When is a punch list created and by who?
Created during contrcution admin phase and by the general contractor
What is substantial completion?
The stage when the work is sufficently complete in accordance with the contract documents so the owner can occupy/utilize the space
Who prepares the certicated of substantial completion?
Interior designer/architect
Who sends certicate of completion to the owner and contractor for their written acceptance?
Interior designer/architect
Do warranties commernce on the date of substantial completion or before?
On the date of substantial completion
Project closeout process
Who initiates the project closeout process in writing?
Contractor
Project closeout process
Who completes a first inspection and develps a punchlist and final inspection once the items on the punch list are addressed?
Architect/Designer
Project closeout process
Who submits the final application for payment?
Contractor
Project closeout process
Who completes the final cleaning?
Contractor