What is in a Project Manual for a multistory building
Prequalification Form
Supplementary Conditions
General Requirements
General Conditions
Under stair storage needs what fire protection
1 hour
what can help avoid a contractor withdrawling from a project
bid security requirement
circuit breakers in an electrical system are analogous to BLANK in a hydrolic system
Flow limiting device
a 2 hour shaft wall in a multistory building
2 1/2”” 25 ga. C-H studs spaced at 24” 1” gypsum liner panel, friction fitted 2-layers 1/2” gypsum board
what material is measured in squares during estimating
roofing
What is the maximum force allowable to open the main entry doors?
As little as possible.
Exterior doors have no maximum force requirements, they shall open with as little force as possible.
The amount of cooling in BTU/h required of an air conditioning system is based on which of the following?
Enthalpy
It is the is the sum of total heat in the air, both sensible and latent heat. Both are used to calculate air-conditioning loads.
correct drawing sequence
Civil/Architectural/Plumbing/Electrical
AFUE of 90 means?
Furnaces (and boilers) are rated by the annual fuel utilization efficiency (AFUE) ratio, which is the percent of heat produced for fuel consumed. A furnace with an AFUE of 90 will turn 90% of its fuel into useable heat. Any furnace with an efficiency of 90% or higher is considered high-efficiency.
What is the allowable gallons per flush based on the U.S. Energy Policy of 1992?
The Federal allowable gallons per flush is 1.6
method to reduce size of septic drain field
constructed wetland can act as a secondary treatment of effluent from septic tanks
what is the most cathodic fastener
stainless steel fasteners
Brick MW
Moderate Weathering
Brick NW
negligible weathering
Brick FBX
face brick type
Brick SW
severe weathering
Where are the sensors for emergency lights that are located in a corridor found?
Locally on each fixture
Which of the following causes ice damming on a roof?
Heat loss through the roof/wall junction
what is the minimum distance between two doors in a vestibule
48”
FEC requirements per ADA
6” deep fully recessed FEC mounted with handle at 48” AFF. There can be no protrusion equal to or greater than 4” between 27” and 80” AFF. For an unobstructed approach, the maximum reach is 48.”
Which occupancy group requires a rated fire wall between it and every other occupancy group?
Residential
Refer to table 508.4 in the IBC 2012 for fire-resistance ratings between occupancy groups.
More detailed information about the contractor’s overhead and profits, provisions for this request shall be included in which of the following documents?
Supplementary conditions
Supplementary conditions modify the general conditions to cover unique situations. A way to distinguish between supplementary and special conditions is that supplementary conditions are things that may be repeated project to project for the same client. Special conditions would be project specific.
Which of the following is found in the low pressure side of a compressive refrigeration cycle?
The evaporator is where the refrigerant is turned from a liquid into a gas and absorbs heat from the area to be cooled. This is the low pressure side of the cycle.
Brick Header
a brick that ties two adjacent wythes together. end visible, laid on bottom face akin to a stretcher
Rowlock Brick
a brick laid on its face with its end visible at the wall surface
Sailor Brick
laid on end with top visible
Soldier Brick
laid on end with face visible
Brick Shiner
laid on face with top visible
According to IBC 2012, emergency illumination for a means of egress in any occupancy must endure for how many minutes?
90 minutes
Section 1006.3
What is the benefit of using BIM on the drawing and specification coordination effort?
Allows for terminology coordination and consistency, as well as a tighter integration of specification attributes
Subsurface drainage should flow to which of the following?
Subsurface drainage pipes from foundations should be designed to either run to daylight, to a sump pump, or a storm sewer system.
low sheen paint finishes
Satin and Eggshell
What is the minimum width of a curb ramp, exclusive of flared sides?
36”
2 story office building type IV
1 hour IBC 1023
min size structure member truss roof for Type IV
4 x 6
Béton brut
Béton brut means raw, and it was popular during the brutalism movement of the 1970s.
Universal design carpet max depth?
According to ADA 2010 standard 4.5.3 and 2009 ANSI A117.1, carpets should have a level cut pile, level loop, textured loop, or cut-and-loop texture, with a maximum pile height of 1/2”.
What has the biggest impact on the design of a concert hall during SD?
Type of performance
Different types of performances require different spaces. The needs of a concert hall are different than both a theater for drama and one for movies. Desirable reverberation time, stage size, and audience arrangement and sight lines all vary with the type of theater.
What is the most dimensionally stable lumber
Rift sawn