Whose Role is it? Flashcards
This person retains the right to reject any and all bids, specifically any incomplete bids or bids which are not accompanied by the required bid bond or other documentation
During Bidding Phase
Owner
This person is responsible for liquidated damages for every day the project is overdue
Owner contractor agreement
Contractor
This person will prepare a change order to authorize changes in contract time and/or contract cost after the execution of the contract
During construction
Interior Designer
This person is responsible for selecting the routes to be used from the delivery points to the final destination
FF&E
Owner
This person is responsible for abiding by the agreed upon critical dates in the progress schedule submitted by the contractor
FF&E
Contractor
Who is responsible for visiting the site on a regular basis to ascertain the progress that has been made?
During construction
Interior Designer
This person can hold onto part of each payment made in order to protect against poor work, knowns as a retainage
During contract administration
Owner
This person is responsible for informing the owner about any special equipment or services that will be required for the proper delivery and installation of the work
FF&E
Contractor
Who prepares any necessary changes to shop drawings by way of change order?
During construction
Interior Designer
This person shall maintain one record copy of the drawings, specs, addenda and change orders at the site for the owner
During construction
Contractor
Who is responsible for providing access to the area of work at reasonable work times, as well as for providing suitable space for the receipt and storage of materials, furniture and equipment
During construction
Owner
Who has the authority to reject work that does not conform to the CDs
During construction
Owner & Contractor
This person must make sure all delivery and staging areas and delivery routes are free from obstacles or any other factors that may hinder the contractor
FF&E
Owner
Who should continually review shop drawings
During construction
Interior Designer
This person is required to provide labor, means and methods of carrying out the work according to the prevailing labor conditions at the job site
FF&E
Contractor
This person is responsible for making the acceptance inspection of Furniture and fixtures.
FF&E
Owner
Who will issue the final certificate for payment?
During construction
Interior Designer
If the owner instructs the contractor to proceed without acceptance of the change proposed, then who is solely responsible for any resulting loss or damage?
During construction
Owner