16. Controlling Flashcards

1
Q

What is the project status? What are the status variables?

A

The status reflects the actual state of the project regarding the three main project variables:
Scope/results - cost - time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain at least 3 common ways of determining the rate of progress.

A
  • percent complete
    PC = (results achieved as of the status date / planned total results) *100
  • performance based on time data
    • > elapsed time/planned total duration
  • based on performance variables
    • > lines of code
  • based on resource consumption data
    • > working hours up to the status date/total
How well did you know this?