What ERRCDs identify repair cycle assets?
XD & XF items
When does the repair cycle of an asset begin and end?
Begins with the removal of the item & Ends with TRIC TIN to delete DIFM detail record to end the repair cycle
What DIFM Status Flag identifies an Issue to Maintenance?
0 (Firm)
What DIFM Status Flag identifies a backorder for an item?
1 (Memo)
What DIFM Status Flag identifies that the requested item is still Due-Out, but the exchanged item was already Turned-In?
2 (Credit)
What are DFM change inputs used for?
to update status & location of a DIFM asset
In what quantity are DIFM items normally requested?
1 ea.
What listing is used to perform the DIFM reconciliation?
D23 (Repair Cycle Asset Management List)
What is the purpose of the D23?
To make sure Maintenance physically has all items listed on the D23
What listing is used to review Base-in house repair capability program?
Q04 (Repair Cycle Data List)
What listing is used to monitor Awaiting Parts (AWP) end items?
D19
What paperwork must accompany DIFM items when they are returned to the LRS?
- AFTO FORM 350
- ISU
- DOR
- Condition Tag
- Repairable Item Processing Tag
What is the concept of two-level maintenance?
Sending an XD2 asset directly to depot for repair w/o trying to repair them at base level
What is the source of data for TRN processing?
AFTO Form 350, Part 2
The process of removing a broken repair cycle asset and reinstalling it is called a…?
TRN (Turnaround)