Valuations Flashcards
What is the procedure for carrying out a valuation under the JCT Design and Build Contract 2016?
The contractor submits an application on the specified date within the Contract Particulars, which triggers the payment process.
The due date is 7 days from that date, and the Employer then has 5 days to submit a payment notice.
The final date for payment is 14 days from the due date, unless it has been amended
What is the significance of a due date?
Due date triggers the payment cycle for all interim payments. Construction act states a payment notice is required 5 days after Due Date.
This is also the date that the last date for payment is calculated from
What is the procedure for carrying out a valuation under the JCT Standard Building Contract?
The contractor submits an application on the date stated in the Contract Particulars, which is 7 days prior to the due date.
The quantity surveyor values the works as of the due date, and issues a recommendation for payment to the contract administrator within 5 days of the due date.
Pay less notice due 5 days before final date of payment.
The final date for payment is 14 days from the due date, unless it has been amended.
What happens if the contractor does not submit application on the specified date under the D&B?
The payment process is not triggered.
Should a notice be issued after the 5 day period for interim certificate, the final date for payment is delayed by the same amount
A payment notice is still required
What happens if the contractor does not submit application on the specified date under the SBC?
Regardless of whether the contractor submits an application the quantity surveyor should still carry out a valuation and the contract administrator should issue a payment certificate within 5 days of the due date, otherwise the contractor can issue a default payment notice.
What is the procedure for carrying out a valuation under the NEC 3 Contract?
Assessment date is 7 days before Due Date
Interim Certificate due 5 days after Due Date
Pay Less Notice 7 days before Final Date For Payment
What happens if the contractor does not submit application on the specified date under the NEC?
Provision under the NEC 4 is that the PM is obliged to assess the amount due to the contractor as the lesser of
- the amount assessed by PM
- amount due at previous assessment date
Meaning best case is Contractor receives zero but they may be liable for money due to the client in the event where contractors have caused delay
What happens where Employer party fails to issue payment notice?
Contractor is entitled to submit a default payment notice under the Construction Act
This would then be obliged to be paid by the Employer, subject to any deductions in a Pay Less Notice
What are the payment provisions under the JCT Design and Build Contract 2016?
- Alternative A - Stage Payments
- Alternative B - Periodic Payments (the default)
- Contractor can suspend the works for non-payment 7 days after notifying the Employer
You’ve mentioned your experience has provided an understanding of payment provisions, what are the two methods of payment under the JCT?
Alternative A – Stage Payments, Alternative B – Periodic (interim)
Specified in Contract Particulars.
What assurances could you give a contractor that the Client pays?
I would remind them of the Employers implied terms under the housing grants act. With the clients approval we could also suggest using bonds such as advance payment and retention bonds.
What is a variation quotation under Schedule 2 of the JCT Standard Building Contract?
- The Contract Administrator instructs the contractor to submit a variation quotation, and provides information to the contractor in order for them to provide that quotation to the quantity surveyor.
- If the contractor feels the information is insufficient to provide a quotation he must notify the Contract Administrator within 7 days of the instruction.
- The variation quotation should include the cost of the variation, any adjustment to the time required for completion of the works, any loss and / or expense due as a result of the variation, the cost of preparing the quotation and any additional resources required to carry out the variation.
- The variation quotation should be submitted to the Contract Administrator within 21 days of being instructed to do so or receiving the additional information requested.
- Remains open for acceptance for 7 days from the date of submission.
- If the Contract Administrator does not accept the variation quotation, the contractor is still entitled to be paid the cost of its preparation provided it has been prepared on a fair and reasonable basis.
How does the valuation process for Alternative A and B vary?
A - cumulative value of stages completed + value of changes
B - works done to date
What are the advantages of LD’s?
- They do not require proof of loss after the event
- Can be deducted simply by employer under the mechanism in the contract
- Agreed in advance so contractor knows extent of their liability
- No need to prove actual damage and does not matter if loss is greater or less than anticipated
What is a liquidated damage?
A sum stated in the contract as damages payable in the event of a specified breach / failure to complete in time
Actual losses only, predetermined, not a penalty
QS don’t advise on calculation but can advise it would include elements such as loss of rent, loss of income, storage costs, rental costs, financing costs, fines from third parties