Town Planning / Development Appovals Flashcards
3 types of development application ?
- Prohibited development - Development for which a DA may not be made.
- Assessable development - Development for which a DA is required. Code Assessable OR Impact Assessable.
- Accepted development - Development for which a DA is not required. In this category there is two subsets being Accepted Development (ie.exempt) and Accepted Development subject to compliance with identified requirements (formerly self-assessable).
what does Code Assessable mean ?
Code assessable development applications are for development that is generally expected and can be assessed against the planning scheme requirements. It is not required to be publicly notified.
what does Impact Assessable mean ?
- Impact assessable development applications are for complex proposals or where the development has the potential for greater impacts:
- Assessed against the entire planning scheme.
- It is required to be publicly notified for a set period of time.
- Sign on site
- letter to adjacent lots
- Notice in local newspaper
- The community may make properly made submissions and have appeal rights.
- If development is larger scale than the planning scheme intended.
- The client needs to be warned in writing that this process is probably slower, more costly (to all parties involved) and it is more likely to be rejected than a code assessable application.
What documents will be required for a town planning application in QLD?
- Architectural plans, sections, elevations, perspectives etc
- Landscape concept plan
- Reports from consultants as outlined by planner i.e. Traffic, acoustic, civil for overland flow & bio retention
- Planning report from town planner
- Check with townplanner
If DA is rejected what do you do?
This would be very unusual in my experience as the council would more likely send through a large RFI that would need to be conformed to in order for the proposed development to pass DA.
- Investigate why it had been rejected.
- Call PII
- Discuss the ensuing procedure with the Town planner to ensure that the DA is passed in a timely manner.
What do you do with the DA conditions?
- File them
- Send to all consultants as there may be conditions that apply to them
What are DA conditions ?
- Most development approvals have conditions. The conditions form part of the development approval package and set out the circumstances in which the approved development may proceed.
- Often the purpose of conditions is to protect or reduce impacts on the environment and amenity. Some conditions relate to the provision of infrastructure to adequately service the proposed development.
- The Planning Act 2016 (PA) allows an applicant to negotiate conditions of development approval, following receipt of the decision notice.
- Example conditions (so many things) construction management plan, amplified music operating hours for a restaurant, usually a condition that states development must be built in line with drawings, protection of existing infrastructure, complete all building work, food hygeine , equitable access etc.
After talking to the Town planner the DA has been approved. What next?
- Send DA conditions to all consultants
- Meet with client for requirements and moving forward. Marketing etc.
- startup meeting with consultant team
- review Costs with quantity surveyor & estimate
What is the expected timeframe for a DA ?
- Code Assessable statutory timeframe is 45 business days not including any requests for information.3 to 6 months.
- Impact Assessable statutory timefram is 70 business days not including any requests for information. 6 months minimum.
- Minor change - 6 weeks.
- Other change - the same as a new DA.
- However, town planner will able to advise.
How long is the currency period of a DA following approval ?
- Material change of use: 6 years for the first change of use to start
- Reconfiguring a lot not requiring operational works: 4 years for the subdivision plan for the reconfiguration to be lodged to Council for plan sealing
- Building works: 2 years for the development to substantially start
- Operational works: 2 years for the development to substantially start.
- You can apply to extend a currency period.
What is the QLD DA Process ?
- Pre Application / Pre-lodgment meeting (not mandatory)
- Application
- Referal Agency Assessment (if req’d) & Information Request (if req’d)
- Public Notification (Only Impact Assessable)
- Decision
- Appeal Period
What are Referral Agencies ?
- Under the Planning Act 2016, a development application may trigger a requirement for an application to be referred to a referral agency.
- Referral agencies are generally Queensland Government departments and authorities such as Transport and Main Roads and Environment and Heritage Protection
- SARA (State Assessment and Referral Agency) was established to coordinate the state’s assessment and decision making role in the development process.
- Third Party Refferal Agencies are agencies that may have an interest in a application eg Brisbane Airport Corporation are interested in buildings over 100m, Energex etc.
When does the QFES become involved in a DA ?
- Under the terms of the Planning Act 2016 and associated legislation, referral to QFES for advice is required for any application for building work that involves a fire safety system and:
- requires special fire services (SFS) mentioned in the Planning Regulation 2017 or
- proposes a performance solution in relation to fire safety.