. (1) a break in the HPSI Pump ‘A’ discharge header
(2) enter 40EP-9EO09, Functional Recovery, and restore power to PBB-S04
C. (1) a sheared shaft on HPSI Pump ‘A’
(2) remain in 40EP-9EO03 and restore power to PBB-S04 using 40AO-9ZZ12,
Degraded Electrical Power
D. (1) a break in the HPSI Pump ‘A’ discharge header
(2) remain in 40EP-9EO03 and restore power to PBB-S04 using 40AO-9ZZ12,
Degraded Electrical Power

A

A Wrong Incorrect because a sheared shaft would result in low amps on the pump.
Plausible because low discharge pressure and low flow are also indications of a
sheared shaft. Also plausible because the second part is correct.
B Correct High amps, low discharge pressure and low flow are indications consistent with a
discharge header pipe rupture. The FRP is structured to restore power to class
buses.
40DP-9AP16, Section 7.0.1, states:
The FRP might also be entered from an ORP if an ORP had been initially
selected but failed the Safety Function Status Check or the ORP selected is not
mitigating the event. If the Safety Function Status Check acceptance criteria are
not satisfied at any time, then the operator is directed to evaluate the need to
implement the FRP.
40DP-9AP16, Section 9.0, states: Each ORP has its own Safety Function Status Check (SFSC) which must be
used whenever the ORP is in use. The SFSC is used to check the status of safety
functions. By satisfying the SFSC acceptance criteria, the operating staff is
assured that the actions being taken are maintaining the plant in a safe condition.
If SFSC criteria are not satisfied, the operators will take corrective actions to
satisfy the safety functions, implement another ORP, or exit to the FRP.
Since the RCS Pressure Control Safety Function Acceptance Criteria are not met
(HPSI flow is in the Region Not Acceptable on Appendix 2), entry into the FRP is
required.
NOTE – K/A MATCH:
If the question was structured to ask for “predict impact of an ECCS header
rupture,” the answer would have to be similar to “reduced injection flow” and this
would have little discriminatory value. Therefore, to improve discriminatory
value, “reverse logic” was used to require the examinee to determine the event
and the mitigating action.
NOTE – APPROPRIATE LICENSE LEVEL
This question is at the RO level because the conditions in the stem provide the
Entry Conditions to a major EOP.
C Wrong Incorrect because a sheared shaft would result in low amps on the pump. Also
incorrect because the EOP User’s Guide requires entry into the FRP when a
Safety Function is not satisfied. Plausible because using 40AO-9ZZ12 would
work.
D Wrong Incorrect because the EOP User’s Guide requires entry into the FRP when a
Safety Function is not satisfied. Plausible because using 40AO-9ZZ12 would
work. Also plausible because the first part is correct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
• The #3 seal on Reactor Coolant Pump 1A has degraded.
• The crew has verified a 17 gpm leakrate per 40AO-9ZZ02, Excessive RCS Leakrate.
• Reactor Drain Tank (RDT) pressure is 5 psig and increasing.
• RDT level is 56% and increasing.
• Volume Control Tank (VCT) level is 41% and lowering.
• Pressurizer level is stable.
Which ONE of the following identifies (1) the result if NO operator action(s) are taken and (2) the
required action to take to maintain parameters within limits?
A. (1) the RDT rupture disk will blow.
(2) vent the RDT to Containment.
B. (1) the RDT rupture disk will blow.
(2) vent the RDT to the gas surge header.
C. (1) charging pump suction will be lost.
(2) take manual control of makeup to the VCT.
D. (1) charging pump suction will be lost.
(2) align the Reactor Water Tank to the charging pump suction.

A

A Wrong Incorrect because 40AL-9RK3A requires that the RDT be vented to the gas surge
header. Plausible because the first part is correct. Also plausible because
venting to Containment is an option in 40AL-9RK3A.
B Correct Explanation: VCT level will drop due to the loss of inventory. Pzr level will
remain stable as letdown flow lowers. RDT level will increase as the RCS
fluid flows past the failed seal. Containment temp and humidity are
unaffected as failed RCP seal flow is collected in the RDT. The RDT rupture
disc blows at 120#. If no actions are taken to relieve the increasing
pressure, the rupture disc will eventually blow
Per the NOTE in 40AL-9RK3A:
If the reactor drain tank pressure continues to increase to 10 psig the RDT
vent to gas surge header valve CHN-UV-540 and RDT outlet containment
isolation valve CHA-UV-560, will close. At approximately 120 psid the RDT
rupture disc, CHN-PSE-12 will rupture.
Per the 40AL-9RK3A:
Unit 2 Only: Vent the RDT to the gas surge header using CHN-UV-540 to
maintain RDT pressure below 7 psig.
Units 1 and 3 Only: Vent the RDT to the gas surge header using
CHN-UV-540 to maintain RDT pressure below 10 psig
C Wrong Incorrect because the makeup capabilities exceed the given leak rate. VCT
level will be maintained above 34%, above the point where charging pump
suction is lost. The action is plausible because, if the VCT TRBL (due to LOW
level) actuates, 40AL-9RK3A, window 3A09A requires manual makeup.
D Wrong Incorrect because the makeup capabilities exceed the given leak rate. VCT
level will be maintained above 34%, above the point where charging pump
suction is lost. The action is plausible because, if the VCT LVL LO-LO alarm
actuates, 40AL-9RK3A, window 3A08B describes that the charging pump suction
will auto-swap to the RWT (when CHN-UV-514 opens)..

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q
Which ONE of the following identifies (1) the normal and (2) the backup makeup source to the
Nuclear Cooling Water Surge Tank?
A. (1) Condensate Storage Tank.
(2) Cooling Water Holdup Tank.
B. (1) Condensate Storage Tank.
(2) Reactor Makeup Water Tank.
C. (1) Demineralized Water System.
(2) Cooling Water Holdup Tank.
D. (1) Demineralized Water System.
(2) Reactor Makeup Water Tank.
A

A Wrong Incorrect because the CST is not the normal makeup to the NC Surge Tank.
Plausible because the CST supplies makeup to many surge tanks, such as the
Essential Chilled Water Surge Tank and the Essential Cooling Water Surge
Tank. Also plausible because the 2nd part is correct.
B Wrong Incorrect because the CST is not the normal makeup to the NC Surge Tank.
Also incorrect because the RMWT does not supply backup makeup. Plausible
because the CST supplies makeup to many surge tanks, such as the Essential
Chilled Water Surge Tank and the Essential Cooling Water Surge Tank. RMWT
is plausible because it is a source of pure makeup water for other tanks in the
Auxiliary Building, such as the Equipment Drain Tank and the VCT.
C Correct Per DWG 01-M-NCP-001 (upper left corner), the normal makeup source is
automatically supplied from Demineralized Water System via LCV 75. Backup
makeup is from the Cooling Water Holdup Tank via normally-closed manual
valve V070.
D Wrong Incorrect because the RMWT does not supply backup makeup. RMWT is
plausible because it is a source of pure makeup water for other tanks in the
Auxiliary Building, such as the Equipment Drain Tank and the VCT. Also
plausible because the 1st part is correct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Given the following plant conditions:
• Unit 1 is MODE 4.
• An Inservice Test is being performed on containment penetration isolation valves using
73ST-9XI23, CP, EW, IA, and NC Valves – Inservice Test.
• The Close Stroke Time is slower than the Tech Spec Acceptance Criteria.
For this test, the valve stroke time is measured from handswitch operation to when the ___(1)___
and the crew must apply the requirements of LCO ___(2)___.
A. (1) green light is ON.
(2) 3.9.3, Containment Penetrations.
B. (1) green light is ON.
(2) 3.6.3, Containment Isolation Valves.
C. (1) red light goes OUT.
(2) 3.9.3, Containment Penetrations.
D. (1) red light goes OUT.
(2) 3.6.3, Containment Isolation Valves.

A

A Wrong Incorrect because stroke time is until the red light goes out, not when the green
light comes on. Plausible because each close stroke time test in 73ST-9XI23
contains the following step:
“Verify only the green light is on at…”
T.S. 3.9.3 is incorrect because it only applies during Refueling Ops.
T.S. 3.9.3 is plausible because 73ST-9XI23 specifically cites entry into this T.S.’s
actions when a Containment Purge Isolation Valve is declared INOPERABLE.
These valves are also tested in 73ST-9XI23.
Per 73ST-9XI23, Step 8.3:
IF any valve fails to satisfy the Technical Specification Acceptance Criteria OR is
otherwise determined to be Inoperable,
THEN perform the following:
8.3.1 Declare the valve Inoperable.
8.3.1.1 IF any Containment Purge Isolation Valve is determined to be Inoperable,
THEN observe the action requirements of LCO 3.9.3, Containment Penetrations.
B Wrong Incorrect because stroke time is until the red light goes out, not when the green
light comes on. Plausible because each close stroke time test in 73ST-9XI23
contains the following step: “Verify only the green light is on at…” Also plausible because the second part is
correct.
C Wrong T.S. 3.9.3 is incorrect because it only applies during Refueling Ops.
Plausible because the first part is correct. T.S. 3.9.3 is plausible because
73ST-9XI23 specifically cites entry into this T.S.’s actions when a Containment
Purge Isolation Valve is declared INOPERABLE. These valves are also tested
in 73ST-9XI23.
D Correct Per several NOTES in 73ST-9XI23:
Valve close stroke time is measured from handswitch operation to when the red
light goes out.
Per several Steps in 73ST-9XI23:
Measure stroke time from handswitch operation until red indication light goes out.
Per 73ST-9XI23, Step 8.3:
IF any valve fails to satisfy the Technical Specification Acceptance Criteria OR is
otherwise determined to be Inoperable,
THEN perform the following:
8.3.1 Declare the valve Inoperable.
Once a Containment Isolation Valve is declared INOPERABLE, T.S. 3.6.3 must
be applied.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q
Given the following plant conditions:
• The Unit is operating at 100% power.
• The selected Pressurizer pressure transmitter, PT-100Y, fails HIGH.
Assuming NO operator action, which ONE of the following identifies the effect of this failure on the
1. Steam Bypass Control System (SBCS)
2. Output of the Master Pressure Controller?
A. 1) modulate signal biases downward
2) goes to MINIMUM output
B. 1) modulate signal biases downward
2) goes to MAXIMUM output
C. 1) permissive signal biases downward
2) goes to MINIMUM output
D. 1) permissive signal biases downward
2) goes to MAXIMUM output
A

A Wrong Incorrect because the permissive signal will be biased downward, not the
modulate signal. Plausible because downward bias is correct for the permissive
signal. Also incorrect because the Master Pressure Controller goes to MAX, not
MIN. Plausible because it is a common misconception that the output of the
Master Pressure Controller acts “in reverse” of the direction of failure (HIGH
failure – LOW output; LOW failure – HIGH output).
B Wrong Incorrect because the permissive signal will be biased downward, not upward.
Plausible because downward bias is correct for the permissive signal. Also
plausible because the 2nd part is correct.
C Wrong Incorrect because the Master Pressure Controller goes to MAX, not MIN.
Plausible because the 1st part is correct. Plausible because it is a common
misconception that the output of the Master Pressure Controller acts “in reverse”
of the direction of failure (HIGH failure – LOW output; LOW failure – HIGH
output).
D Correct Per Lesson Plan NKASYC014306, Pressurizer Pressure Control System:
Selected Pressurizer pressure transmitter fails high:
• “Pressurizer Trouble” annunciator.
• “Pressurizer Pressure Hi-Lo” annunciator.
• “Turbine Bypass Demand” annunciator.
• SBCS affected:
• If PT-100X - Modulation signal biased downward (controller
demand generated).
• If PT-100Y - Permissive signal biased downward (permissive light
lit).
• Master Pressure Controller goes to Maximum output.
• Proportional heaters to minimum output.
• Pressurizer spray valve controller goes to maximum output.
• Spray valves go full open.
• All Backup heaters turn off.
• High Pressurizer pressure indication on B04.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q
Given the following conditions:
• The core is at 150 EFPD.
• Reactor Startup is in progress.
As power increases above \_\_\_(1)\_\_\_, the High Log Power Bypass Permissive light \_\_\_(2)\_\_\_.
A. (1) 10-2%
(2) goes out
B. (1) 10-2%
(2) illuminates
C. (1) 10-4%
(2) goes out
D. (1) 10-4%
(2) illuminates
A

A Wrong Incorrect because the setpoint for the High Log Power Bypass Permissive is
10-4%, not 10-2%. Also incorrect because the light illuminates, not goes out.
Plausible because the Hi Log Power trip setpoint is 10-2%. Also plausible
because the light goes out as power drops below 10-4%.
B Wrong Incorrect because the setpoint for the High Log Power Bypass Permissive is
10-4%, not 10-2%. Plausible because the Hi Log Power trip setpoint is 10-2%.
Also plausible because the second part is correct.
C Wrong Incorrect because the light illuminates, not goes out. Plausible because the first
part is correct. Also plausible because the light goes out as power drops below
10-4%.
D Correct Per 41AL-1RK5A, Window 5A15B:
PT ID POSSIBLE CAUSE SETPOINT
SBJS10A Hi Log Power Byp Perm Ch A l0-4% power
SBJS10B Hi Log Power Byp Perm Ch B l0-4% power
SBJS10C Hi Log Power Byp Perm Ch C l0-4% power
SBJS10D Hi Log Power Byp Perm Ch D l0-4% power
Per 40OP-9ZZ03, Appendix F:
Appendix F - Bypassing High Log Power Trips
1.0 Bypassing High Log Power Trips.
1.1 WHEN the High Log Power Bypass Permissive light illuminates (HI LOG
PWR BYP PERM, B05A15B will alarm also),
THEN perform the following:
1.1.1 Bypass the High Log Power Trips for each Log Safety Channel on B05.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Given the following conditions:
• The Unit is operating at 100% one week after a refueling outage.
Which ONE of the choices below completes the following statement?
There are a total of ___(1)___ channels of ESF Matrix Logic and a loss of ALL of them will result
in exceeding the peak fuel centerline temperature Safety Limit of ___(2)___ in the event of a
Design Basis Accident?
A. (1) four
(2) 5022°F
B. (1) four
(2) 5080°F
C. (1) six
(2) 5022°F
D. (1) six
(2) 5080°F

A

A Wrong Incorrect because there are 6 ESF Matrix Relays, not four. Plausible because
there are 4 Initiation Relays. Also incorrect because the correct temperature
limit is 5080°F, not 5022°F. 5022°F is plausible because this would be correct
(5080 – 58 = 5022) for a burnup of 10000 MWD/MTU.
B Wrong Incorrect because there are 6 ESF Matrix Relays, not four. Plausible because
there are 4 Initiation Relays. Also plausible because the 2nd part is correct.
C Wrong Incorrect because the correct temperature limit is 5080°F, not 5022°F. 5022°F is
plausible because this would be correct (5080 – 58 = 5022) for a burnup of
10000 MWD/MTU. Also plausible because the 1st part is correct.
D Correct Per TS 2.1.1.2: In MODES 1 and 2, the peak fuel centerline temperature
shall be maintained < 5080°F (decreasing by 58°F per 10,000 MWD/MTU for
burnup and adjusting for burnable poisons per CENPD-382-P-A). Stem
states 1 week after startup.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Given the following conditions:
• Containment pressure Channel A is 3.4 psig.
• Containment pressure Channel B is 2.7 psig.
• Containment pressure Channel C is 3.1 psig.
• Containment pressure Channel D is 2.6 psig.
• Pressurizer pressure Channel A is 1845 psia.
• Pressurizer pressure Channel B is 1830 psia.
• Pressurizer pressure Channel C is 1832 psia.
• Pressurizer pressure Channel D is 1840 psia.
• SG 1 pressure Channel A is 980 psia.
• SG 1 pressure Channel B is 950 psia.
• SG 1 pressure Channel C is 970 psia.
• SG 1 pressure Channel D is 970 psia.
Assuming NO Operator actions, the SG sample valves are…
A. closed, due to both the MSIS and CIAS actuations.
B. closed, due to both the SIAS and MSIS actuations.
C. open, Hi containment trip setpoint has not been reached.
D. open, Lo SG pressure trip setpoint has not been reached.

A

A Wrong Incorrect because CIAS does not close these valves. Plausible because valves
will be closed (this part is correct). Also plausible because “MSIS” is correct.
B Correct 3.0 psig in Containment will initiate CIAS, SIAS and MSIS signals on 2/4
channels. Valves will be closed due MSIS (Containment press) and SIAS
(Pzr press). CIAS, although the same setpoint, does not close these valves.
C Wrong Incorrect because valves will be closed, not open. Also wrong because CIAS
initiates at 3 psig on 2/4 channels). Plausible because a novice operator may
confuse the setpoint for CIAS with that of the Containment Spray Actuation
Signal (CSAS) setpoint of 8.5 psig. See Operator Information Manual, Pages 48
and 49.
D Wrong Incorrect because valves will be closed, not open. Plausible because it is true
that Lo S/G pressure MSIS has not initiated (setpoint is 960 psig).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Given the following conditions:
• Unit 3 is operating at rated power.
• The “A” train CEDM cooling fans (A02A/A02C) are running.
THEN
• Alarm window 7A9B, CEDM ACU COOLS SYS TRBL, alarms.
• The Operator observes that both CEDM cooling fans A02A/A02C have brighter than normal
green lights.
Under these conditions, the “B” train CEDM fans should ___(1)___ and, if cooling is NOT restored,
then ___(2)___.
A. (1) start immediately
(2) the Reactor must be tripped within 10 minutes of loss of cooling.
B. (1) start within 2 minutes
(2) the Reactor must be tripped within 10 minutes of loss of cooling.
C. (1) start immediately
(2) the Reactor must be tripped within 40 minutes of loss of cooling.
D. (1) start within 2 minutes
(2) the Reactor must be tripped within 40 minutes of loss of cooling.

A

A Wrong Incorrect because B trains fan will NOT start immediately. There is time delay
installed in the auto start feature to allow time for damper closing. “Immediately”
is plausible because there are some standby HVAC fans (PZR Cooling Fan and
the Containment Normal ACU), that automatically start without a time delay.
The shutdown is plausible because 40AO-9ZZ20 requires a cooldown if cooling
flow cannot be restored; it just doesn’t have to be started within 40 minutes.
B Wrong The fans will start within 2 minutes. There is time delay installed in the auto start
feature to allow time for damper closing. The cooldown must be started within 10
minutes. Also plausible because the first half is correct.
C Wrong Incorrect because B trains fan will NOT start immediately. Also plausible because
the second half is correct.
D Correct The B train fans have a 2 minute time delay and 40AO-9ZZ20 directs a Reactor
trip if cooling not restored within 40 minutes.
40OP-9HC01, Containment HVAC (HC), Limitations and Precautions 3.13
states:
“When one set of CEDM fans is running, the other set may be spinning
backwards. A time delay agastat of 120 seconds is installed so that when the
set of running CEDM fans is shut down, that the other set won’t auto-start for 120
seconds (meaning the second set of fans is no longer running backwards.) There
should be no need to manually start the second set of fans unless 120 seconds has passed and they still haven’t started.”
40AO-9ZZ20, Section 10.0, Step 7 states:
IF at least one CEDM ACU Fan is NOT restored within 40 minutes of
the initial loss,
THEN perform the following:
a. Trip the reactor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Given the following conditions:
• Unit 1 has tripped due to a LOCA inside Containment.
• Containment pressure is 9.2 psig and rising.
• Both Containment Spray trains have failed to actuate.
• The CRS has entered 40EP-9EO09, Functional Recovery.
• CTPC-2 is being implemented to supply CS flow using LPSI Pump ‘A.’
Which ONE of the below listed sets of parameters will be monitored to satisfy CPTC-2?
Containment…
A. humidity and LPSI pump amps.
B. pressure and LPSI pump amps.
C. humidity and CS “A” discharge flow transmitter SIA-FI-338.
D. pressure and CS “A” discharge flow transmitter SIA-FI-338.

A

A Wrong Incorrect because humidity will be high initially from the LOCA, so a change
would not be seen. Plausible because the second part is correct. Also
plausible because Containment humidity is a parameter that could be used to
determine Containment conditions and diagnose a LOCA; therefore a novice
operator may deduce this parameter is used to monitor CTPC-2.
B Correct 40EP-9EO09, CTPC-2 step 3.1.f limits amps to ensure continued operation
of the LPSI pump. Containment pressure will drop if the section is
performed correctly. Containment pressure is also used in subsequent
steps to monitor CTPC-2 (Steps 9 and 10).
C Wrong Incorrect because, when LPSI is cross tied to CS, CS header flow is not
available. (40EP-9EO09, CTPC-2, note by step 3). Also incorrect because
humidity will be high initially from the LOCA, so a change would not be seen.
Plausible because Containment humidity is a parameter that could be used to
determine Containment conditions and diagnose a LOCA; therefore a novice
operator may deduce this parameter is used to monitor CTPC-2.
D Wrong Incorrect because, when LPSI is cross tied to CS, CS header flow is not
available. (40EP-9EO09, CTPC-2, note by step 3). Plausible because the first
part is correct.

41
Q

Given the following conditions:
• Unit 1 at normal operating temperature and pressure.
• Testing of AFA-P01 in progress.
• AFA-P01 is tripped from the control room due to SGA-UV-134, Main Steam Supply Valve, not
opening.
• SGA-UV-134A, Main Steam Bypass Valve, has been closed.
WHICH ONE of the following identifies the required operator actions to reset AFA-P01?
A. Open AFA-HV-54 ONLY.
B. Close AFA-HV-54, then open AFA-HV-54 ONLY.
C. Reset trip linkage on AFA-HV-54, then open AFA-HV-54 ONLY.
D. Close AFA-HV-54, then reset trip linkage on AFA-HV-54, then open AFA-HV-54.

A

A Wrong Incorrect because the valve must first be closed, then opened. Plausible
because the valve must be opened to reset AFA-P01.
B Correct IAW 40OP-9AF01, Section 11.3 (Steps 11.3.7-9), after AFA-P01 is manually
tripped from the CR, AFA-HS-54D is placed in JOG CLOSE, then in JOG OPEN
to fully reset the valve.
IAW 40OP-9AF01, Section 11.3:
11.3.7 Trip AFA-HV-54, AFA-P01 Trip & Throttle valve using AFA-HS-54A,
“ESS STM DRIVEN AFW PMP MANUAL TRIP” (B06).
11.3.8 Reset AFA-HV-54 by performing the following (B06):
1. Place and hold AFA-HS-54D in “JOG CLOSE”.
2. WHEN AFA-HV-54 stem closed rotation stops,
OR the valve indication shows the valve full closed,
THEN release AFA-HS-54D.
11.3.9 Direct the Nuclear Operator to perform the following locally:
1. Take AFA-HS-54E, AFA-P01 Trip & Throttle Valve, to “JOG OPEN”
until the valve stem is observed to move in the open direction.
C Wrong Incorrect because the operator does NOT have to reset the trip linkage on
AFA-HV-54 for a manual trip from the CR. Plausible because the trip linkage
must be reset locally if an overspeed condition occurs. See 40OP-9AF01, Step
11.3.28 for resetting AFA-P01 after an overspeed.
D Wrong Incorrect because the operator does NOT have to reset the trip linkage on
AFA-HV-54 for a manual trip from the CR. Plausible because the trip linkage
must be reset locally if an overspeed condition occurs. See 40OP-9AF01, Step
11.3.28 for resetting AFA-P01 after an overspeed. Plausible because these are
the correct steps for resetting AFA-P01 after an overspeed condition.

42
Q
Given the following conditions:
• Unit 1 was operating at 100% power
• ALL Main Feedwater is lost.
The Auxiliary Feedwater System will initiate feeding the SGs at (1) WR level and terminate AFW
flow at (2).
A. (1) 20.3 (2) 40.8% WR level.
B. (1) 20.3 (2) 44.3% WR level.
C. (1) 25.8 (2) 40.8% WR level.
D. (1) 25.8 (2) 44.3% WR level.
A

A Wrong 20.3% WR is the DAFAS setpoint which is wrong but plausible since it is a SG
level setpoint. 44.3% is also wrong but it is the RPS SG level trip setpoint, also
B Wrong plausible
C Correct This is the control band for AFW flow to the SGs
D Wrong 25.8% is the setpoint for AFAS but 44.3% is the RPS trip setpoint making this
choice plausible but wrong.

43
Q

Unit 1 is operating at rated power, while monitoring DFWCS you observe the following:
• SG 1 LT-1111 indicates 50% NR level and stable.
• SG 1 LT-1112 has failed to 54% NR and stabilized.
• SG 2 LT-1121 indicates 51% NR level and stable
• SG 2 LT-1122 indicates 50% NR level and stable
1. What effect will the failure of LT-1112 have on SG 1 level?
2. Which of the following automatic OR manual actions are found in 40AL-9RK6A, ARP that
must occur to control SG 1 level?
A. 1. Actual SG 1 level will lower.
2. When SG 1 level deviation exceeds 8%, then a canned value will be
inserted into the SG 1 DFWCS to restore level.
B. 1. Actual SG 1 level will rise.
2. Place LT-1112 in the maintenance mode, SG 1 level will lower to the level
setpoint.
C. 1. Actual SG 1 level will rise.
2. SG 1 DFWCS will then use SG 2 LT-1121 signal and lower SG 1 level.
D. 1. Actual SG 1 level will lower.
2. Place LT-1112 in the maintenance mode and then slowly raise SG 1 level
to the level setpoint

A

A Wrong Level will lower because the failed signal is > the setpoint ~ 52%. There is no 8%
deviation that causes an auto action in level control there 8% deviations which occur
in FW temperature and reactor power.
B Wrong Actual level will lower but these are the actions for a failed transmitter.
C Wrong Actual level will lower but the 15% deviation will not occur in the control signal since
the DFWCS uses the higher level, only the actual SG levels
D Correct Level will lower because the failed signal is > the setpoint ~ 52%. These are the steps
as described in the ARP for actual level < than setpoint that will be used.

44
Q

Auxiliary Feedwater flow should be maintained ___(1)___. This limitation is intended to ___(2)___,
A. (1) less than 250 gpm to both SGs when differential steam pressure is less than
50 psig.
(2) balance primary side cooling action
B. (1) less than 250 gpm to both SGs when differential steam pressure is less than
50 psig.
(2) minimize damage due to voiding in the feed ring
C. (1) between 250 & 1000 gpm to both SGs when SG levels are less than 27%NR
(2) balance primary side cooling action
D. (1) between 250 & 1000 gpm to both SGs when SG levels are less than 27%NR
(2) minimize damage due to voiding in the feed ring

A

A Wrong Incorrect because operators are not required to maintain <250 gpm if DP is less
than 50 psig. Plausible because there is a L&P in 40OP-9AF01 related to 50
psid between SGs.
40OP-9AF01, Limitation and Precaution 3.12:
Attempt to maintain less than 50 psig differential steam pressure between the
Steam Generators while feeding with the Essential Auxiliary Feedwater System.
This action helps balance the primary side cooling action of the Steam
Generators.
Also plausible because the 2nd part is the correct reason for L&P 3.12 in
40OP-9AF01.
.
B Wrong Incorrect because operators are not required to maintain <250 gpm if DP is less
than 50 psig. Plausible because there is a L&P in 40OP-9AF01 related to 50
psid between SGs (see A, above). Also plausible because 250 gpm is the lower
limit for AFW flow when SG levels are <27% NR and this limitation is based on
voiding in the feed ring (see D, below).
C Wrong Incorrect because operators are not required to maintain <250 gpm if DP is less
than 50 psig. Plausible because there is a L&P in 40OP-9AF01 related to 50
psid between SGs (see A, above). Also plausible because 250 gpm is the lower
limit for AFW flow when SG levels are <27% NR and this limitation is based on
voiding in the feed ring (see D, below).
D Correct 40OP-9AF01, Essential Auxiliary Feedwater System, Limitations and
Precautions:
3.25 Minimize the use of Aux Feed to maintain Steam Generator levels at less than or equal to 27% narrow range to prevent damage to the
downcomer feed ring and piping. A flowrate of less than 250 gpm, while
level is less than 27% NR, may cause damage to the downcomer feed ring
and piping due to voiding that occurs within the feed ring at this reduced
flowrate.
3.26 If it is necessary to feed with Steam Generator level less than or equal
to 27% narrow range, establish a feed flow of greater than or equal to 250
gpm until level is greater than 27% narrow range.
Lesson Plan NKASYC012105, Auxiliary Feedwater System page 21 of 56,
EO1.5:
Design modifications to the downcomer feed rings have imposed
operational restrictions to minimize voiding and water hammer in the
downcomer lines. Since very little feedwater is required of the S/Gs during
normal shutdown conditions, the lines become voided when S/G level dips
below 27% narrow range indication. When this occurs, a minimum feed of
250 gpm is required to quickly collapse the void and minimize the effect of
the waterhammer. Above this level, the voiding does not occur, and any
minimum feeding rate is acceptable.

45
Q

Given the following conditions:
• Unit 1 has tripped on Low SG level.
• AFAS-1 automatically initiated.
• The CRS directed the manual initiation of AFAS-2 on trend.
• The operator placed all 4 AFAS-2 handswitches on B05 to the initiate position and released the
handswitches.
• Both SG levels are now 45% WR level and rising.
Which ONE of the following describes the AFAS response to these conditions?
A. AFW flow to both SGs will stop.
B. AFW flow to both SGs will continue until SG levels reaches the AFAS reset
setpoint.
C. SG-1 AFW flow will stop, SG-2 AFW flow will continue to feed until overridden
by the Operator.
D. SG-1 AFW flow will stop, SG-2 AFW flow will continue until the high level
override setpoint is reached.

A

A Wrong Incorrect because flow will continue to SG-2. Plausible because this choice
would be true if the AFAS-2 handswitches had been returned to “normal.”
B Wrong Incorrect because flow to SG-1 AFW flow will stop as level rises above 40.8%
WR. “Both SGs” is plausible because this part would be true if the AFAS-2
switches had been returned to “normal.” “45.8%” is plausible because it is a
derivation of the two setpoints (40.8% and 25.8%) around which the AFW
FCVs cycle.
C Correct Since AFAS-1 was automatically initiated, SG-1 AFW FCVs will open
automatically at 25.8% WR and close at 40.8% WR. Since the AFAS-2
switches were NOT returned to normal, the FCVs will open and remain open.
Per Lesson Plan NKASYC012105, Auxiliary Feedwater System, Page 43:
“Additionally, the AFAS channel actuation switches on B05 do not spring return
to a normal position. They must be intentionally returned to the normal position
by the operator. This is an important point, because if these switches are not
returned to the normal position the isolation and flow control valves will not
auto cycle based on S/G level, as described above. The valves will open and
remain open until the operator overrides them to take manual control.”
D Wrong Incorrect since the SG-2 AFW FCVs will NOT close on the High Level
Override. Plausible because the first part is correct. Also plausible because
MFW valves will close on HLO at 88% NR.

46
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
• The 4.16 kV bus NBN-S01 faults and is de-energized.
Which ONE of the following correctly identifies:
(1) Condensate pump(s) that remain running?
(2) Heater Drain pumps that remain running?
A. (1) Condensate Pump C only (2) Heater Drain Pump A.
B. (1) Condensate Pump C only (2) Heater Drain Pump B.
C. (1) Condensate Pump B and C (2) Heater Drain Pump A.
D. (1) Condensate Pump B and C (2) Heater Drain Pump B.

A

A Correct Per the AOP. Condensate pumps are a PRA important load because, on a Loss of
MFW, SGs may be depressurized to feed from the Condensate Pumps.
B Wrong
Condensate pumps A and B are supplied by NBN􀍲S01. Heater Drain pump B is supplied
by NBN􀍲S01.
C Wrong
D Wrong

47
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
• 1-E-NAN-S05 faults and is de-energized.
􀂾 PBA-II-S03L, 4.16 KV Bus S03 Norm Sply, is CLOSED.
􀂾 PBA-II-S03K, 4.16 KV Bus S03 Alt Sply, is OPEN.
􀂾 NO 86 lockouts are present.
30 seconds later, what is the expected condition of PBA-S03, 4160 kV bus?
A. Energized; the NAN-S01 / NAN-S03 “fast bus transfer” will actuate.
B. De-energized; power can be restored by closing PBA-II-S03K, alternate supply
breaker.
C. De-energized; power can be restored by opening the normal supply breaker,
PBA-II-S03L.
D. Energized; PBA-ll-S03B, DG output breaker, closed since there are no 86
lockouts on the bus.

A

A Wrong There is a fast bus transfer between these buses but it only works to keep NAN􀍲S01
energized in case of a turbine trip.
B Wrong This is an available means of energizing the bus as identified MVAC step 3 of the FRP.
This will not work with the normal supply breaker still closed in.
C Correct Per appendix M of 40AO􀍲9ZZ12, Degraded Electrical Power. Ensure that PBA􀍲S03L
and K are OPEN. This will allow the DG breaker to auto close.
D Wrong As identified in the SPTAs, No lockout present is one of the conditions for the DG
breaker, PBA􀍲S03B, to close making this a plausible distracter.

48
Q
Given the following conditions:
• Unit 1 is in Mode 1.
• Battery Charger 'AC' (PKA-H15) is connected to Battery Bus 'C' (PKC-M43).
• Battery Charger 'A' (PKA-H11) trips.
Under these conditions, Battery Charger 'AC' cannot be aligned to both PKA-M41 and PKC-M43 due to a(n)
\_\_\_(1)\_\_\_ interlock and the loss of PKA-H11 also results in the loss of \_\_\_(2)\_\_\_.
A. (1) electrical
(2) MSIV Logic Control Power
B. (1) mechanical
(2) MSIV Logic Control Power
C. (1) electrical
(2) AFN-P01 Backup Control Power
D. (1) mechanical
(2) AFN-P01 Backup Control Power
A

A Wrong Incorrect because the interlock is mechanical, not electrical. Also incorrect
because MSIV Logic Control Power is NOT lost since the battery will still supply
the DC loads. Plausible because there are electrical interlocks in the AC
electrical distribution system, such as the fast bus transfers between NBN-S01
and NBN-S02 (also NAN-S01-S03; NAN-S02-S04). Also plausible because
MSIV Logic Control Power is fed from the PKA-M41 DC control center and
because a loss of power to the MSIV logic cabinet will result in a 125V IE CC M41
CHGR A/AC PNL D21 TRBL alarm.
B Wrong Incorrect because MSIV Logic Control Power is NOT lost since the battery will
still supply the DC loads. Plausible because the first part is correct. Also
plausible because MSIV Logic Control Power is fed from the PKA-M41 DC
control center and because a loss of power to the MSIV logic cabinet will result in
a 125V IE CC M41 CHGR A/AC PNL D21 TRBL alarm.
C Wrong Incorrect because the interlock is mechanical, not electrical. Also incorrect
because MSIV Logic Control Power is NOT lost since the battery will still supply
the DC loads. Plausible because there are electrical interlocks in the AC
electrical distribution system, such as the fast bus transfers between NBN-S01
and NBN-S02 (also NAN-S01-S03; NAN-S02-S04). Also plausible because the
second part is correct.
D Correct Per Operator Information Manual, 4.16kv to 125vdc Electrical Distribution, page
72 of 88, if PKA-H11 trips, Backup Control Power to AFN-P01 will be lost since
the Battery Charger supply breaker to PKA-M41 is downstream of the breaker for
the AFN-P01 Control Power.
Per Lesson Plan NKASYC128D02, 125 VDC Class IE Power (PK): “Each charger has four breakers associated with it. The supply breaker located at
the MCC, the AC Input and DC Output breakers located on the charger, and the
control center feed breaker located on the 125 Vdc control center. Since the
backup chargers are capable of supplying either control center in its load group, a
mechanical interlock is provided to prevent aligning this charger up to BOTH
control centers at the same time.”

49
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
• DG “A” left bank Starting Air Receiver is under clearance.
• There is an inadvertent “A” train Safety Injection System actuation.
The remaining right bank receiver and starting air subsystem will apply air to (1) diesel cylinder
bank(s) and the “A” DG starts in the (2) mode.
A. (1) both
(2) Test Run
B. (1) both
(2) Emergency
C. (1) only the right
(2) Test Run
D. (1) only the right
(2) Emergency

A

A Wrong Crossover piping allows starting air to be supplied to both banks of diesel
cylinders. The diesel starts in the Emergency run mode of operation on an
inadvertent SIAS.
B Correct Crossover piping allows starting air to be supplied to both banks of diesel
cylinders. The diesel starts in the Emergency mode of operation on an
inadvertent SIAS.
C Wrong Crossover piping allows starting air to be supplied to both banks of diesel
cylinders. The diesel starts in the Emergency run mode of operation on an
inadvertent SIAS.
D Wrong Crossover piping allows starting air to be supplied to both banks of diesel
cylinders. The diesel starts in the Emergency run mode of operation on an
inadvertent SIAS.

50
Q

Given the following plant conditions:
• A loss of offsite power has occurred.
• Diesel Generator ‘A’ has started and is carrying PBA-S03.
• The operator selects “LOWER” on the voltage regulator control switch.
Assuming NO Operator actions (other than those addressed in the choices below), which ONE of the
following identifies the effect, if any, of this action?
A. The indicated amps will rise.
B. The indicated voltage lowers AS the switch is held.
C. The indicated voltage will change ONLY when the DG is taken to override.
D. The VAR meter will move in the counter-clockwise direction AS the switch is held.

A

A Wrong Incorrect because ONLY the internal voltage setting WILL change as the switch
is placed in LOWER. Plausible because, in the Test Start mode, amps will
increase as voltage is lowered if the DG is supplying a leading pF.
B Wrong Incorrect because indicated voltage will NOT change until the DG is in override.
Plausible because the internal voltage setting WILL change as the switch is
placed in LOWER.
Per Lesson Plan NKASYC012711, Emergency Diesel Generator, Page 60:
“When the DG is started in Emergency Mode, the following conditions will exist:
• Diesel generator voltage and frequency are preset
• It is important to note that while in emergency run, the controls will not
affect diesel generator speed or voltage, however the potentiometers for
these circuits are still being adjusted. When the diesel generator is taken
to override, the speed and/or voltage will immediately go to the value
determined by the position of these potentiometers. This may result in
unacceptable speed or voltage transients when the DG is taken to
override.”
C Correct Per Lesson Plan NKASYC012711, Emergency Diesel Generator, Page 60:
“When the DG is started in Emergency Mode, the following conditions will exist:
• Diesel generator voltage and frequency are preset
• It is important to note that while in emergency run, the controls will not
affect diesel generator speed or voltage; however, the potentiometers for
these circuits are still being adjusted. When the diesel generator is taken
to override, the speed and/or voltage will immediately go to the value
determined by the position of these potentiometers. This may result in
unacceptable speed or voltage transients when the DG is taken to
override.”
Per Lesson Plan NKASYC012711, Emergency Diesel Generator, Page 42:
“In the emergency run mode, the governor controls on the local or remote panels
have no effect on the setting of the governor, but in the test mode or in override
they will.”
Per Lesson Plan NKASYC012711, Emergency Diesel Generator, Page 44:
“It is important to note that while in emergency run, the controls will not affect
diesel generator speed or voltage, however the potentiometers for these circuits
are still being adjusted. When the diesel generator is taken to override, the speed
and/or voltage will immediately go to the value determined by the position of
these potentiometers. This may result in unacceptable speed or voltage
transients when the DG is taken to override.”
Per 40ST-9DG01, Diesel Generator A Test, Section 3.2.6:
“Emergency Mode Conditions:
When the engine is started in the emergency run mode, speed and voltage are
maintained automatically. Raise and lower switches will have no effect on
running engine speed or voltage; they will, however, continue to change the
settings of the rheostats.”
D Wrong Incorrect because indicated VARs will NOT change until the DG is in override.
Plausible because the internal voltage setting (and subsequently VARs) WILL
change as the switch is placed in LOWER.

51
Q

Given the following conditions:
• Unit 1 has entered 40AO-9ZZ03. Loss of Cooling Water.
• Essential Cooling Water train “A” has been cross-tied to the Nuclear Cooling Water system.
• An RCS leak into the Nuclear Cooling Water system now occurs.
The Process Radiation Monitoring system will respond by alarming…
A. RU-6, Nuclear Cooling Water, ONLY.
B. RU-2, “A” Essential Cooling Water, ONLY.
C. RU-2, “A” Essential Cooling Water, AND RU-6, Nuclear Cooling Water.
D. RU-2, “A” Essential Cooling Water, ONLY and closing the EW-NC cross-tie
valves.

A

A Wrong Incorrect because RU-2 will alarm, not RU-6. Plausible because the alarm
response for RU-2 directs the Operator to perform the RU-6 alarm response, in
addition to the RU-2 alarm response, if EW is cross-connected to NC. Also
plausible because RU-6 is the normal monitor for the NC System.
Per 74RM-9EF41, Page 13 of 83, Appendix A, Monitor No. RU-2/RU-3:
“If EW is cross-tied to the NC system, concurrently perform RU-6 alarm
response.”
Per Lesson Plan NKASYC010403, Nuclear Cooling Water System, Page 24:
“NOTE: If the NCW system is being supplied by the Essential Cooling Water
System, RU-6 is NOT in the flowpath, the monitor is still on line and would alarm
if contaminated water were to migrate to the detector but it is not expected to
alarm due to no flow through the detector to transport the contamination to the
detector. Under these conditions, either RU-2 (ECWS “A”) or RU-3 (ECWS “B”) is
used to monitor for activity in the NC system depending on what train is
cross-connected to the NCW system.”
B Correct Per Lesson Plan NKASYC010403, Nuclear Cooling Water System, Page 24:
“NOTE: If the NCW system is being supplied by the Essential Cooling
Water System, RU-6 is NOT in the flowpath, the monitor is still on line and
would alarm if contaminated water were to migrate to the detector but it is
not expected to alarm due to no flow through the detector to transport the
contamination to the detector. Under these conditions, either RU-2 (ECWS
“A”) or RU-3 (ECWS “B”) is used to monitor for activity in the NC system
depending on what train is cross-connected to the NCW system.”
C Wrong Incorrect because RU-2 will alarm, not RU-6. Plausible because the alarm
response for RU-2 directs the Operator to perform the RU-6 alarm response, in
addition to the RU-2 alarm response, if EW is cross-connected to NC. Also
plausible because RU-6 is the normal monitor for the NC System.
Plausible because the first part is correct.
D Wrong Incorrect because the EW-NC cross-tie valves will not close on a high radiation
alarm. Plausible because the 1st part is correct and because other systems
have automatic actions when a radiation monitor goes into alarm. For example,
RU-7 will swap discharge from the Auxiliary Steam Condenser Receiving Tanks
from the Main Condenser to the Low TDS Holdup Tank.

52
Q

Given the following conditions:
• Nuclear cooling water has been lost due to a pipe rupture in the yard.
• Essential Cooling Water Train “A” has been cross-connected to supply priority loads.
• No other equipment is out of service or in an abnormal lineup.
WHICH ONE of the following identifies the plant conditions that will isolate essential cooling water to the
Reactor Coolant Pumps?
A. RCS pressure of 1800 psia.
B. HIGH level in EW ‘A’ Surge Tank.
C. Containment pressure of 2.6 psig.
D. LOW pressure in EW ‘A’ Surge Tank.

A

A Correct An RCS pressure of 1800 psia is less than the SIAS setpoint of 1837 psia.
Per Lesson Plan NKASYC010703, Essential Cooling Water System, Page 18:
“The EW to NC cross-tie valves will automatically close on either of the following
signals:
• SIAS
• LO Level in the Surge Tank”
B Wrong Incorrect and plausible because a LOW level, NOT a HIGH level will isolate the
cross-connect valves.
Per 41AL-1RK2A, Panel B02A Alarm Responses, Window No. 2A09A:
Lo Alarm
1. If Train A EW is cross connected to nuclear cooling water, and the EW surge
tank level drops to 17 inches, the EW to NC cross-tie valves (EWA-UV-65/145)
will auto close.
PT. ID POSSIBLE CAUSE SETPOINT
GROUP A
EWLS97 Ess Cooling Water Surge Tank A level Hi-Lo Hi 50 inches
Lo 20 inches
EWLS98 Ess Cooling Water Surge Tank B level Hi-Lo Hi 50 inches
Lo 20 inches
C Wrong Incorrect because 2.6 psig is below the SIAS setpoint of 3.0. Plausible because,
if Containment pressure was greater than 3.0, this would be true and the
cross-connect valves would close.
D Wrong Incorrect because the EW-NC cross-connect valves do NOT close on LOW
pressure in the surge tank. Plausible because the cross-connect valves will
close on LOW level. Also plausible because the ESS CLG WTR SYS TRBL
(Window No. 2A09A) alarm response draws a clear correlation between surge
tank pressure and surge tank level in the NOTE preceding Second Priority Action
1 as follows:
Per 41AL-1RK2A, Panel B02A Alarm Responses, Window No. 2A09A:
“Normal EW surge tank pressure is 0.5 to 2.0 psig. A rising pressure in the EW
Surge Tank may be the result of rising level in the surge tank.”
Conversely, a lowering surge tank pressure may be indicative of a lowering tank
level.

53
Q

Given the following plant conditions:
• The Unit 1 crew has implemented 40AO-9ZZ06, Loss of Instrument Air.
• IAA-UV-2, Outside Cntmt Isol Valve, has failed CLOSED and will not reopen from B07.
• When attempting to align Service Air via the cross-tie, the Cross-Tie filters indicated a need for
replacement (yellow indicator).
In accordance with 40AO-9ZZ06, (1) which ONE of the following actions must be taken to restore the
Containment Instrument Air header and (2) what will be the makeup source?
A. (1) Manually open UV-2, in the East Penetration of the AB 120’ elevation, using
the LOCAL valve operator
(2) Service Air
B. (1) Manually open UV-2, in the East Penetration of the AB 120’ elevation, using
the LOCAL valve operator
(2) Instrument Air
C. (1) Install a temporary modification to route a rubber hose between two valves
on the 90’ elevation inside Containment
(2) Instrument Air
D. (1) Install a temporary modification to route a rubber hose between two valves
on the 90’ elevation inside Containment
(2) Low pressure Nitrogen

A

A Wrong Incorrect because the valve cannot be locally operated. Also incorrect because
the makeup source will be LP Nitrogen, not Service Air. Plausible because a
novice operator may believe that the isolation valve is an AOV or MOV, which
may have a local operator, not a solenoid. Also plausible because the second
part may be correct if the valve could be locally opened. Also plausible because
Step 5 of 40AO-9ZZ06, directs the operator to (manually) open IAA-UV-2,
although from B07, not locally.
B Wrong Incorrect because the valve cannot be locally operated. Also incorrect because
the makeup source will be LP Nitrogen, not Instrument Air. Plausible because a
novice operator may believe that the isolation valve is an AOV or MOV, which
may have a local operator, not a solenoid. Also plausible because the second
part may be correct if the valve could be locally opened. Also plausible because
Step 5 of 40AO-9ZZ06, directs the operator to (manually) open IAA-UV-2,
although from B07, not locally.
C Wrong Incorrect because the makeup source will be LP Nitrogen, not Instrument Air.
Plausible because the first part is correct. Also plausible because a novice
operator may believe that the purpose of the temporary modification is to jumper
around IAA-UV-2 and supply the Containment header from its normal source.
Per NOTE prior to Step 2 in 40AO-9ZZ06, Loss of Instrument Air, Appendix J,
Aligning N2 to the CTMT Instrument Air Header:
“This appendix will install a T-Mod to place Low Pressure N2 in service on the
CTMT IA Header when IAA-UV-2 has failed closed and will not reopen. This
appendix routes a rubber hose between GAN-V062 and IAN-V1036 inside
Containment.”
Per Contingency Action 5.2 of 40AO-9ZZ06, Loss of Instrument Air:
“IF any Instrument Air/Service Air Cross-Tie filter indicate the need for replacing,
THEN consider aligning nitrogen to the Containment Instrument Air header,
REFER TO Appendix J, Aligning N2 to the CTMT Instrument Air Header.”
Plant Event - Unit 3 Loss of IA:
While a Loss of Instrument Air to the Containment can be caused by other
failures, the loss of IA in Unit 3 on 12/3/09 resulted from a failure of the solenoid
on IAA-UV-2, Instrument Air to the Containment Isolation Valve. This failure
brought in an alarm associated with PKA-M41. The alarm, Bus
Undv/Ground/Breaker, cleared when the AO investigated. When instrument air is
lost to containment, it initially results in RCP seal bleed-off flow being redirected
to the RDT via a relief valve as CHA-UV-506 fails closed. Also, RCP Seal
Injection valves fail open and the Charging Line Back Pressure Control Valve
(CHNPDV-240) fails closed.
IIR3-2-90-047: Switching of Air Dryers causes a Loss of Instrument Air, TCS
91-0425, Dec. 18, 1990
D Correct

54
Q

Given the following conditions:
• Containment Building Normal ACU Fans A01A and A01C are running.
• Containment Building Normal ACU Fans A01B and A01D control switches are in Normal After
Stop.
• Fan A01A trips.
Two minutes after the A01A fan trips, fans __(1)___ will be running to help maintain Containment
Air Temperature within the Technical Specification 3.6.5 limit of ___(2)___ °F.
A. 1) A01B and A01D
2) 117
B. 1) A01B and A01D
2) 170
C. 1) A01B and A01C
2) 117
D. 1) A01B and A01C
2) 170

A

A Wrong Incorrect since A01B and A01C will be running, not A01B and A01D. Plausible
because the CEDM Normal ACU fans operate in pairs (B/D and A/C) and a
novice operator may confuse operation of the Containment Building Normal
ACU Fans with the CEDM fans. Also plausible because the 2nd part is correct.
Also plausible because the two minute time provided in the stem is the time
delay for auto-start of the standby CEDM fans.
B Wrong Incorrect since A01B and A01C will be running, not A01B and A01D. Plausible
because the CEDM Normal ACU fans operate in pairs (B/D and A/C) and a
novice operator may confuse operation of the Containment Building Normal
ACU Fans with the CEDM fans. Also incorrect because the TS limit is 117°F,
not 170°F. Also plausible because 170°F is the Containment Temperature
value for harsh conditions in EOPs. Also plausible because the two minute
time provided in the stem is the time delay for auto-start of the standby CEDM
fans.
Per 40EP-9EO03, Loss of Coolant Accident, NOTE prior to Step 1:
“Harsh conditions are containment temperature greater than 170°F or
containment radiation level greater than 108 mR/hr. Harsh containment values
are placed in brackets next to the normal setpoint or band.”
C Correct Per T.S. 3.6.5 LCO:
“3.6.5 Containment Air Temperature
LCO 3.6.5 Containment average air temperature shall be ≤ 117°F.”
Per Lesson Plan NKASYC130B02, Containment Building HVAC, Page 15:
“The fans are all of vane-axial type and are paired together, with each pair
discharging to a common duct. The pair arrangement is the “A” and “B” along
with the “C” and “D”. Under normal conditions, one fan in each pair is operating.
Power is supplied by Class 1E 480 Vac Load Centers.”
Per Lesson Plan NKASYC130B02, Containment Building HVAC, Page 18:
“Upon a trip of an operating fan (sensed by a low D/P across the fan), the other
fan will automatically start after a 60 second time delay as long as its control
switch is in the “Normal After Stop” position.”
D Wrong Incorrect since A01B and A01C will be running, not A01B and A01D. Plausible
because the CEDM Normal ACU fans operate in pairs (B/D and A/C) and a
novice operator may confuse operation of the Containment Building Normal
ACU Fans with the CEDM fans. Also incorrect because the TS limit is 117°F,
not 170°F. Also plausible because 170°F is the Containment Temperature
value for harsh conditions in EOPs.
Per 40EP-9EO03, Loss of Coolant Accident, NOTE prior to Step 1:
“Harsh conditions are containment temperature greater than 170°F or
containment radiation level greater than 108 mR/hr. Harsh containment values
are placed in brackets next to the normal setpoint or band.”

55
Q

Given the following conditions:
• Unit 1 is operating at 50% power.
• Letdown flow is 65 gpm and lowering.
• Charging pumps CHA-P01 and CHE-P01 are running.
• Charging pump CHB-P01 is available.
• RCS temperature is stable.
• PZR level is 40% and lowering at 0.5% per minute.
1. The leakrate IS WITHIN/EXCEEDS the capacity of all three charging pumps with letdown
isolated.
2. Per 40AO-9ZZ02, Excessive RCS Leakrate the following actions should be taken…
A. 1. EXCEEDS
2. Isolate letdown; then start an additional charging pump and trip the reactor.
B. 1. EXCEEDS
2. Start an additional charging pump; then isolate letdown and trip the reactor.
C. 1. IS WITHIN
2. Isolate letdown; if level continues to lower then start an additional charging
pump.
D. 1. IS WITHIN
2. Start an additional charging pump; if level continues to lower then isolate
letdown.

A

A Wrong Pzr level lowering at .5% minute = 33 gallons a minute, which is well within either the
capacity of starting a charging pump or reduction of letdown flow. Two charging
pumps makeup at 88 gpm. Three charging pumps makeup at approximately 130
gpm.
COMMENT ON OVERLAP:
This question was reviewed against the 2013 Operating exam and that there was
enough difference to keep this question on the written exam.
B Wrong
C Wrong Start a charging pump then isolate letdown is the procedural direction
D Correct Per 40AO􀍲9ZZ02

56
Q
What are the power supplies to the Charging Pumps?
1. Charging Pump #1, CHA-P01
2. Charging Pump #2, CHB-P01
3. Charging Pump #3, CHE-P01
A. 1. PGA-L31
2. PGB-L32
3. PGA-L33 or PGB-L34
B. 1. PGA-L31
2. PGB-L32
3. PGA-L35 or PGB-L36
C. 1. PHA-M31
2. PHB-M32
3. PHA-M33 or PHB-M34
D. 1. PHA-M31
2. PHB-M32
3. PHA-M35 or PHB-M36
A

A Wrong L31 and L32 are correct but the power supply to CHE􀍲P01 is incorrect, but are credible
since they are class Load Centers
B Correct As found in the CH01 operating procedure
C/D Wrong The PH designator indicates the 480 vac motor control centers and is wrong since
these pumps come off of the 480 vac LCs. Credible since they are also 480vac class
power and located in the Control Building. PH powers other motors such as EC circ
pump, DG oil transfer pump, DG Jacket Water pump and Condensate transfer pumps

57
Q

Given the following conditions:
• Unit 1 is operating at 80% power following a SNOW outage.
• Group 5 CEAs are 120 inches withdrawn.
• The CRS directs a 10 inch withdrawal for ASI control.
• The operator is monitoring CEA 14 on SEN-JI-17, Selected CEA Position.
• On the 4th step out CEA 16 motion stops due to a Timer Card failure.
• The operator continues the CEA withdrawal.
Which ONE of the following reflects CEA 16s:
1. Reed Switch Position Transmitters, CEACs
2. Board 4 alarms that will be generated
A. (1) 123 inches (2) CEA Withdrawal Prohibit, CWP.
B. (1) 124 inches (2) CEA Withdrawal Prohibit, CWP.
C. (1) 123 inches (2) Automatic Withdrawal Prohibit, AWP.
D. (1) 124 inches (2) Automatic Withdrawal Prohibit, AWP.

A

A Correct 4 x .75 = 3 inches of movement. As the remaining CEAs withdrawl a CWP will be
generated at 5.5 inch deviation within a subgroup.
B Wrong CEAs move ¾ inch with each step not 1 inch. 2nd part is correct 􀍲 CWP
C Wrong 4 x .75 = 3 inches of movement. As the remaining CEAs withdrawl a CWP will be
generated at 5.5 inch deviation within a subgroup. AWP is generated to stop CEA
motion due to temp or SBCS demands
D Wrong CEAs move ¾ inch with each step not 1 inch. AWP is generated to stop CEA motion due
to temp or SBCS demands

58
Q

Given the following plant conditions:
• Unit 1 is operating at 100% power.
• Group 5 CEAs are at 140 inches withdrawn.
• The Reactor Regulating System (RRS) is aligned to average Tavg.
• RCN- TT-111Y (Tcold) input into the RRS fails LOW.
Which ONE of the following conditions has, or could, occur due to this failure?
A. The letdown control valve(s) will modulate open.
B. Prevents a “Quick Open Block” following a reactor trip.
C. Prevents turbine runback demand to RPCS on a cutback.
D. A maximum SG refill demand would be generated following a reactor trip.

A

A Correct Low temperature causes the PLCS to lower its program setpoint causing
the letdown control valves to come open.
B Wrong This would be generated on a hi temp failure. See Appendix B, Page 1 of 3, of
40AO-9ZZ16, RRS Malfunctions.
C Wrong This would be generated on a hi temp failure. See Appendix B, Page 1 of 3, of
40AO-9ZZ16, RRS Malfunctions.
D Wrong This would be generated on a hi temp failure. See Appendix B, Page 1 of 3, of
40AO-9ZZ16, RRS Malfunctions.

59
Q

Given the following conditions:
• The CRS has entered 40EP-9EO03, LOCA, following a major plant transient.
• The hydrogen analyzers indicate 0.4% hydrogen and rising in containment.
• Containment pressure is 4.2 psig and rising.
• Containment Spray flow is adequate.
To prevent exceeding the ___(1)___ limit of 4% hydrogen, 40EP-9EO03 FIRST directs the crew
to place the (2) in service.
A. (1) explosive
(2) Hydrogen Recombiners
B. (1) flammable
(2) Hydrogen Recombiners
C. (1) explosive
(2) Hydrogen Purge Exhaust System
D. (1) flammable
(2) Hydrogen Purge Exhaust System

A

A Wrong Recombiners are placed in service as directed by the LOCA procedure and at
the discretion of the CRS/SM. Placed in service if H2 concentration is > 0.7%
per step 67 of LOCA. Also placed in service when CSAS is actuated (Step 17).
B Correct Recombiners are placed in service as directed by the LOCA procedure
and at the discretion of the CRS/SM. Placed in service if H2 concentration
is > 0.7% per step 67 of LOCA.
C Wrong Use of the H2 Purge Exhaust System is normally limited to when the Hydrogen
D Wrong Recombiners are ineffective.

60
Q

Given the following conditions:
• PCA-P01 (Spent Fuel Pool Cooling Pump A) is operating on the Spent Fuel Pool.
• A large break occurs in the discharge of the pump.
Which ONE of the following will prevent Spent Fuel Pool level from lowering to the point of
uncovering fuel assemblies?
A. Excessive flow check valves will automatically close.
B. PCA-P01 (Spent Fuel Pool Cooling Pump A) will trip on high discharge flow.
C. PCA-P01 (Spent Fuel Pool Cooling Pump A) will trip on low suction pressure.
D. Fuel pool cooling suction piping will become uncovered by the lowering spent fuel
pool level.

A

A Wrong The check valves installed on the discharge of the pump are not excessive flow check
valves as used in other locations in the plant.
B Wrong PC Cooling Pumps are not provided with a high discharge flow trip. Some pumps at
PVNGS do have a high discharge pressure trip.
C Wrong PC Cooling Pumps are not provided with a low suction pressure trip. Some pumps
installed at PVNGS do have a low suction trip.
D Correct Fuel pool cooling suction piping is in the upper level of the SFP

61
Q

Which ONE of the following is the procedural guidance found in the Standard Appendices, 40EP-
9EO10, with regards to establishing feedwater flow if both SGs are dry?
A. Feed both SGs at a maximum of 1000 gpm.
B. Feed only one (1) SG at a maximum of 1000 gpm.
C. Feed both SGs at a maximum of 1600 gpm.
D. Feed only one (1) SG at a maximum of 1600 gpm.

A

A Wrong Fill only one SG as stated in the Std App associated with restoring FW flow to dry SGs.
B Correct Per the procedures 1000 gpm or less and only 1 SG.
C Wrong The max fill rate is 1000 gpm as stated in all of the SA associated with restoring FW
flow to dry SGs. The 1600 gpm is the upper FW flow rate with a dual event; an ESD on
a SG with a tube leak that is releasing to atmosphere.

62
Q

Given the following conditions:
• The Reactor is stable at 50% power.
• The Main Turbine has tripped.
• Normal CEA overlap has been established.
Subsequently
• CEAs are withdrawn 10 inches in Manual Sequential.
If the Steam Bypass Master Controller, SGN-PIC-1010 is in Remote/Auto, which ONE of the
following correctly describes the expected response?
RCS T-cold increases (1) and reactor power (2) .
A. (1) and remains higher (2) increases slightly but returns to 50%
B. (1) and remains higher (2) increases and remains at a higher level
C. (1) then returns to program (2) increases slightly but returns to 50%
D. (1) then returns to program (2) increases and remains at a higher level

A

A Wrong SBCS in auto means it is controlling temperature not power. Examines may
confuse 100% power response with what happens when SBCS is maintaining
the plant. CEA withdrawal at power raises temperature since the turbine is
maintaining power.
This is an old PVNGS event, in an attempt: following a turbine trip the crew was
attempting to raise temperature by withdrawing CEAs. The operator pulled CEAs
until a VOPT trip occurred.
B Wrong
C Wrong
D Correct Tcold will increase as CEAs are withdrawn then return to program as the
SBCS controls temperature. Power increases due to the positive reactivity

63
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
• Main Turbine Control and Stop valve testing is about to commence.
Which ONE of the following is a set of plant perturbations and an associated mitigating action
identified in 40OP-9MT02, Main Turbine?
A. 1. Due to swings in RCS temperature, ensure CEDMCS is in Auto Sequential.
2. Due to deviations between steam flow transmitters, place DFWCS in single
element control.
B. 1. Due to swings in RCS temperature, ensure CEDMCS is not in Auto
Sequential.
2. Due to deviations between steam flow transmitters, place DFWCS in single
element control.
C. 1. Due to swings in RCS temperature, ensure CEDMCS is in Auto Sequential.
2. Due to oscillations in RCS pressure, place the Pressurizer in Boron
Equalization.
D. 1. Due to swings in RCS temperature, ensure CEDMCS is not in Auto
Sequential.
2. Due to oscillations in RCS pressure, place the Pressurizer in Boron
Equalization.

A

A Wrong Per 40OP-9MT02, Personnel Indoctrination 7:
All plant control systems should remain in the “automatic” mode of control when
possible, with the exception of the CEDMCS system, which shall be placed in
one of the “manual” modes as directed prior to testing, due to the Tave and Tref
difference which may occur, causing undesired CEA movement.
Incorrect because, under the Given Conditions, the procedure does NOT direct
the crew to place, or consider placing, the DFWCS in Single Element control.
Plausible because Personnel Indoctrination 8 states that testing may cause the
DFWCS to go into Single element control, but does not direct use of Single
element control. Personnel Indoctrination 6 admonishes the crew to minimize
time in Single Element control.
Per 40OP-9MT02, Personnel Indoctrination 8:
Main Turbine testing may place the DFWCS in Single Element control or switch
transmitters out of average due to steam flow oscillations.
Also plausible because Personnel Indoctrination 4 states:
Main Turbine Stop Valve testing with a steam flow transmitter out of service and
in maintenance, will be performed with the DFWCS in Single Element control due to the lower magnitude of S/G level oscillations, which are predicted to be up to
7% NR.
B Wrong Incorrect because the procedure does NOT direct the crew to place, or consider
placing, the DFWCS in Single Element control. Plausible because Personnel
Indoctrination 8 states that testing may cause the DFWCS to go into Single
element control, but does not direct use of Single Element control. Personnel
Indoctrination 6 admonishes the crew to minimize time in Single Element control.
Plausible because the 1st part is correct.
C Wrong Incorrect because the procedure does NOT direct the crew to place, or consider
placing, the DFWCS in Single Element control. Plausible because Personnel
Indoctrination 8 states that testing may cause the DFWCS to go into Single
element control, but does not direct use of Single Element control. Personnel
Indoctrination 6 admonishes the crew to minimize time in Single Element control.
Also plausible because Personnel Indoctrination 4 states:
Main Turbine Stop Valve testing with a steam flow transmitter out of service and
in maintenance, will be performed with the DFWCS in Single Element control due
to the lower magnitude of S/G level oscillations, which are predicted to be up to
7% NR.
Also plausible because the 2nd part is correct.
D Correct Per 40OP-9MT02, Personnel Indoctrination 7:
All plant control systems should remain in the “automatic” mode of control when
possible, with the exception of the CEDMCS system, which shall be placed in
one of the “manual” modes as directed prior to testing, due to the Tave and Tref
difference which may occur, causing undesired CEA movement.
A NOTE prior to Step 4.6.3.5 states:
NOTE
RCS pressure oscillations may be experienced during Control Valve testing.
Consideration should be given to going to Boron Equalization in the Pressurizer
while performing this test.

64
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
• RU-31, Spent Fuel Pool Area, monitor exceeds the high trip setpoint.
• The Fuel Building Normal Supply and Exhaust units have stopped.
• The Control Room Essential AHUs have started.
Which ONE of the following describes the response of the Fuel Building Essential Air Filtering
Unit A and the Control Room Essential Air Handling Units Outside Air Intake Damper?
FB Ess AFU A CR Ess AHUs OSA Damper
A. Started Open
B. Started Closed
C. Stopped Open
D. Stopped Closed

A

A Correct According to 40OP-9SA01, BOP/ESFAS Module Operation, Appendix F,
FBEVAS Actuated Equipment Train A and B, page 1 of 1:
Fuel Bldg. Ess Exh Damper M05/Fuel Bldg. Ess AFU A, the Actuated
Condition is Open/Started.
According to 40OP-9SA01, BOP/ESFAS Module Operation, Appendix G,
CREFAS, Actuated Equipment Train A:
Contl Rm Ess AHU A (B) OSA Intake Damper M01 (M03) Actuated
Condition is Open.
B Wrong Incorrect because the OSA damper opens, not closes. Plausible because the 1st part is
correct. Also plausible because a novice operator may deduce that, in a high radiation
condition, it would be logical to isolate all paths to the environment.
C Wrong Incorrect because the FB AFU starts, not stops. Plausible because the 2nd part is
correct.
D Wrong Incorrect because the OSA damper opens, not closes. Also incorrect because the FB
AFU starts, not stops. Plausible because a novice operator may deduce that, in a high
radiation condition, it would be logical to isolate all paths to the environment.

65
Q

Given the following conditions:
• Unit 1 is at 80% power.
• You are a trainee performing OJT duties on shift.
• The unit is staffed with 3 Reactor Operators.
• You are under the direct supervision of the third RO, (TRO).
1. Which of the following evolutions are specifically listed in Operations Department Practices,
ODP-1 as requiring a Peer Check? (not all inclusive)
2. If you as the trainee were to perform an manipulation requiring a Peer Check who could
provide it?
A. (1) All B01 manipulations and Turbine Load Adjustments
(2) Reactor or Control Operators ONLY.
B. (1) All B01 manipulations and Turbine Load Adjustments
(2) Reactor, Control or Third Reactor Operator.
C. (1) All B03 manipulations and CEA manipulations from B04
(2) Reactor or Control Operators ONLY.
D. (1) All B03 manipulations and CEA manipulations from B04
(2) Reactor, Control or Third Reactor Operator.

A

A Correct Per ODP􀍲1 and Conduct of Shift Operations
B Wrong All B01 manipulations and Turbine Load adjustments require a Peer check. But the
operator who is supervising the examinee cannot perform the peer check because
they are considered the “performer”. Plausible because the 1st half is correct and ROs
on shift are required to perform peer checks.
C Wrong Not ALL manipulations on B03 require a peer check but the boration/dilution and CEA
manipulations do, making this plausible. Plausible because the ROs on shift are
required to perform peer checks.

66
Q

Per 40AC-0ZZ06, (Locked Valve, Breaker, and Component Control), when verifying the position of
a locked throttled valve, the second checker MUST:
A. independently verify the valve is throttled by position indication, then lock it.
B. independently check the valve closed and return it to throttled position and install
lock.
C. concurrently verify the correct throttled position and verify the lock installed
correctly.
D. concurrently verify the valve is throttled by position indication, then independently
verify position by alternate verification methods and install lock.

A

A Wrong Incorrect since throttled valves must be concurrently verified. Plausible
because this is similar to a second check described in Step 4.2.4.2 of
40AC-0ZZ06: “The person performing the second check shall verify that the
valve, breaker, or component is in the required position using local and remote
indication where possible per 02DP-0ZZ01 and verify that the locking device is
locked.”
B Wrong Incorrect since throttled valves must be concurrently verified. Plausible
because this is similar to a second check described in Step 4.2.4.3: “If the
second checker can not determine the position of the locked valve, breaker, or
component, the CRS may authorize removal of the lock and the use of
concurrent verification to place the valve, breaker, or component in the locked
position per 02DP-0ZZ01.”
C Correct Per 40AC-0ZZ06, Locked Valve, Breaker, and Component Control:
“4.2.4.4 For valves placed in a throttled position, the person performing the
second check shall perform the verification concurrently with the initial
manipulation of the valve. The person performing the second check shall then
verify that the locking device is installed and locked.”
D Wrong Incorrect since the independent verification by alternate methods is not required.
Plausible because this is similar to a second check described in Appendix B,
Step 1.7.2 of 02DP-0ZZ01, Verification of Plant Activities:
“1.7 Alternative Verification Methods
1.7.1 Performance of Alternative Verification Methods 1.7.2, 1.7.3 and 1.7.4 in
lieu of those verification methods listed in step 1.6 shall be authorized by the Shift
Manager and documented in a retrievable document.
1.7.2 Process parameters (i.e., flow, pressure, current, voltage, etc.)
If using process parameters as a second verification ensure the check is valid by
considering alternate flow paths or other conditions that could result in false
indications.”

67
Q

Given the following conditions:
• A Temporary Approved Procedure Action (TAPA) is required due to a procedure deficiency.
• The task cannot be completed without a change to the procedure.
• The proposed change meets all the requirements of 01DP-0AP01, Procedure Process.
• The change has been approved by two members on the plant supervisory staff including the
Shift Manager.
After the TAPA is approved for use it…
A. will be cancelled upon completion of the task.
B. is routed as a permanent procedure change with no further review required.
C. must undergo completion of an Independent Quality Review (IQR) and Owner
approval within 4 days.
D. must undergo completion of an Independent Quality Review (IQR) and Owner
approval within 14 days.

A

A Wrong It would be reasonable for the examinee to believe that a “temporary “ change would
be cancelled upon completion of the specific task
B Wrong It would be reasonable for the examinee to believe that once all the required reviews
for the TAPA have been completed and the procedure change has been used then no
further reviews would be required to make the change permanent.
C Wrong Incorrect because 14 days is allowed, not 4. Plausible because 4 days is the review
time for a “minor” revision
D Correct Per 4.12.5.2 of Procedure Process:
4.12.5 Post-Approval Process
4.12.5.1 The Procedure Preparer notifies the Procedure Owner that the
TAPA has been approved for use.
4.12.5.2 Completion of an IQR review and Owner approval of the TAPA
must occur within 14 days of the TAPA change.

68
Q

Which one of the following meets the MINIMUM requirements of 40DP-9OP29, Power Block
Clearance and Tagging with regards to High Energy systems?
Fluid or gas systems that operate with temperatures greater than (1) should be isolated by two
valves in series and (2) .
A. (1) 200°F (2) if possible OPEN a vent or drain between the two closed isolation
valves.
B. (1) 200°F (2) ensure there are NO open vents or drains between the two closed
isolation valves.
C. (1) 500°F (2) if possible OPEN a vent or drain between the two closed isolation
valves.
D. (1) 500°F (2) ensure there are NO open vents or drains between the two closed
isolation valves.

A

A Correct Per the procedure
B Wrong Examinee may believe that closing the vents and drains is required to prevent any
release of energy if a leak develops in the first isolation valve
C Wrong 500 relates to the high energy pressure limit of 500 psig.
D Wrong

69
Q

Given the following conditions:
• A motor-operated ESF valve is disabled and unable to perform its function.
• The valve is NOT alarmed.
• The impairment will last more than one shift.
In accordance with 40DP-9OP02, Conduct of Shift Operations, the operating crew shall…
A. perform and document an IV of the valve’s position.
B. rack out the valve breaker after it has been disabled.
C. hang a Yellow Caution Tag on the valve’s handswitch.
D. insert a manual SESS alarm associated with the valve.

A

A Wrong Incorrect since an IV is not required by 40DP-9OP02. Plausible because this
could be one method of tracking the valve’s status.
B Wrong Incorrect since racking the breaker out is not required by 40DP-9OP02.
Plausible because this could be one method of tracking the valve’s status.
C Wrong Incorrect since hanging tags on the valve is not required by 40DP-9OP02.
Plausible because this could be one method of tracking the valve’s status.
D Correct There is no alarm to alert operations that the ECCS system is out of its
normal alignment/status so the manual SESS alarm is inserted.
Per 40DP-9OP02, Conduct of Shift Operations:
6.2.1 A manual SESS alarm input shall be initiated when any ES
annunciator panel monitored component or system is either:
• Disabled and unable to perform its function by any method that is not
alarmed
• Rendered incapable of performing its design function by any method that
is not alarmed
The impairment may be the result of a Permit, T-mod., procedural
alignment, or component failure.
6.2.2 The manual SESS alarm is required if the impairment or failure is
anticipated to last longer than the current shift.

70
Q

Which ONE of the following correctly identifies the Federal Exposure Limits?
A. 1.5 Rem/year, Whole Body and 15 Rem/year Eye Dose.
B. 1.5 Rem/year, Whole Body and 50 Rem/year Eye Dose.
C. 5 Rem/year, Whole Body and 15 Rem/year Eye Dose.
D. 5 Rem/year, Whole Body and 50 Rem/year Eye Dose.

A

A Wrong 1.5 is the first PVNGS hold point
B Wrong 1.5 is the first PVNGS hold point and 50 is the extremities limit
C Correct 5 whole body and 15 eyes are both correct
D Wrong 5 is correct but 50 is the extremities limit not eyes.

71
Q

Given the following conditions:
• RU-37, Power Access Purge “A”, is in HIGH alarm.
• RU-38, Power Access Purge “B”, is in HIGH alarm.
• RU-34, Containment Building Refueling Purge, is in HIGH alarm.
74RM-9EF41, Radiation Monitoring System Alarm Response, requires the operator to verify
CPIAS and CREFAS have actuated.
Which ONE of the following describes the reason for performing this action?
A. CREFAS and CPIAS both actuated off the RU-37/38 HIGH alarms.
B. CREFAS actuated off the HIGH alarms; CPIAS actuated off the cross trip.
C. CPIAS actuated off the HIGH alarms; CREFAS actuated off the cross trips.
D. CPIAS actuated off the RU-37/38 HIGH alarms; CREFAS actuated off the RU-34
HIGH alarm.

A

A Wrong BOTH CREFAS and CPIAS will be actuated, RU-37/38 actuate a CPIAS which
B Wrong will cause a cross trip of CREFAS.
C Correct RU-37/38 actuate a CPIAS, CREFAS actuates off the cross trip.
D Wrong CREFAS is actuated off RU-29/30 high alarms not RU-34.

72
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
Subsequently
1. The running Plant Cooling Water pump faults and trips.
2. The standby Plant Cooling Water pump does not auto-start.
3. Attempts to manually start the standby pump have failed.
Which ONE of the following was the correct use of procedures?
Implement a(n) (1) when attempting to start the standby Plant Cooling Water pump, then
transition to a(n) (2)
A. (1) Normal Operating procedure (2) General Operating procedure
B. (1) Abnormal Operating procedure (2) General Operating procedure.
C. (1) Normal Operating procedure (2) Abnormal Operating procedure
D. (1) Abnormal Operating procedure (2) Emergency Operating procedure

A

A Wrong OPs are used for switching pumps under normal conditions; GOP is plausible if the
examinee does not realize that a reactor trip is required for a loss of PCW.
B Wrong GOP is plausible if the examinee does not realize that a reactor trip is required for a
loss of PCW.
C Wrong OPs are used for switching pumps under normal conditions; EOP – SPTAs and Reactor
Trip will be implemented
D Correct AOP for the abnormal condition followed by the EOP after the reactor is tripped

73
Q

Given the following conditions:
• Unit 1 has tripped from 100% power.
• SPTAs are complete and the CRS has implemented the appropriate EOP.
• You have been directed to perform a Standard Appendix.
• You determine that a step on the left side column cannot be completed.
What should be done if the contingency action cannot be completed either?
A. Proceed to the next step in the left hand column.
B. Proceed to the next step in the right hand column.
C. Exit the Appendix/EOP and enter the Functional Recovery Procedure.
D. Progress thru the Standard Appendix must be halted until the step can be
completed.

A

A Correct Per the EOP users guide
B Wrong This is normal procedure progression to stay in the column you are in
C Wrong If conditions cannot be met such as safety functions then exit to the FRP is reasonable
D Wrong This would be true for an OP

74
Q

Given the following conditions:
• Unit 1 tripped on DNBR LO.
• SIAS/CIAS have auto actuated.
• Containment pressure is 2.8 psig and slowly rising.
• The CRS has implemented 40EP-9EO03, LOCA.
• The 1A and 2A RCPs have been secured, RCPs 1B and 2B are running.
• Reactor Drain Tank HI pressure and temperature alarms have annunciated.
• Reactor Vessel Level Monitoring System readings have been erratic.
• RCS T-cold is 560°F and stable.
• RCS pressure is 1800 psia and stable.
• Pressurizer level is 33% and stable
• HPSI throttle criteria has been met.
• The RO has closed the “A” train HPSI injection valves.
• The CO has initiated a 40°F/hr cooldown.
• The RO has initiated main spray flow to de-pressurize the RCS.
30 minutes later:
• RCS T-cold is 540°F and lowering.
• RCS pressure is 1790 psia and stable.
• Pressurizer level is 55% and rising.
Which ONE of the following is the cause and associated mitigation strategy identified in the LOCA
procedure?
A. Safety Injection flow is not adequate; perform Std App -15, RCS Void Control.
B. A void has formed in the Reactor Vessel Upper Head; perform Std App -15,
RCS Void Control.
C. Safety Injection flow is not adequate; vent the RCS per Std App -115,
Depressurizing the RCS for Inventory Control.
D. A void has formed in the Reactor Vessel Upper Head; vent the RCS per Std
App -115, Depressurizing the RCS for Inventory Control.

A

A Wrong Safety Injection flow is adequate.
B Correct VOID is forming in the RVUH, LOCA directs the use of SA􀍲15
C Wrong Safety Injection flow is adequate.
D Wrong Not directed by LOCA for Void control

75
Q

Given the following conditions:
• Unit 1 tripped from 100% power.
• The crew has implemented 40EP-9EO03, LOCA.
• SIAS/CIAS/MSIS have actuated.
• RCPs 1A and 2A have been secured.
• A cooldown and depressurization to SDC entry conditions has commenced.
• The cooldown was started 70 minutes ago.
Current conditions:
• RCS Tcold is 396°F.
• RCS Thot is 399°F.
• REP CET is 407°F.
• RCS pressure is 1500 psia.
• Containment pressure is 5.2 psig and slowly lowering.
• Containment temperature is 185°F and slowly lowering.
Which ONE of the following would be the proper implementation of step 37 (provided) of the
LOCA procedure? (Std App 2 is provided)
A. P/T limits have been exceeded; continued cooldown is permitted but at a lower
rate.
B. P/T limits have NOT been exceeded; continue the cooldown/depressurization at
the current rate.
C. P/T limits have been exceeded; stop the cooldown and depressurize the RCS.
Because the cooldown limits have been exceeded an RCS “soak” is required
before the cooldown can be continued.
D. P/T limits have been exceeded; stop the cooldown and depressurize the RCS.
There is no requirement to “soak” the RCS, cooldown may continue once the
RCS has been restored to within the P/T limits.

A

A Wrong CD rate limits have been exceeded. The examinee must evaluate conditions to
determine this. Not permitted to continue a soak is required. Plausible because this part
of the answer is correct but further evaluation will detrermine that the more restrictive
limit has also been exceeded.
B Wrong Examinee may pick this if they use the “Normal” containment curves or REP CET
temperature. Making this a plausible choice/evaluation.
C Correct The examinee must properly evaluate Thot and “HARSH” curve to determine that
the 200° limit has been exceeded. Then they must determine that the CD rate has
been exceeded and therefore a “soak” is required.
D Wrong Examinee must correctly interrupt contingency action 37.2 to determine that a soak is
required. Since the candidate must evaluate graphs and curves this choice is one of
choices that could be made.

76
Q

Given the following conditions:
• Unit 1 tripped from 100% power due to a Loss of the 525 kV switchyard.
• Conditions have required the CRS to enter 40EP-9EO08, Blackout.
• SG levels are 50% WR and lowering.
• RCS pressure is 2050 psia slowly lowering.
• RCS Tcold is 562°F and stable.
• RCS Thot is 585°F and stable.
• REP CET temperature is 592°F and stable.
• AFA-P01, Turbine Driven AFP was feeding each SG at 150 gpm, but has been secured.
• Reactor Makeup Water tank level is 36 feet.
• The Condensate Storage Tank has been damaged and level is 4 feet and lowering.
(1) Natural Circulation conditions
(2) SG feed flow can be restored by implementing Standard Appendix …
A. (1) have been established (2) 45, Feeding Unit 1 SGs with the Unit 2
Condensate Pumps.
B. (1) have been established (2) 42, Aligning Essential Aux Feedwater Pumps
Suction to RMWT.
C. (1) have NOT been established (2) 45, Feeding Unit 1 SGs with the Unit 2
Condensate Pumps.
D. (1) have NOT been established (2) 42, Aligning Essential Aux Feedwater
Pumps Suction to RMWT.

A

A Wrong Nat’l Circ conditions have been established (refer to Blackout procedurereferences).
Std App 45, Condensate Pumps would be legitimate for a single
unit LOOP event or other LOAF scenarios but will not work for a loss of 525kV
grid event. This is plausible because part 1 is correct
B Correct Nat’l Circ conditions have been established (refer to Blackout procedurereferences).
Blackout procedure directs the use of SA 42 if CST level is
below 9 feet and cannot be recovered or filled.
C Wrong Nat’l Circ conditions have been established (refer to Blackout procedurereferences).
Plausible because using ther other units Condensate pumps is a
procedurally directed step although it will not work for a LOOP.
D Wrong Nat’l Circ conditions have been established (refer to Blackout procedurereferences).
Part two is correct making this plausible.

77
Q

Given the following conditions:
• Unit 2 has tripped from 100% power due to a Loss of Offsite Power.
• AFB-P01, Essential Aux Feed Pump is feeding the SGs at 350 gpm.
• PKA-M41, Class 125Vdc bus has faulted and is de-energized.
• 40EP-9EO07, Loss of Offsite Power/Loss of Forced circulation has been entered.
• MSIS has been manually actuated.
Subsequently
• AFB-P01, Essential Aux Feed Pump faults.
Which ONE of the following describes the appropriate actions?
A. Remain in LOOP/LOFC, AFW flow can be restored by starting AFA-P01 from
the Control Room.
B. Remain in LOOP/LOFC, AFW flow can be restored by starting AFN-P01 and
then overriding and opening the downcomer isolation valves.
C. Transition to 40EP-9EO06, Loss of all Feedwater and restore AFW flow by
implementing SA 40, Local Operation of AFA-P01 using Main Steam.
D. Transition to 40EP-9EO06, Loss of all Feedwater and use 40AO-9ZZ13, Loss
of Class Instrument or Control Power to shift AFN-P01 control power to PKAH11
then restore AFW flow using AFN-P01.

A

A Wrong The combination of LOOP and loss of M41 (prevents DG A from starting) means that
the only energized bus is PBB􀍲S04 so the crew must transition to LOAF to restore AFW
flow.
B Wrong
C Correct LOAF will allow the crew to use manual operation of AFA􀍲P01 (SA􀍲40) to recover
AFW flow. The SFSCs is met for LOAF so entry to the FRP is not mandatory.
D Wrong ZZ13 does transfer control power to the A battery charger but PBA􀍲S03 is de􀍲energized
with no DG A running

78
Q

With regards to the (EW) Essential Cooling Water system in mode 1, which of the following is the
correct application of Tech Specs?
(1) When cross connected to the Nuclear Cooling Water (NCW) system, EW is INOPERABLE…
(2) When cross connected to the Fuel Pool Cooling, EW is INOPERABLE…
A. (1) and remains inoperable while cross connected.
(2) and remains inoperable while cross connected.
B. (1) and remains inoperable while cross connected.
(2) but operability can be restored if a flow balance is performed because the
EW system is sized to supply the SDC heat exchanger, Essential Chiller and
the SFP heat exchanger.
C. (1) but operability can be restored if a flow balance is performed because the
EW system is sized to supply the NCW priority loads and the SDC heat
exchanger.
(2) and remains inoperable while cross connected.
D. (1) but operability can be restored if a flow balance is performed because the
EW system is sized to supply the NCW priority loads and the SDC heat
exchanger.
(2) but operability can be restored if a flow balance is performed because the
EW system is sized to supply the SDC heat exchanger, Essential Chiller and
the SFP heat exchanger.

A

A Wrong Operability is not restored for EW when cross tied to NC even if a flow balance is
completed. EW is not sized to supply both NC priority loads and the SDC heat
exchanger.
EW is sized to carry the SFP heat exchanger, Essential chiller and the SDC heat
exchanger.
Operability is restored if a flow balance is completed after cross ting to Fuel Pool
Cooling.
Distracters A and D are plausible because one part of the answer is correct.
Distracter C is plausible because the answers are true for the opposite condition

79
Q
Given the following conditions:
• Units 1-3 all operating at 100% power.
• Unit 2 has DG "A" out of service for scheduled maintenance.
Subsequently
• Startup transformer NAN-X01 faults and is de-energized.
Refer to the provided Tech Spec to determine which ONE of the following is the correct application of the
LCO 3.8.1.
Unit - (1)
Unit - (2)
Unit - (3)
A. (1) enters condition C only.
(2) enters conditions A and B only.
(3) no condition entry is required.
B. (1) no condition entry is required.
(2) enters conditions A and B only.
(3) no condition entry is required.
C. (1) enters condition C only.
(2) enters condition D as well as LCO 3.8.9 due to a de-energized AC bus only.
(3) enters condition A only.
D. (1) no condition entry is required.
(2) enters condition D as well as LCO 3.8.9 due to a de-energized AC bus only.
(3) enters condition A only.
A

A Wrong Examinee may choose this if they don’t know the switchyard distribution scheme and
realize that the A DG and X01 secondary winding are on the same class bus or that X01
is the backup supply to U1 and the normal supply to U3􀍲S06.
B Wrong
C Wrong Examinee may choose this if they do not understand that the alternate supply to the
class buses would not require entry into the LCO
D Correct These are correct for the switchyard scheme and application of the LCO 3.8.1

80
Q

Given the following conditions:
• Unit 1 is in a refueling outage.
• Core offload is in progress.
• It is reported that a fuel assembly has been dropped in the Spent Fuel pool.
• RU-31 is in alert alarm
• RU-145 is in high alarm.
• RU-146 channel 1 reads 2.13E-01 uCi/cc.
• No field survey reports have been received at this time.
Based on these conditions, this event should currently be classified as a(n)…
(EAL table provided)
A. Unusual Event
B. Alert
C. Site Area Emergency
D. General Emergency

A

A Wrong Various monitors in alert or RU-145 reading > 1.13E-01 uCI/cc would be an alert
but readings are higher
B Correct Meets alert criteria
C Wrong RU-146 readings must be considered but levels have not reached these criteria
D Wrong

81
Q

Given the following conditions:
• Unit 1 is in Mode 3.
• Pressurizer level is 32% and stable.
• Letdown flow is 60 gpm and stable.
• 2 charging pumps are operating.
• Containment temperature is 90°F and stable.
• RU-1, Containment Atmosphere is stable.
• RU-6, Nuclear Cooling Water System is stable.
• RU-141, Condenser Vacuum/Gland Seal Exhaust is in Alert with a rising trend.
• RU-142, (all channels) Main Steam Line N-16 monitor trends are rising.
Which ONE of the following is the correct application of procedures for this event?
The CRS should implement….
A. 40AO-9ZZ02, Excessive RCS Leakrate and isolate letdown.
B. 40EP-9EO11, Lower Mode Functional Recovery and isolate letdown.
C. 40AO-9ZZ02, Excessive RCS Leakrate and take actions to minimize release to
atmosphere.
D. 40EP-9EO11, Lower Mode Functional Recovery and take actions to minimize
release to atmosphere.

A

A Wrong Pzr level is stable so not required to isolate letdown
B Wrong Do not meet LMFRP entry conditions
C Correct Per section 5 perform app C to minimize release to atmosphere
D Wrong Do not meet LMFRP entry conditions

82
Q

Given the following conditions:
• Unit 1 is stable at 220°F.
• Preparations are being made for a plant heat-up.
• An RO reports that all B06 position indications for SGB-HS-221, SG sample valve are out.
• The valve has been stroked and all lights remain extinguished.
Which ONE (if any) is the maximum time limit with regards to LCO 3.6.3, Containment Isolation
Valves?
A. LCO 3.6.3 is not applicable in the current mode.
B. SGA-UV-220 must be closed and de-energized within 1 hour.
C. SGA-UV-220 must be closed and de-energized within 4 hours.
D. SGA-UV-220 must be closed and de-energized within 24 hours.

A

A Wrong Mode 4 LCO does apply
B Wrong Action for two CI valves INOP
C Correct Per condition A of LCO 3.6.3
D Wrong Purge valve leakage not within limits

83
Q

Given the following conditions:
• Unit 1 is operating at 55% power.
• Main Feedpump A is in service.
• Main Feedpump B is in standby.
• AFA-P01 is out of service for scheduled maintenance.
Subsequently
• The reactor trips due to a complete loss of vacuum.
• PBA-SO3, normal supply breaker, PBA-S03L, has an 86 lockout trip and has tripped open.
• DG “A” starts but it’s output breaker, PBA-S03B, did not close.
• AFB-P01 trips when started.
Which ONE of the following procedures should be used to establish feedwater flow?
A. 40EP-9EO09, FRP, implement MVAC-2; DGs.
B. 40EP-9EO09, FRP, implement HR-1; SG with no SI.
C. 40EP-9EO06, LOAF, implement Standard Appendix 43, Restarting MFPs.
D. 40EP-9EO06, LOAF, implement Standard Appendix 41, Local Operation of
AFN-P01.

A

A Wrong Examinee may not realize that the bus will not energize with an 86 LO on PBA􀍲S03L
B Correct SA 44 would be directed by HR􀍲1 to restore FW flow
C Wrong Could believe that the B MFP could be available to restore FW flow but loss of vacuum
trips the MFPs
D Wrong This is an available success path in the LOAF procedure and therefore credible but the
candidate must determine that AFN􀍲P01 has no power source available at this time.

84
Q

Given the following conditions:
• Unit 1 had been operating at 100% power.
• A large break has occurred on the RCS 1A cold leg.
• Automatic reactor trip on low DNBR.
• 40EP-9EO03, LOCA has been implemented.
• RAS has actuated.
• All RAS automatic and manual actions are complete.
Subsequently
• Emergency Core Cooling System (ECCS) pumps display the following characteristics…
Pump Discharge Pressure Flow Amps
HPSI Pump A Steady Steady Steady
CS Pump A Steady Steady Steady
HPSI Pump B Lowering Lowering Erratic
CS Pump B Lowering Lowering Erratic
The CRS should direct the crew to…
A. Immediately stop CS pump “B”; go to 40EP-9EO09, FRP.
B. Immediately stop BOTH CS pump “B” and HPSI pump “B”; remain in 40EP-
9EO03, LOCA.
C. Immediately stop BOTH CS pump “B” and HPSI pump “B”; go to 40EP-9EO09,
FRP.
D. Immediately stop CS pump “B”, evaluate HPSI pumps performance; remain in
40EP-9EO03, LOCA.

A

A Wrong These actions are performed in LOCA there is no need to go to FRP still have one good
CS pump
B Wrong Both pumps are stopped in the contingency actions and stopping the pumps would
seem reasonable to prevent pump damage.
C Wrong Both pumps are stopped in the contingency actions and stopping the pumps would
seem reasonable to prevent pump damage.
D Correct As directed by the LOCA procedure

85
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
• The RJ point SAYS65, CSAS A Leg 1 - 3 trip, is in alarm.
• ONLY the following alarm windows have actuated:
Using the provided picture of B05 and LCOs 3.3.5 and 3.3.6, determine which ONE of the following
is the correct application of Tech Specs?
A. Enter LCO 3.3.5, Condition A.
B. Enter LCO 3.3.6, Condition A.
C. Enter LCO 3.3.6, Condition B.
D. Enter LCO 3.3.6, Condition D.

A

A Wrong Any time an ESFAS function alarms the first choice would be a transmitter failure
affecting LCO 3.3.5. The examinee has to determine with no other alarms in that no
transmitter failed.
B Wrong If the examinee does not understand the relationships between matrix, initiation and
actuation functions this would be a viable choice due to multiple windows in alarm.
C Correct This is an initiation failure, good transmitters and the initiation light extinguished.
D Wrong If the examinee does not understand the relationships between matrix, initiation and
actuation functions this would be a viable choice but no actuations have actually
occurred.

86
Q

Given the following conditions:
• Unit 1 was manually tripped from 100% power due to lowering pressurizer level.
• The CRS has entered 40EP-9EO03, LOCA.
• Containment pressure is 9.0 psig and rising.
• Containment level is indicated.
• RCPs are off and controlled bleedoff is isolated.
• Containment Spray flow instrument SIA-FI-338 indicates 3700 gpm.
• The “B” train SESS window 16J, CS PUMP B P03 status is:
􀂾 White SEIS light in alarm.
􀂾 Blue SEAS light in alarm.
Which ONE of the following is correct regarding the status and required actions (if any) associated
with the CTPC safety function?
Containment Temperature and Pressure Control safety function is currently….
A. met: with Containment pressure < 55psig and CS flow indicated, remain in the
LOCA procedure.
B. not met: transition to 40EP-9EO09, FRP and implement CTPC-1 to restore
Containment Fans.
C. not met: transition to 40EP-9EO09, FRP and implement CTPC-2 to align LPSI
pump “B” to the “B” CS header.
D. met: CS pump B failed to auto start, start the pump by going to start on SIB-HS-6,
remain in the LOCA procedure.

A

A Wrong Cntmt pressure < 55# and 4350 gpm would meet criteria.
B Wrong CTPC-1 could be used if Cntmt level is not indicated.
C Correct CTPC-2 directs x-tying LPSI to the CS hdr
D Wrong The CS pump could be in this condition during an inadvertent CS when the crew
is directed to “anti-pump” the breaker to stop CS flow. In that case resetting the 86
would start the pump. SF would be met if a fail to auto start is the only fault.

87
Q

Given the following conditions:
• Unit 1 is coming out of a SNOW outage.
• RCS pressure is 2250 psia.
• RCS temperature is 450°F and rising.
• RCPs 1A, 2A and 1B are operating.
• Alarm window 4A03A RCP 1B TRB is alarming.
• RCP 1B has the following indications
􀂾 RCN-PI-153, No. 2 Seal Outlet Pressure - 1750 psig and stable
􀂾 RCN-FI-166, Controlled Bleedoff flow 10.1 gpm and rising.
􀂾 RCN-HV-431, RCP 1B Controlled Bleedoff valve is OPEN.
􀂾 CHN-FIC-242, RCP 1B Seal Injection Flow Control 5.8 gpm and stable.
Evaluate the above readings and determine which ONE of the following actions should be taken?
A. Enter 40OP-9RC01, Reactor Coolant Pump Operation; Stop RCP 1B and
maintain seal bleedoff in service.
B. Enter 40AO-9ZZ04, Reactor Coolant Pump emergencies; Stop RCP 1B and
maintain seal bleedoff in service.
C. Enter 40OP-9RC01, Reactor Coolant Pump Operation; Stop RCP 1B and close
RCN-HV-431, RCP 1B Controlled Bleedoff valve.
D. Enter 40AO-9ZZ04, Reactor Coolant Pump emergencies; Stop RCP 1B and
close RCN-HV-431, RCP 1B Controlled Bleedoff valve.

A

A Wrong This would be the correct response for Seal 2 outlet pressure > 1700 psig. If controlled
BO flow is > 9.5 gpm then Seal/Controlled BO must be isolated.
B Wrong Going to the AOP is correct due to the high SBO flowrate but the AOP directs isolating
Seal Bleedoff but whereas the OP has SBO remaining in service. If controlled BO flow is
> 9.5 gpm then Seal/Controlled BO must be isolated.
C Wrong Both the first and second parts are wrong for the conditions given but part 1 would be
correct for the outlet pressure of the Seal 2.
D Correct >9.5 gpm requires entry into ZZ04 and isolation of Seal Bleedoff.

88
Q

Given the following conditions:
• Unit 1 is operating at 100% power.
• The upper half of window 5B03A “LEG 1 -3 CIAS LEG 2 - 4” is alarming.
• The CIAS annunciator on B05 is alarming.
• The RO reports that there are no abnormal trends in Containment parameters.
Which ONE of the following is the required action(s) per LCO 3.4.16, RCS Leakage Detection
Instrumentation?
A. Both the Containment Sump and Atmosphere monitors are Inoperable. Enter
LCO 3.0.3 immediately.
B. Only the Containment Sump monitor is Inoperable. Perform an RCS water
inventory balance once per 24 hours.
C. Only the Containment Atmosphere radioactivity monitor is Inoperable. Analyze
grab samples of the containment atmosphere, once per 24 hours.
D. Both the Containment Sump and Atmosphere monitors are Inoperable. Be in
Mode 3 within 6 hours and mode 5 within 36 hours, entry into LCO 3.0.3 is NOT
required at this time.

A

A Correct Per 3.4.16 action D 􀍲 with both the atmosphere and sump monitors inoperable enter
LCO 3.0.3 immediately.
When an “A” train CIAS is actuated RU􀍲1 is isolated and therefore Inoperable due 2
of 4 CI valves going closed, HCA􀍲UV􀍲45/46.
On the “A” train CIAS the containment sump isolation valve RDA􀍲HV􀍲23 will go
closed making the containment sump monitoring system Inoperable..
B Wrong Both are inoperable. Plausible because this is an action in the LCO. Refer to A.
C Wrong Both are inoperable. Plausible because this is an action in the LCO. Refer to A.
D Wrong Both are inoperable but this action is required in the conditions of actions A or B or not
met. This would be applicable if the mode change time requirements had not been
met. Condition D overrides this requirement. Plausible because this is an action in the
LCO

89
Q

Given the following conditions:
• A reactor startup is in progress.
• The core is at 225 EFPD (U1C18).
• The Estimated Critical Condition (ECC) is group 5 at 45 inches.
• Hold Point 1 is gp 1 at 80 inches.
• Hold Point 2 is gp 2 at 36 inches.
• Hold Point 3 is gp 2 at 95 inches.
• Hold Point 4 is gp 3 at 60 inches.
During the CEA withdrawal process the following data was observed.
• Countrate has doubled 4 times during the startup.
• At hold point 2 the Anticipated Critical Position (ACP) is gp 4 at 75 inches.
• At hold point 3 the Anticipated Critical Position (ACP) is gp 4 at 90 inches.
Using the provided Core Data Book curves determine which ONE of the following is the required
actions per 40OP-9ZZ03, Reactor Startup?
A. Fully insert all Regulating Group CEAs.
B. Continue with the startup; withdraw CEAs to group 3 at 60 inches.
C. Stop the CEA withdrawal, stabilize countrate and direct Reactor Engineering to
re-evaluate the 1/M plot.
D. Trip the reactor, ensure adequate SDM, verify countrate is lowering and direct
Reactor Engineering to investigate.

A

A Wrong Guidance for a dropped CEA in Mode 3 from 40AO􀍲9ZZ11.
B Correct 2 ACPs within the minus 500 position means that a withdraw to the less of ½
distance to critical position or HP 4 is permitted. HP 4 is 550 pcm away, ACP is > 1300
pcm away
C Wrong This would be correct with 3 or fewer doublings and the ACPs had been outside the
minus 500 pcm position
D Wrong 2 ACP < (􀍲) 500 pcm position and 4 doublings then a reactor trip is required.

90
Q

Given the following conditions:
• Unit 1 automatically tripped from 100% power.
• HPSI pump “A”, SIA-P02 is under clearance and unavailable.
• PBB-S04, 4160 kV class bus faulted and is de-energized.
• SPTAs are in progress.
• Pressurizer level is off scale low.
• RVLMS indicates 21% in the outlet plenum.
• RCS pressure is 900 psia and lowering.
Subsequently
• Core Exit Thermocouples (CET) temperatures are 650°F and rising.
• RCS pressure is 700 psia and slowly lowering.
• RVLMS level indicates 0% in the outlet plenum.
(1) Which EOP should the CRS implement?
(2) What is the CET temperature that corresponds to significant superheating of the coolant
resulting in a LOSS of the clad barrier?
A. (1) 40EP-9EO09 (FRP) (2) 700°F
B. (1) 40EP-9EO03 (LOCA) (2) 700°F
C. (1) 40EP-9EO09 (FRP) (2) 1200°F
D. (1) 40EP-9EO03 (LOCA) (2) 1200°F

A

A Wrong CET temperatures greater than 700°F represents the “potential “ loss on the fuel clad
barrier. The question B Wrong asks for the “onset” of clad damage.
C Correct 1200°F is the onset on clad damage and no HPSI flow requires entry into the FRP
D Wrong No HPSI flow is a loss safety function and the FRP must be entered.

91
Q

Given the following conditions:
• Unit 1 is in a Refueling outage.
• Refueling pool level is at 138 ft 2 inches.
Per LCO 3.9.1 the minimum refueling pool boron concentration is (1) ppm, which is designed to
maintain Keff 􀑇 (2) during fuel movement.
A. (1) 2150 (2) .95
B. (1) 2150 (2) .99
C. (1) 3000 (2) .95
D. (1) 3000 (2) .99

A

A Wrong 2150 is the Spent Fuel Pool Boron concentration requirement
B Wrong Keff .99 can be found in the U1R18 COLR figure 3.1.1􀍲1 SDM vs. Cold Leg Temperature
and 2150 is the SFP TS limit
C Correct Per COLR and TS 3.9.1 bases
D Wrong 3000 ppm is correct but .99 can be found in the U1R18 COLR figure 3.1.1􀍲1 SDM vs.
Cold Leg Temperature

92
Q

Given the following conditions:
• Unit 2 is operating at 100% power.
• The unit is staffed as follows:
UNIT 1 UNIT 2 UNIT 3
1 Shift Manager 1 Shift Manager 1 Shift Manager
1 STA (Unlicensed) 1 STA (Unlicensed) 1 STA (Unlicensed)
1 CRS 1 CRS 1 CRS
2 ROs 2 ROs 3 ROs
• 4 Auxiliary Operators
(Unlicensed)
• 4 Auxiliary Operators
(Unlicensed)
• One AO has left the protected
area to attend required training
• 4 Auxiliary Operators
(Unlicensed)
In accordance with BOTH Technical Specifications and PVNGS administrative procedures: Unit 2
staffing requirements are currently…
A. NOT met, 4 AOs are required to be within the unit at all times per ODP-2,
Operations Shift Coverage.
B. met, all of the Technical Specifications and PVNGS administrative requirements
are satisfied by the current manning.
C. NOT met, each unit is required to have their own licensed individual designated
as the FTA per TS 5.2.2, Organization; Unit Staff.
D. met, provided the 3rd RO in Unit 3 satisfies all requirements and has been
designated the FTA per 40DP-9OP02, Conduct of Shift Operations.

A

A Wrong The 4th AO is allowed outside the unit provided they are in contact and can return
within 10 minutes.
B Wrong The Tech Spec requirements are met but the FTA position is designated by U2 manning
C Wrong There can be a “SITE” FTA
D Correct Staffing requirements would be met if either of the other units have a third RO who
is designated as the Site FTA

93
Q

Given that Unit 1 is operating at 100% power:
1. Per LCO 3.4.17, what is the limit for Dose Equivalent I-131 in the RCS?
2. What is the required action if Dose Equivalent I-131 is currently 100 μCi/gm in the RCS?
A. (1) < 0.1 μCi/gm
(2) Be in Mode 5 in 37 hours.
B. (1) < 1.0 μCi/gm
(2) Be in Mode 5 in 37 hours.
C. (1) < 0.1 μCi/gm
(2) Be in Mode 3 with RCS cold leg temperature < 500° F within 6 hours.
D. (1) < 1.0 μCi/gm
(2) Be in Mode 3 with RCS cold leg temperature < 500° F within 6 hours.

A

A Wrong > 0.1 􀈝Ci/gm is the limit for secondary specific activity (LCO 3.7.16)
B Wrong 1st part is correct but the second is based on LCO 3.0.3 if the examinee is not
aware of the applicable condition they may think that entry into LCO 3.0.3 is
required
C Wrong > 0.1 􀈝Ci/gm is the limit for secondary specific activity (LCO 3.7.16)
D Correct Proper RCS limit and application of Condition B: be in Mode 3 with Tcold <
500° w/I 6 hours

94
Q

Given the following information from Tech Specs:
• Tech Spec 3.7.7 states …with one EW train inoperable, restore the EW train to OPERABLE
status within 72 hours.
• Tech Spec 3.6.6 states …with one Containment Spray train inoperable, restore the
Containment Spray train to OPERABLE status within 72 hours.
• An evaluation has been performed per the Safety Function Determination Program and found
that NO loss of safety function exists.
Given the following conditions:
1200 10/05/13 EW ‘A’ is declared inoperable due to a breaker problem.
1200 10/07/13 CS ‘A’ is declared inoperable due to failed room cooler.
1100 10/08/13 EW ‘A’ is restored to service.
Assuming that LCO 3.0.6 was implemented when does CS ‘A’ have to be restored to service?
(LCO 3.0.6 provided)
A. 1200 10/08/13
B. 1100 10/09/13
C. 1200 10/10/13
D. 1200 10/11/13

A

A Wrong 72 hours from EW INOP, if 3.0.6 is not used then this would be correct
B Wrong SR 3.0.3 has provisions for a 24 delay if a surveillance is missed
C Correct 72 hours from CS inoperability, with LCO 3.0.6 invoked.
D Wrong 72 hours after EW is restored to service.

95
Q

Given the following conditions:
• Unit 1 is in a Refueling Outage.
• The crew is establishing conditions for Core Offload per 40OP-9ZZ23, Outage GOP.
• Refueling Pool level has been raised to 127 ft 7 inches and stabilized.
• The CEA support plate has been lowered and is on the Guide Plate.
• The L-SRO has verified that all CEA extension shafts have latched.
• The SM has given permission to raise the UGS Lift Rig CEA Support Plate.
Subsequently
• The Effluent tech reports that due to a procedural error both RU-29/30, Control Room
Ventilation Intake monitors, are INOPERABLE.
Which ONE of the statements is correct?
Raising the CEA support plate (1) considered a core alteration and (2)
A. (1) IS (2) movement of the CEA Support Plate must be suspended immediately.
B. (1) IS (2) movement of the CEA Support Plate must be suspended within 1 hour.
C. (1) IS NOT (2) no Core Alterations are permitted until at least one CREFS train is
in operation.
D. (1) IS NOT (2) no Core Alterations are permitted until both monitors are declared
OPERABLE.

A

A Correct This is considered a core alteration by TS, 40OP􀍲9ZZ23 and the Core Reloading
procedure. TS requires Core Alts to be suspended immediately.
B Wrong One hour relates to the condition time required to place a train of CREFS in operation
in Modes 1􀍲4.
C Wrong This is considered a core alteration by TS, 40OP􀍲9ZZ23 and the Core Reloading
procedure. Part (2) CREFS would allow Core Alts to continue.
D Wrong This is considered a core alteration by TS, 40OP􀍲9ZZ23 and the Core Reloading
procedure. TS would allow Core Alts to continue with only one of the monitors
OPERABLE but examinee may think that both trains are required.

96
Q

Given the following conditions:
• Unit 1 was manually tripped due to a tube rupture in SG 1
• Offsite power was lost on the trip
• SG 1 has been isolated per 40EP-9EO04 (SGTR)
• SG 1 pressure is 1100 psia
• SG 1 narrow range level is 65% and rising
• RCS pressure is 1400 psia
• RCS cooldown rate is currently 12°F/hr
Which of the following are the preferred methods to maintain SG level and control the spread of
contamination?
A. Lower RCS pressure below SG 1 pressure or Drain SG 1 to the condenser.
B. Increase the RCS cooldown rate to 100°F or Lower RCS pressure below SG 1
pressure.
C. Open the affected MSIVs and steam SG 1 to the condenser or Drain SG 1 to the
condenser
D. Increase the RCS cooldown rate to 100°F or open the affected MSIVs and steam
SG 1 to the condenser

A

A Correct step 32 of SGTR directs either one of these actions
B Wrong Due to the loss of offsite power CD rate is limited to 30°F per SGTR. But
increasing the CD rate would get to SDC quicker limiting secondary
contamination
C Wrong Steaming to condenser is correct but not thru the MSIVs. MSIV bypasses should
be used to limit secondary water hammer
D Wrong both of these are wrong as stated above

97
Q

Given the following conditions:
• Unit 1 is in a refueling outage.
• Tcold is 180°F.
• RCS pressure is 150 psia
• LPSI A is providing Shutdown Cooling flow at 3780 gpm.
Subsequently:
• RCS level is lowering.
• Containment sump alarms are annunciating.
• Shutdown Cooling Lo Flow alarms are annunciating.
• An operator reports that the “A” train LTOP is partially open.
The CRS should implement the (1) procedure, Isolate the LTOP and restore Shutdown Cooling
flow by placing (2) .
A. (1) Loss of Coolant Accident (2) Shutdown Cooling train “B” in service.
B. (1) Loss of Coolant Accident (2) Containment Spray pump “A” in service.
C. (1) Lower Mode Functional Recovery (2) Shutdown Cooling train “B” in service.
D. (1) Lower Mode Functional Recovery (2) Containment Spray pump “A” in
service.

A

A Wrong With LTOPs in service LOCA entry conditions are not met even though the
B Wrong event in progress is a Loss of Coolant accident
C Correct with LTOPs open the LMFRP is the correct procedure to enter and the
other train of SDC should be placed in service because the to isolate the
LTOP the SDC suction valves are closed so CS A is not available.
D Wrong Isolating the LTOP require that the SDC suction valves are closed so CS A is
not available.

98
Q

Given the following conditions:
• Unit 1 is in Mode 4 exiting a 29 day refueling outage.
• Armed intruders have entered the B-Safe building and taken hostages.
• No injuries have been reported.
• The SM has implemented the Emergency Preparedness (EP) procedures.
• The CRS has implemented 40AO-9ZZ24, Deliberate Acts Against PVNGS.
(EAL Table is provided)
The SM will classify this event as a(n) (1) Emergency Response Personnel will be directed to
(2) .
A. (1) Alert (2) Report to their Emergency Response Facility IAW EP-0902,
Notifications.
B. (1) Alert (2) Take immediate cover in the nearest building IAW 40AO-9ZZ24,
Deliberate Acts Against PVNGS.
C. (1) Site Area Emergency (2) Report to their Emergency Response Facility IAW
EP-0902, Notifications.
D. (1) Site Area Emergency (2) Take immediate cover in the nearest building IAW
40AO-9ZZ24, Deliberate Acts Against PVNGS.

A

A Wrong Note in EP 0901 directs the EC to use ZZ24 to make announcements and the
associated appendix directs ALL personnel to seek shelter.*
B Correct B􀍲Safe building is outside the PA therefore this event is an Alert and ZZ24 directs ALL
personnel to seek shelter.*
C Wrong Would be SAE in the intruders were within the PA
D Wrong Would be SAE in the intruders were within the PA