Contract Administration 15% (Submittals) Flashcards
Submittal Reveiw OR Project Closeout
GC Receives and reviews submittals
Submittal review
Step 2
Submittal Reveiw OR Project Closeout
GC sends submittals to the interior designer
Submittal review
Step 3
Submittal Reveiw OR Project Closeout
Interior designer reviews and approves submittals for design intent conformance
Submittal review
Step 4
Submittal Reveiw OR Project Closeout
Interior designer sends approved and signed submittals to GC for record in a timely manner
Submittal review
Step 5
Submittal Reveiw OR Project Closeout
Submittals prepared by Subcontractors or material suppliers
Submittal review
Step 1
Submittal Reveiw OR Project Closeout
Submittal Reveiw OR Project Closeout
Contractor corrects/addresses punch list items
Project closeout
Step 3
Submittal Reveiw OR Project Closeout
Contractor initiates closeout process in writing
Project closeout
Step 1
Submittal Reveiw OR Project Closeout
Contractor submits the final application for payment
Project closeout
Step 6
Submittal Reveiw OR Project Closeout
Designer completes final inspection (if work is substantially complete)
Project closeout
Step 4
Submittal Reveiw OR Project Closeout
Designer completes first inspection and develops a punch list
Project closeout
Step 2
Submittal Reveiw OR Project Closeout
Designer completes first inspection and develops a punch list
Project closeout
Step 2