Retention Flashcards
Why is retention included in contracts?
- It’s a sum at each payment notice to provide client security that the contractor will return to correct any defects during the defects liability
- Retention can be used to fund payment of others to correct the defects if the contractor does not return
How may retention be applied?
% of the value of contract works
May have caps or limits
Some contracts may have retention free amounts
Retention bonds
What are the standard retention releases on some of the contracts you have worked on?
all 3% except intermediate (and minor) which is 5%
In intermediate and Minor works contracts, the % is stated is the value of the works that will be paid, rather than the value with held i.e 95%
What contracts do not have provisions for retention bonds?
Intermediate, prime cost and Minor contracts
What if no retention is to be taken?
This may be agreed in the contract
Would require ‘nil’ to be entered - as no % entry would result in the default applying
Would expose client to risk, unless a retention bond was agreed
What does retention apply to?
Generally to all works and materials on & off site
Would depend on the contract
How does a retention bond differ to a Performance bond?
A performance bond is to provide surety for non-performance of contractual duties
Retention bond is to rectify failures
Where both - employer has first use of retention
How do retention bonds work?
If selected, retention isn’t deducted but the statement is still prepared to show what would have been
Provided to Employer prior to date of Possession
Should state max aggregate sum & expiry date - included in contract particulars
If retention deductions exceed bond value, the bond can be increased by the contractor or the excess retention can be deduced
When is retention released?
At Practical Completion half is released
Final retention is released 28 days after end of DLP or Certificate of Making Good or the Final Statement is issued
How are retention monies held?
Retention is held in a separate bank account - designated to show the amount is the retention held
Except where LA, the Employer is entitled to any beneficiary from the moneys
What needs to be entered in to the contract for retention?
In the CP’s
Retention % or ‘nil’
Retention bond if applicable - expiry date and maximum aggregate sum
How does retention differ between JCT & NEC?
No retention bonds
Entered into the contract in Option Clause X16
No release at Sectional Completion
Final release on Defects Certificate
Where a performance bond is required, the retention clause is not normally used
How does retention differ between JCT & FIDIC?
Where sectional completions, only 40% of the proportional value is released. At the end of the DLP for the section, only a further 40% is released
Contractor is required to include retention deduction in monthly statements
Retnetion bonds are an option on some suites
What problems can occur with retention release?
- Any sum set off against retention where defective works should be fully justified
- Some contracts don’t release defects certificate until all defects are complete which can be a significant period
- Further down supply chains the retention may not be significant enough to incentivise correction
- On occasion the cost of administering the retention may be higher than the proportion of the actual retention
How are issues of insolvency dealt with?
JCT requires employer to act as trustee for the contractor, meaning the funds are in a separate account
If a client is liquidates, banks charge over fund will take precedence over the contractual obligation of the employer to place funds in a separate account - i.e. priority won’t be to return the funds to the contractor