Contract Administration Flashcards
What is a Building Approval?
- You require building approval, also called certification, for development that involves carrying out building work under the Planning Act 2016 (PA), as well as under specific building legislation.
- Building approvals require assessment against the Building Code of Australia (forming Volumes 1 and 2 of the National Construction Code) and Queensland’s building and plumbing regulations.
What is the role of the architect under the construction contract?
- Administer the contract on behalf of the owner
- The architect is the owner’s agent for giving instructions to the contractor
- Act independently when acting as assessor, valuer or certifier
- The architect is not the owners agent for giving or recieving notices under Dispute Resolution & Termination of Engagement
Who certifies building at completion and performs a final check? Who undertakes the fire commission check? When are you totally finished?
- Certifier certifies building
- Architect deems practical completion & final completion
- 7 year statute of limitation
What does the building certifier need for a building approval?
- Plumbing approval
- QFRS Certificates
- Form 15’s
- Architectural Drawings
What is Operational Works
Council infrastructure to be provided by the contract in order to fulfil the DA & BA as per the authority’s requirements.
Before work on site, builder needs?
- Contract executed
- Insurances
- Offcial documents required under contract schedule
- Building Approval
- Plumbing approval
- Dilapidation survey of the site and adjacent properties
- Surveyor to set out the works
Before make first progress payment the contractor must ?
- Have in place the security
- Have in place the insurances, unless owner is taking out the insurances
- Have given the architect the program
Under the terms of the ABIC contract the contractor is required to produce a program showing how the works will be completed. Should this program become part of the contract documents?
- The Program needs to be given to the architect within the required time as outlined in the contract after the contractor taking possession of the site (10 days)
- However the program does not form part of the contract documents because it is the contractors responsibility to meet PC
You have received the first progress claim from the contractor and it appears that he is front loading the contract and over claiming on the project. What can you do?
- Assess the claim vs progress on site
- Communicate with the builder where you think the difference has come from to ensure you’re suspicions
- note reasons for difference on progress certificate and issue the progress certificate with the corrected amount owed by the owner
If the builder is claiming for products ordered but not on site can you approve the claim?
- Short answer is yes – if agreed by both parties + ABIC MW has provision for this below
- Contractor warrants that any off-site plant or material claimed for payment:
- is as specified by the contract documents
- is stored securely
- is insured appropriately, noting the interest of the owner and
- wil become the property of the owner on payment of the amount claimed
What can a subcontractor do if they are not paid by the head contractor ?
- In Queensland, subcontractors can rely on two pieces of legislation to secure payment for works they’ve done. These two pieces of legislation, Subcontractors Charges Act 1974 and the Building and Construction Industry Payments Act 2004 (BCIPA) create a process which subcontractors can utilise to ensure they are paid.
- This is done by handing a charge to secure money payable by the head contractor. The charge is given to the developer to redirect money otherwise payable to the head contractor to the subcontractor. This charge can then be enforced in Court.
- Contractor can be asked to provide Stat Dec that sub-contractors have been paid. Can reject progress claim otherwise. This is state legislation, not a contract obligation
What are Prime Costs & Provisional Sums?
Provisional Sum:
- Sum excl. of GST for performance of foreseeable necessary work, including the supply of materials, not fully described by the contract documents OR
- for connection of infrastructure service to the site if detail of the service required or the supplier was not known or had not been decided on the date the contract was signed.
- eg. joinery, landscape
Prime Cost Sum:
- Sum excl. of GST for a foreseeable item of material or equipment, the precise identity of which was not known or had not been specified in the contract documents
- Sum excl. of GST for an allowance for payment of a fee or charge to a relevant authority.
- eg. floor tiles, tapware, door hardware
What are the risks with using either prime cost and/or provisional sum?
- Over-reliance on these estimates can result in inaccurate conclusions concerning the total contract price
- Undefined amounts of money & the owner bares the risk
In an ABIC contract what is the procedure to be followed when using prime cost and/or provisional sums?
- Fill out the schedule in the contract
- Get them priced/quotes
- Make sure client agrees with them
What power does the architect have In giving instructions on Latent Defects?
- The architect cannot give the first instruction to correct an outstanding defect or to finalize any incomplete necessary work after the end of the defects liability period and final certificate has been issued.
When excavating, the contractor uncovers a footing of the adjacent site’s heritage building – how do you proceed?
- This is an encroachment if ABIC MW
- Contractor should suspend the necessary work in the vicinty of the situation, ensure that any adjoining structure is stable and request instruction from the architect. (Tell them to do this if they havent already)
- Contractor should notify of a delay, if it will cause a delay
- Inform the client, they may need to speak with the owner of the neighboring site to come to an agreement on how to proceed
- Client may require legal advice
- Consult with heritage architect, structural engineer, geotechnical engineer, surveyor (check setout) and discuss ways to proceed, this may include altering the design.
If a safety issue occurs on site, what do you do?
- Safety is utmost importance. If safety issues become apparent;
- Go to site,
- Stop work if necessary
- Call Ambulance
- Call consultants to site if necessary.
- Keep Client informed
- Advise client to seek legal advice
- Talk to PI Insurance if claim could arise
- Ensure works continue if not a safety issue
When assessing a progress claim from the contractor, what must you take account of?
- any adjustments to the cost of building work
- proportion of the cost of building work claimed representing the value of work completed, making allowance for the cost of rectifying defects
- proportion of the cost of building work claimed representing the value of materials and equipment delivered, ensuring it has been incorporated/fixed.
- proportion of the cost of building work claimed representing the value of off-site plant or material
- an allowance for cash retention if thats the chosen security
- any claim by the owner for set off monies
- owners entitlment to liquidated damages
- GST
- Stay fair and impartial. Do not let builder/client sway your decision
- Can assess against the trade breakdown & the % complete or use Quantity Surveyor to determine level of completeness
What happens if owner takes possession early?
- Advise client not to.
- Check with the contract to see if there are provisions for staged practical completion
- Make sure they have their insurances in place.
- Project is Deemed Practically Complete – early occupation
- Certificate of occupation required (/building classification) is necessary prior to occupancy
- There could possibly be additional costs to the client and to the consultants for builder to have to complete works around an occupant.
- Defects Liability Period Begins
- Half of retention Released
- WH&S issue as some of the works are still incomplete
You have notified the contractor and he is refusing to come to site and rectify defects during DLP. What do you do?
- Inspect the defects
- Use the security remaining as negotiation
- If contractor refuses to rectify the defects, use the money to have another contractor to do the work
Pedestrian has been injured adjacent to site. What do you do?
- Call an ambulance if required
- Check contract regarding the insurances by the contractor
- (public liability insurance) and how to proceed
- Contractor will have to notify their insurer
- Discuss workplace health and safety with contractor, perhaps an audit needs to be conducted by appropriate authority?
- The site and adjacent areas are covered under the contractor’s insurances (contract works insurance and public liability insurance)