Final Accounts Flashcards
How long do you get to settle a final account under the forms of contract you are most familiar with?
JCT Standard Building Contract (clause 4.5) - The contractor has 6 months from the date of Practical Completion to submit all the necessary details for the QS to make the final adjustment to the contract sum, and the QS then has 3 months in which to make the final adjustment.
JCT Design and Build Contract (clause 4.12) - The contractor has 3 months from the date of Practical Completion to submit their Final Statement. If they do not provide it within this period the Employer notifies the contractor that he has a further 2 months in which to submit it or the Employer will submit his own Final Statement in lieu of that of the contractor.
What is the Final Statement conclusive of under a D&B contract?
- All extensions of time due have been awarded
- The quality of materials and goods specified are to the satisfaction of the Employer
- All claims have been settled
- Unless challenged within 28 days of the due date for final payment the Final Statement is conclusive and cannot be challenged.
What is the structure of a Final Account?
- Summary
- Variable costs; Provisional sums, Prime Costs, Day works, Approx quants
- Variations
- Contract Instructions
- L&E
- Fluctuations
- Risk allowances
What would ISO9001 look for in a Final Account?
- Project Control Plan
- Instructions
- FA structure
- Statement prepared
- Statement distributed to A / CA
- Disputes recorded & resolved
- Page numbers / comping
What is Final Account?
- Conclusion of the contract um
- Includes L&E / EoT / Finalisation of disputes
- Excludes LD’ / VAT / interest on overdue payments
- End of financial obligations except defects
- Contractor substantiates, Employer assesses
What is included in a Final Account Statement?
- Usually covers the headers of the structure of the FA
- Statement of ‘full & final settlement’
- Not LD’s - taken in a pay less notice
Contract sum - Risk allowance (+/-) omissions / additions = FA total
How is retention affected at Final Account?
- If agreed at PC, the Employer can release %
- If it is to be agreed then the Employer can release a % of the amount they feel is due
- If the FA is not agreed at the end of the defects libaility period, release only what is agreed
- Retention on disputed items not released
- Final certificate only released when the FA is agreed
How is a FA managed on an NEC?
- No reference to FA
- CE are time barred, making it more of a rolling FA
- On going so the FA is agreed by the final CE agreement
What contractor documents are needed for final account?
- Day work sheets
- Subcontractor quotes
- Substantiation to variation
- L&E claims
How is a FA prepared??
- Scheduling out the cost impacts e.g.
Prov sums (most agreed, possible later ones such as FF&E)
Prime costs
L&E
Approx quants
Fluctuations
Contra charges (variation in SBC or pay less notice) - Should only be the difference in variatiosn from final monthly report
What should a PM prepare to manage the FA?
Project Execution Plan
- Contract admin procedures
- Change control mechanisms
- Instruction procedure
Allows the employer to make informed decisions, auditable, notification & times as in contract
What is the QS role in FA?
- Prepare FA
- Value variations
- Advise on cost implications of L&E
- Advise on defects costings
- Calculations or withholding LD’s
- Preparing statement
- Outside of contractor account may report on; professional fee tracking, Section 106 / 278, CIL, VAT
Ultimately the agreement is between the Employer and Contractor
What are the causes of dispute when it comes to FA?
- Change in personnel - method of valuing
- Defects where another contractor is used
Was there a defect?
Unsatisfactory work by 2nd Contractor - Value of variations
How are disputes managed when it come to FA?
- Construction Act requires Adjudication
- Settlement agreements
- FA not agreed
- Solicitor, not a QS
- Wrap up outstanding disputes
- Doesn’t change liabilities of latent defects, warranties & bonds
What if there are defects at final account?
Patent defects - Plain to see! Discoverable by reasonable inspection. Cannot agree to final account
Latent defects - Not discoverable by reasonable inspection. Discovered later. Final Account may be agreed
After DLP, further defects are claimed through negligence through Limitation Act 1980 ( 6 yrs / 12 years)