Termination / Insolvency Flashcards

1
Q

What is repudiation?

A

Not a contractual termination. Complete abandonment of the contract.
If other party has repudiated, must ensure not to continue with contract else may mitigate right to terminate under repudiation

Serious breach that allows the receiving party to consider the contract as terminated with immediate effect and sue for damages e.g. refusal of the party to carry out works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are step-in rights?

A

Enable a party to ““step in”” to the place of another party in relation to the rights and obligations of a contract. Named beneficiaries in a CW can step in

E.g. funder can step in to complete the works should the Employer become insolvent.

Right - not an obligation to step in

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When might an Employer terminate a contract?

A

If the contractor
- Without reasonable cause suspends carrying out the works
- Fails to comply with their obligations
- Refuses to comply with a notice or instruction to remove any work, materials or goods not in accordance with the contract
- Fails to comply with CDM regulations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the process for an Employer terminating a contract?

A
  • Must given notice specifying each default / reason
  • If contractor continues with specified default for 14 days after receipt of notice, Employer has 21 days to terminate employment
  • Employer to terminate, not the EA

The process is the same if a contractor terminates, with the contractor giving notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What happens after termination of a contract?

A

Following termination
- Not further sums due to the contractor except what is due in the termination provisions
- Where the contractor terminates the works, employer shall pay the amount properly due without reduction for retention
- Contractor obliged to clear site of temporary buildings, plant tools etc
- Contractor provides design documents to employer
- Contractor to prepare and submit final account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When might a Contractor terminate a contract?

A

Contractor gives notice if Employer:
- Does not pay by final date of payment
- Fails to comply with the requirement to get the consent of the contractor to assign the contract
- Fails to comply with CDM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What terms might either party terminate a contract under?

A
  • Force majeure
  • Employers instructions issued as a result of negligent work by a statutory undertaker
  • Loss or damage to works by specified perils
  • Civil commotion / threat of terrorism
  • Use of statutory powers by UK Government that affects the execution of works
  • Delay in receipt of any permission of approval for development control requirements where contractor has taken all practicable steps to avoid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is corporate recovery?

A

Process / actions to bring an ailing company back to full health, including financial provisions, restructuring, accounts & legal advice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What types of termination of a construction contract are there?

A
  • Voluntary - where parties mutually agree
  • Involuntary - may be a result of insolvency, where party is unable to pay debts

Contracts set out the process to be followed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the checklist for termination of a contract?

A
  • Discuss situation with the other party
  • Make a note of the relevant contract clauses for termination
  • Seek legal advice to ensure correct procedures
  • Seek assistance from an expert if required
  • Write and service notice detailing the breach
  • If breach continues after 14 days, dispatch further notice for the termination of the contract within 21 days
  • Prepare documents / final account / site security information
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What guidance would you follow in cases of insolvency?

A
  • RICS - Termination of contract, corporate recovery & insolvency GN - 2013
  • RICS has additional regulation information sheet published on their website
  • Government Insolvency Service including information on Insolvency Acts, Enterprise Act etc
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What types of insolvency are there?

A
  • Company Voluntary Arrangement
  • Administration - allows continued trading for a period, assets protected allowing to receive best price for assets
  • Liquidation
  • Receivership
  • Voluntary liquidation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What signs of insolvency should you be aware of?

A
  • work lacking progression on site
  • applications for payment over valued
  • unexpected claims for additional payment
  • materials / plant not ordered / delivered to site as expected
  • regular changes in work force suggesting non-payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What can a surveyor do when insolvency is suspected?

A
  • review of Companies House to identify any financial issue. Credit check on Experian
  • keep detailed records of transactions & events
  • if in breach of contract, consider termination
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a contra charge?

A

Where there has been a breach of contract and damages have been incurred
E.G Contractor may off sets costs against sub contractor that caused damage to finished work adjacent to the working area of the subcontractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

As a surveyor, what do you do when a party becomes insolvent?

A
  • Ensure protection of other party’s interests
  • Appoint an insolvency expert to co-ordinate actions
  • Seek legal advice
  • Secure site
  • Record the progress on site accurately including schedule of materials on and off site
  • Service an Urgent work notice as necessary
  • Ensure adequate interim insurance - contractors would likely have ceased as contract ceases
  • Consider claims on any bonds or consequential claims against 3rd parties
  • Ensure auditable financial reconciliation
  • Prepare notional FA
17
Q

Why is following the termination procedure important?

A

Incorrect following of the termination procedure could put the “terminating” party at risk of being in breach of contract, in which the other party could make claim for loss & expense

18
Q

What reasons would be a termination of contract?

A

Set out in contract but could include

  • Non- payment
  • Employer finds the project will carry too much ris and is unviable
  • Alternative land use is considered
  • Finance cannot be secured due to lack of pre-lets
19
Q

What is a breach of contract?

A

Failure by party to the contract to comply with an obligation imposed on it under the terms of the contract

Material - party not causing the breach can terminate
Non-material - contract remains open and issue can be rectified under the terms of the contract

20
Q

What is frustration?

A

Neither party has defauted on the contract, but unforeseen circumastances have prevented the contract from being performed as originally intended. Further performance of the contract is not possilble, is not legal or inherently different from what was contemplated by parties when considering the contract that it is void

21
Q

What happens if the employer becomes insolvent?

A

”- Contractor acts in accordance with the contract
-Inform sub contractors to remove materials that have not been invoiced & paid
- Surveyor issues valuation statement, FA and any claims including L&E