Variations Flashcards

1
Q

What is a Variation? What does it impact?

A

A change in:

  • The scope of works as outlined by the contract documents
  • A dimension or level of the works
  • The material, workmanship or quality of any part of the works
  • A detail of the works
  • The order of precedence of the contract documents

Impacts:

  • The time – may affect the program
  • The cost – may affect the cost of building works
  • The quality – may affect the quality of the product
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Describe the process by which a variation and its effects are recorded & managed under the ABIC contract?

A

A variation is communicated and managed through written correspondence

  • The architect may instruct variations
  • The contractor may review the instruction
    • ​IF no adjustment to contract price and/or pc date the contractor must carry out the instruction
    • IF instruction results in adjustment of contract price and/or pc date the contractor must notify the architect
  • The architect to instruct whether the variation is to proceed
  • The contractor proceeds based on the written instruction from the architect
  • Adjustment to the contract (contract price & date for PC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Client requested variations after PC, not included in contract. What now?

A
  • The contract only allows for variations to the works prior to PC
  • The architect could instruct the builder to provide a variation price request but the contractor is not obliged to fulfil their request.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How can the client be protected from site related claims?

A
  • Have the contractor produce a dilapidation report on the existing site / building & surrounds.
  • This needs to be called up on the specification
  • This could involve the architect, the consultants & any 3rd parties.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If there are Errors or omissions on docs, what happens?

A
  • Check drawings, check responsibility, issue variation, inform client.
  • Architect to resolve error, omission or discrepancy by giving contractor written instruction and a copy to the owner.
  • If it is the architect’s fault client must pay and then other arrangements can be made between the client and arch outside contract.
  • Check if critical-path, may need to issue variation and work out cost adjustments after work is complete.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who is responsible for a dilapidation Report?

A
  • The contractor should undertake the dilapidation report, but the architect should review to ensure it is satisfied sufficient documentation has been undertaken.
  • Where there are any existing site conditions on neighboring properties that may be affected by the construction, a dilapidation survey / report should be undertaken to protect the owner and contractor from potential future claims
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Does a variation always cause an adjustment to the contract? Explain.

A

Every variation is a change to the contract (but not necessarily a change to cost or time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Under the ABIC contract what is the difference between the term “variation” and a claim by the contractor to “adjust the contract”?

A
  • A variation does not necessarily result in the contract being adjusted, it is just a change to the scope of works and/or the contract documents
  • It may not trigger the necessity for the contract price to be adjusted nor may it affect the program
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the contractor entitled to if there is a change to the contract price ?

A

Item 31 of Schedule 1 nominates an percentage of the value of the change which the contractor is entitled to. This is a percentage for the contractor’s overheads and profit (15% default).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly