Water Distribution 060201c Flashcards

1
Q

Where is the groundwater we find

A

In porous layers of rock,sand, gravel called aquifers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who established acceptable levels of organic and inorganic matter in drinking water

A

Health Canada in conjunction with concerned individuals from various provinces

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How often should water supplies be tested

A

Once a year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What’s the max velocity of water in a transmission pipe

A

Max of 5ft/sec

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Maximum static pressure allowed in occupied building

A

80 psi (550 kpa)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When the pressure in a building exceeds 80 psi or 550kpa what should be installed

A

Pressure reducing Valve PRV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What’s used in pipes changes of direction to prevent pipes coming apart

A

Thrust blocks or thrust anchors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Minimum size of water service for single family dwelling

A

3/4”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Nicks or scratches deeper than what percent of wall thickness are required to be replaced

A

10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Where does building distribution piping begin

A

Begins at the outlet of the water meter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A ball valve or inverted plug valve installed in the water service pipe at a customers property line

A

Curb cock ( CC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What stops cannot be opened or closed from ground surface as they are covered over with back fill

A

Small corporation main stop

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The threaded connection of the sadddle is located to point toward the property and with its outlet at an angle of what degree

A

30 to 45 degrees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Outlet pipe installed with a service bend is called what for 2” or less

A

Settlement loop or gooseneck

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Some types Cold water supply pipes are only suitable for cold water what should they be protected from

A

Hot water flowing back from water heater

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Device keeps temperature of water from exceeding 99c and must be installed top 6” of the tank

A

Pressure relief valve

17
Q

Controls on-off function of the heating device and maintains water at a pre set temperature of about 60c fire domestic use

A

Thermostat

18
Q

Pressure relief valve must have the outlet directed with a drop tube of same diameter within how many inches of the floor

19
Q

When an eco control trips

A

Control must be replaced means something in the tank is malfunctioning

20
Q

Relief valve piping practices

A

If steel no threads on open end if copper cut at a 45 degree angle

21
Q

Minimum static pressure at water service entry

A

Not less than 200 kpa 30 psi

22
Q

Sizing a water distribution system what distances have to be kept in mind

A

Total developed length most remote fixture to property line not longer than 90 metres

23
Q

After calculation the sum of fixture units needed for building what do you need to check

A

If there are any added demands from things such as a irrigation system or fire sprinkler system

24
Q

The intention of water distribution systems

A

Have all systems function in a manner that will provide adequate pressure and flow to all fixtures under any circumstance

25
Piping from the hot water tank to a fixture less than ____ metres away will operate satisfactorily
30
26
All hot water distribution systems that are more than 30 metres in developed length must have what
Have a re circ system or self regulating heat trace
27
Shut off valve is required on supply line to every what fixture
Water closet
28
If anything could contaminate building water such as hot water boiler with chemicals or glycol products
A second backflow preventer must be installed
29
What can’t you bypass around
Backflow prevention
30
Who states that an air gap will not be permitted on a fixture that is situated in a noxious environment
National plumbing code of Canada
31
What percent of volume should an expansion tank be sized for a hot water heater
Should be sized to accommodate 5% of the tanks volume
32
Where must the drains from water treatment devices be piped
Must be indirectly connected to the drainage system to prevent contamination of the filter bed and water passing through the filter bed
33
These size valves for water service pipe can be stop and drain valves
3/4” 1”
34
What size do they install water metres to allow a passage for a suitable amount of water without causing pressure loss
5/8s water meter
35
Minimum size water service allowed to have a bypass arrangement around the meter
1 1/2” ( 38 mm)
36
Air testing water distribution system what pressure and how long
100 psi and hold for 2 hours
37
Water distribution systems can be found in what section of the national plumbing code of Canada
Section 2.6