Whose Role is it? Flashcards

1
Q

This person retains the right to reject any and all bids, specifically any incomplete bids or bids which are not accompanied by the required bid bond or other documentation

During Bidding Phase

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

This person is responsible for liquidated damages for every day the project is overdue

Owner contractor agreement

A

Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

This person will prepare a change order to authorize changes in contract time and/or contract cost after the execution of the contract

During construction

A

Interior Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

This person is responsible for selecting the routes to be used from the delivery points to the final destination

FF&E

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

This person is responsible for abiding by the agreed upon critical dates in the progress schedule submitted by the contractor

FF&E

A

Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who is responsible for visiting the site on a regular basis to ascertain the progress that has been made?

During construction

A

Interior Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

This person can hold onto part of each payment made in order to protect against poor work, knowns as a retainage

During contract administration

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

This person is responsible for informing the owner about any special equipment or services that will be required for the proper delivery and installation of the work

FF&E

A

Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who prepares any necessary changes to shop drawings by way of change order?

During construction

A

Interior Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

This person shall maintain one record copy of the drawings, specs, addenda and change orders at the site for the owner

During construction

A

Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who is responsible for providing access to the area of work at reasonable work times, as well as for providing suitable space for the receipt and storage of materials, furniture and equipment

During construction

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who has the authority to reject work that does not conform to the CDs

During construction

A

Owner & Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

This person must make sure all delivery and staging areas and delivery routes are free from obstacles or any other factors that may hinder the contractor

FF&E

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Who should continually review shop drawings

During construction

A

Interior Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

This person is required to provide labor, means and methods of carrying out the work according to the prevailing labor conditions at the job site

FF&E

A

Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

This person is responsible for making the acceptance inspection of Furniture and fixtures.

FF&E

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Who will issue the final certificate for payment?

During construction

A

Interior Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

If the owner instructs the contractor to proceed without acceptance of the change proposed, then who is solely responsible for any resulting loss or damage?

During construction

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

This person is responsible for inspection work to determine that such portions are in proper condition to receive subsequent
work.

During construction

A

Contractor

20
Q

Who is not responsible for the contractor’s acts or omissions

During construction

A

Interior Designer

21
Q

This person should inspect FF&E when it arrives to determine whether materials, furniture and equipment are in good condition and in the right quantity

FF&E

A

Owner

22
Q

Who is responsible for making sure materials are put together, that they arrive at the site, and that they are installed properly.

During construction

A

COntractor

23
Q

Who is responsible for making sure that the contract documents conform to relevant building codes and ordinances?

During construction

A

Interior Designer

24
Q

This person is responsible for making adequate facilities available for delivery, staging and storage of FF&E.

FF&E

A

Owner

25
Q

Who must conduct a final inspection and predict a date of substantial completion?

During construction

A

Interior Designer

26
Q

Who has the right to accept work which does not comply with the original terms of the contract, although a change order must be filled out in order for this to be official?

During construction

A

Owner

27
Q

Who does not have the right to stop ongoing work or to terminate any contracts on behalf of the owner

During construction

A

Interior Designer

28
Q

Who is personally responsible for all fabrication, delivery and installation means and procedures

During construction

A

Contractor

29
Q

Must provide the contractor with a strict schedule for the use of unloading facilities and elevators

FF&E

A

Owner

30
Q

Who must interpret and decide any matters concerning contract documents?

During construction

A

Interior Designer

31
Q

This person is responsible for providing security against loss or damage of FF&E that is stored at the site between the time of delivery and the final acceptance by the owner

FF&E

A

Owner

32
Q

Anything done by a subcontractor is the responsibility of this person

During construction

A

Contractor

33
Q

Who will prepare change orders and construction change directives

During construction

A

Inerior Designer

34
Q

While this person is not responsible for ascertaining that contract documents comply with building codes, they are required to give notice to the designer.

During construction

A

Contractor

35
Q

Who has the right to order the contractor to cease work at any
time.

During construction

A

Owner

36
Q

Who has the right to award separate contracts for work which is not then allocated under the original contract?

During construction

A

Owner

37
Q

Who may authorize minor changes in work, not involving adjustments in contract time or sum

During construction

A

Interior Designer

38
Q

Who is responsible for providing temporary utilities and any vertical transportation that is necessary for the construction?

During construction

A

Owner

39
Q

This person is solely responsible for ensuring job site safety and must be seen to make adequate precautions against damage to persons and property.

During construction

A

Contractor

40
Q

Who is responsible for providing proof to the contractor that the financial arrangements have been made to fulfill the obligations of this person under the agreed upon contract?

During construction

A

Owner

41
Q

This person is responsible for providing a schedule to the other parties

During construction

A

Contractor

42
Q

Who is responsible for furnishing all drawings free of charge?

During construction

A

Owner

43
Q

This person shall supervise and direct work

During construction

A

Contractor

44
Q

Who has the right to carry out the work if the contractor fails to do so correctly

During construction

A

Owner

45
Q

This person shall secure and pay for the building permit and governmental fees, licenses and inspections necessary for proper execution and completion of work

During construction

A

Interior Designer