Final Accounts Flashcards

1
Q

How long do you get to settle a final account under the forms of contract you are most familiar with?

A

JCT Standard Building Contract (clause 4.5) - The contractor has 6 months from the date of Practical Completion to submit all the necessary details for the QS to make the final adjustment to the contract sum, and the QS then has 3 months in which to make the final adjustment.

JCT Design and Build Contract (clause 4.12) - The contractor has 3 months from the date of Practical Completion to submit their Final Statement. If they do not provide it within this period the Employer notifies the contractor that he has a further 2 months in which to submit it or the Employer will submit his own Final Statement in lieu of that of the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the Final Statement conclusive of under a D&B contract?

A
  • All extensions of time due have been awarded
  • The quality of materials and goods specified are to the satisfaction of the Employer
  • All claims have been settled
  • Unless challenged within 28 days of the due date for final payment the Final Statement is conclusive and cannot be challenged.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the structure of a Final Account?

A
  • Summary
  • Variable costs; Provisional sums, Prime Costs, Day works, Approx quants
  • Variations
  • Contract Instructions
  • L&E
  • Fluctuations
  • Risk allowances
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What would ISO9001 look for in a Final Account?

A
  • Project Control Plan
  • Instructions
  • FA structure
  • Statement prepared
  • Statement distributed to A / CA
  • Disputes recorded & resolved
  • Page numbers / comping
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Final Account?

A
  • Conclusion of the contract um
  • Includes L&E / EoT / Finalisation of disputes
  • Excludes LD’ / VAT / interest on overdue payments
  • End of financial obligations except defects
  • Contractor substantiates, Employer assesses
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is included in a Final Account Statement?

A
  • Usually covers the headers of the structure of the FA
  • Statement of ‘full & final settlement’
  • Not LD’s - taken in a pay less notice

Contract sum - Risk allowance (+/-) omissions / additions = FA total

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is retention affected at Final Account?

A
  • If agreed at PC, the Employer can release %
  • If it is to be agreed then the Employer can release a % of the amount they feel is due
  • If the FA is not agreed at the end of the defects libaility period, release only what is agreed
  • Retention on disputed items not released
  • Final certificate only released when the FA is agreed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How is a FA managed on an NEC?

A
  • No reference to FA
  • CE are time barred, making it more of a rolling FA
  • On going so the FA is agreed by the final CE agreement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What contractor documents are needed for final account?

A
  • Day work sheets
  • Subcontractor quotes
  • Substantiation to variation
  • L&E claims
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How is a FA prepared??

A
  • Scheduling out the cost impacts e.g.
    Prov sums (most agreed, possible later ones such as FF&E)
    Prime costs
    L&E
    Approx quants
    Fluctuations
    Contra charges (variation in SBC or pay less notice)
  • Should only be the difference in variatiosn from final monthly report
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What should a PM prepare to manage the FA?

A

Project Execution Plan
- Contract admin procedures
- Change control mechanisms
- Instruction procedure

Allows the employer to make informed decisions, auditable, notification & times as in contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the QS role in FA?

A
  • Prepare FA
  • Value variations
  • Advise on cost implications of L&E
  • Advise on defects costings
  • Calculations or withholding LD’s
  • Preparing statement
  • Outside of contractor account may report on; professional fee tracking, Section 106 / 278, CIL, VAT

Ultimately the agreement is between the Employer and Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the causes of dispute when it comes to FA?

A
  • Change in personnel - method of valuing
  • Defects where another contractor is used
    Was there a defect?
    Unsatisfactory work by 2nd Contractor
  • Value of variations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How are disputes managed when it come to FA?

A
  • Construction Act requires Adjudication
  • Settlement agreements
    • FA not agreed
    • Solicitor, not a QS
    • Wrap up outstanding disputes
    • Doesn’t change liabilities of latent defects, warranties & bonds
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What if there are defects at final account?

A

Patent defects - Plain to see! Discoverable by reasonable inspection. Cannot agree to final account
Latent defects - Not discoverable by reasonable inspection. Discovered later. Final Account may be agreed

After DLP, further defects are claimed through negligence through Limitation Act 1980 ( 6 yrs / 12 years)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly