Contract Law Flashcards

1
Q

What are the minimum requirements for forming a legally binding contract?

A
  • Offer
  • Acceptance
  • Consideration
  • Intent
  • Legality
  • Capacity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of a contract?

A
  • Defines the obligations of parties involved
  • Allocates risk between parties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a construction contract?

A

Legally binding written or verbal agreement between 2+ parties for providing a service in exchange for something of value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Privity of Contract? How is it mitigated?

A

Law that prevents a person who is not a party to a contract, enforcing a term of that contract

Collateral warranties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are Collateral Warranties?

A

Supporting document to a contract that creates a contractual link with a 3rd party outside of the contract.

Extends duty of care - used where there is design responsibility i.e. designer to funder

Might be provided to the employer, funders, purchasers and tenants - “ a beneficiary”

Often quicker and easier to deal with than 3rd Party Rights Act (1999)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the Contracts Rights of Third Parties Act (1999)?

A

Allows 3rd party rights to be created

Must expressly be identify the 3rd party

Enables right to enforce a TERM of the contract - not the whole contract!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the provisions of the Construction Act 1996?

A
  • Adjudication must be written in (if not, Scheme for Construction Contracts applies)
  • Payment must be certified within 5 days of the due date, even fi no amount is due
  • Pay when paid clauses banned
  • Right to be paid in interim periodic or stage payments
  • Right to suspend for non-payment

2011 amendments!

  • Right to pay less notice
  • Contractor recovers costs & EoT due to non-payment
  • Applies to verbal & written contracts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How else is the Construction Act known as?

A

HGCRA - Housing Grants, Construction and Regeneration Act 1996

Amended by the LDEDCA in 2009 - Local Democracy, Economic Development and Construction Act. Came in to force in 2011

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the Public Contracts Regulations 2015?

A

Implements the EU Public Sector Procurement Directive

OJEU - Office Journal of EU

Sets out the requirements of contracts for Public Sector works

FTS now

Sets out when a tender would be excluded
Tender must be Most Economically Advantageous Tender (MEAT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the Scheme for Construction Contracts?

A

Applies when construction contracts do not comply with Construction Act. Replaces non-compliant contracts.

Part 1 - provisions for adjudication

Part 2 - provisions relating to payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the Joint Fire Code? When would the Joint Fire Code apply?

A

Provides guidance on fire safety for construction sites, including prevention and detection

Applies to projects with a value >£2.5m or high risk

A large project is one with a value >£20m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is insolvency?

A

The inability to pay ones debts

Types include: administration, company voluntary arrangement, administrative receivership, compulsory liquidation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the difference between liquidation and administration?

A

Liquidation - selling all of a companies assets before dissolving the company completely

Administration - aims to help company repay debts to escape insolvency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What clauses would you expect to see in a collateral warranty?

A

-Warrantor’s obligations
-Insurance
-Limitation of Liability
-Copyright
-Assignment
- Step in rights
-Jurisdiction
-Third party rights

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the difference between collateral warranties & 3rd party rights?

A

CW - contractual link where there would not have been one. Require solicitor to draft. Preferred by employers due to familiarity and a tangible document in place. Argued that step in rights are easier to enforce.

3rd party - allow a named 3rd party to enforce a TERM of a contract, providing the CPs identify the 3rd parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What if contractor doesn’t provide a collateral warranty?

A

Case law where courts forced a CW to be provided

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is a Pay Less Notice?

A

Right under Construction Act 1996
Right to be informed of intention to pay less than set out in payment notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is a Performance Bond?

A

Used to insure against the risk of a contractor failing to fulfill contractual obligations e.g. insolvency
Typically at 10% of project value (cost usually 1%)
Covers the cost of finding a new contractor
Usually stays in place until PC or end of Defects Liability Period when final certificate is issued
Conditional or unconditional (employer to provide proof of contractor not meeting obligations or not)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is a PCG?

A

Protects in the instance a smaller contractor is controlled by a parent company
PC would be liable to meet the contract obligations where the contractor has failed
Covers defect liability period
If wider business goes bust then there is no guarantee
Usually no cap on value or duration as such

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is the Defects Liability Period?

A

AKA. Rectification period in JCT

Begins at certification of PC and typically lasts 6 - 12 months - NOT ISSUES APPARENT AT PC!!!

Client reports defects to CA who decides if they are defects or maintenance issues.

It is the Contractors responsibility to identify & rectify defects so important that those raised by client are not seen as a comprehensive list of all defects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the difference between limitation and rectification periods?

A

Limitation - claim made via PII for LATENT defects (negligence in design or construction). 6-12 years

Rectification - defects that become apparent during the stated period (6-12 months) which the contractor is to put right at own costs. Following final certificate at the end of the rectification period, the contractor is no longer obliged to attend site to rectify anything

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Why does it matter if a contract is signed under hand or under deed?

A

Impacts limitation period!

Under hand - 6 years

Under deed - 12 years (D = douze)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What are the types of Letters of Intent?

A

Comfort Letter - to reassure intention to create a contract. Least detailed, lacks contractual items. NOT LEGALLY BINDING

Consent to spend - gives permission to pay for works that are being done, details relating to works that can be undertaken, caps on value, caps on time. LEGALLY BINDING

Recognition of contract - has contractual details e.g. dispute resolution. Offers the most protection to parties of the contract. Client may be liable for costs and losses. LEGALLY BINDING

To be legally binding executory contract, it must be an offer capable of being accepted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What typical clauses might you find in a letter of intent?

A

Start date

Expiry date (when letter becomes invalid)

Scope

Value (cap of works to be undertaken)

Intention to enter into a formal contract

Key T&C’s

Insurances (those required)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

When would you use a letter of intent

A

Only where there is good reason to start work in advance of concluding the formal contract

Used only as a safeguard of legal right while the contract documents are being finalised

  • Immediate start on site required
  • Long lead times
  • Contract details still being negotiated

Coventry - where planning approval was due to expire, tender was due to expire and market conditions at the time were seeing significant fluctuations in material prices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What are the dangers of using a letter of intent?

A

Details of the contract have not been finalised

Contract is at large - i.e. contractor not bound to complete the works, only needs to be of reasonable quality at a reasonable rate

There are no detailed provisions for interim payments, rectification period, LADs or introducing change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What were the specifics of the LOI on your project?

A

Cap on spend at £3.2m

PII at £5m

Rectification period of 12 months

LAD’s at £3,000 pw

Date of possession

Date of contract to be signed - Sept 2021

Date of expiry of instruction 24th Sept

Date of first interim payment

Termination process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Can a QS draft a Loi!

A

No. A QS may advise on clauses and content such as:

Site possession date
Date of payments
Scope
Consent to spend amounts
Named parties e.g. CA / Principle Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What are liquidated damages?

A

A pre-estimate of losses that will be incurred by the employer should the Contractor miss the completion date. Set out in Contract Particulars

30
Q

How would you calculate LAD’s?

A

This is for the client to do, not a QS role.

Would advise to consider loss of income, additional professional fees, additional storage costs

31
Q

What is the process of recovering LAD’s?

A

Non completion notice issued by the CA

Employer notifies contractor of their intention to levy LAD’s

Can be withheld via pay less notice or recovered as a debt

32
Q

What are the benefits of LAD’s?

A

Certainty - gives certainty to both parties as to what would happen if a breach occurs

Limitation of liability - places a cap on the liability of the contractor, never exceeds the agreed amount

Saves time & expense - pre-agreed, reduces disputes, focus on the issues at hand

Deterrent against breach of Contract - financial consequences known

33
Q

What happens if the LAD section is blank?

A

Cannot levy liquidated damages

Could pursue unliquidated damages in court, will need to prove actual loss

If “nil” is inserted this may prejudice ability to seek unliquidated damages

34
Q

Are LAD’s a penalty?

A

No - genuine loss incurred by client due to late completion

If they are a penalty, the common law view is they would not be enforceable

35
Q

What are unliquidated damages?

A

Occur where actual losses are significantly different to those that were estimated at the time of contract

Not preagreed

Determined by court

Need to be proven - collation of records

36
Q

What are unliquidated damages?

A

Occur where actual losses are significantly different to those that were estimated at the time of contract

Not preagreed

Determined by court

Need to be proven - collation of records

37
Q

Can you recommend payment for materials off-site?

A

Dependant on contract

Material would be specifically referenced in contract

Requires a vesting certificate in name of Employer, insurances, labelled correctly, secure and safe storage, off-site materials bond

38
Q

What is a vesting certificate?

A

Confirms ownership of goods, plant or materials will transfer from own party to another on payment

39
Q

What are the three ways to transfer benefits under a contract?

A

Novation - transfer of contractual rights and obligations

Assignment - transfer benefits e.g. right to payment and claims for breach of contract. Does not transfer burdens e.g. obligations to pay

Collateral Warranties

40
Q

What is another name for limitation period?

A

Latent defects period!

Still no obligation for contract to rectify the latent defect but allows building owner to seek compensation for action for damages, breach of contract or negligence

41
Q

What is the CDM 2015?

A

Construction Design and Management Regulations (revised in 2015)

Ensures H&S issues are considered throughout a projects development

Replaced the role of CDM coordinator with principle designer to give opportunity of influence to someone involved throughout design

42
Q

When is a project notifiable under CDM?

A

Notifiable to H&S executive when it is expected to last longer than 30 days, have more than 20 workers at the same time, exceeds 500 person days

43
Q

What are preliminaries?

A

Provide a description of the works allowing contractor to assess costs. Specify the general conditions. Do not form part of a package of works.

Cost of delivering the works providing general plant, site facilities, site staff that are not included in the rates

44
Q

What examples of prelims would you expect to see in a contract?

A

Method statements

Description of reporting requirements

The site

General works descriptions

Site logistics

Quality management procedures

Requirements for insurances, bonds, warranties and guarantees

45
Q

What are preambles?

A

An explanation of a document to aid understanding e.g. contract. Avoid repeating information set out in the main documents

46
Q

What are preambles?

A

An explanation of a document to aid understanding e.g. contract. Avoid repeating information set out in the main documents

47
Q

What are examples of preambles?

A

Description of parties to a contract

Backgrounds to the document

Tendering procedures

Objective of the project

48
Q

What is the difference between time charge and fixed prelims?

A

Time - based on cost over duration i.e. site management / security

Fixed - lump sum payment items that have staged payments e.g. scaffolding where the bulk of the cost is in erecting and taking don

49
Q

What is retention?

A

An amount deducted from the amount due to contractor at interim payments to provide client security that contractor will return to correct any defects during defects liability period

50
Q

What is retention?

A

An amount deducted from the amount due to contractor at interim payments to provide client security that contractor will return to correct any defects during defects liability period

Set out in Contract particulars. Standard rates will apply if nothing is entered (varies with different contracts).

A % is released upon completion of works (usually approx half) but prior to end of defects liability period

Where contractor does not rectify works, retention can be used to rectify

Right to be held in separate bank account - important in cases of insolvency

51
Q

What alternatives to retention are there?

A

Retention bonds - agreement between employer & surety that acts as a guarantor should the works not be completed.

Equivalent amount of retention is held in a bond.

QS should still prepare statements under JCT SBC (not needed under D&B)

Bonds are typically in a maximum aggregate - where exceeded, can increase bond or retention deducted from interim payments

Retention bonds should be called upon prior performance bonds if both are provided (PB - surety for non performance, RB - rectify failures)

52
Q

What are the benefits / risks of retention bonds?

A

May see less risk priced into contracts

Help contractor cash flow

May have to certify certain conditions before call on the bond (on demand mitigates this)

53
Q

What are the types of retention bond?

A

Conditional (default)

Unconditional (on demand)

54
Q

What is the difference between sectional completion and partial possession?

A

Sectional completion - agreed in advance, included in CP. LAD’s separate for each section.

Partial possession - not planned, (already has it’s P!), Employer needs consent from contractor. LAD’s are as per CPs and reduced pro rata to the value of the part of the works taken over. Treated as a variation so potential cost impacts (may impact sequencing)

Upon SC or PP, rectification period for that part of works commences, no longer liable for LAD’s, half retention is released and Employer must ensure those works

55
Q

What insurances may be required under a contract?

A

All risk - all risks associated with construction project, usually under joint with contractor and principal client. Covers against unforeseen loss or damage to building, public liability, tools plant etc

Employers Liability - compensation if an employee is ill or injured due to work

Public Liability - Contractors to cover against personal injury, death, loss or damage to 3rd party members

PII - professional services, covers negligence of service providers

Performance bond - covers client against risk of contractor failing to fulfill contractual obligations e.g. insolvency. Contractor takes out

Latent defects insurance - cover where latent defects are apparent, more complete cover than CW

56
Q

What alternatives are there to SC and PP?

A

Early use - contractor remains responsible for that part of works with H&S and insurance. Consent of contractor required.

Grants early access but may be denied for sequencing, access or H&S reasons

57
Q

What are the different forms of dispute resolution?

A

Negotiation

Mediation - neutral 3rd party

Adjudicator - ruling given 28 days after hearing

Arbitration - judge gives ruling

Litigation - lawyers, public, harmful to reputations

58
Q

What is the difference between Deed and Underhand?

A

Deed - 2 signatures, witness, limitation period of 12 years

Underhand - 1 signature, limitation period of 6 years

59
Q

What is a PCSA?

A

Contract entered prior to main building contract allowing contractor to collaborate with the Employer and carry out services such as furthering design, advising on buildability, tender packages etc.

Typically used on 2 stage tenders

60
Q

When can you use a PCSA?

A

When main contract is:
-SBC
-D&B
-Major Project
-Intermediate

Regardless of design responsibility

Where novation to contractor of specialist sub / supply / consultancy contracts

Minor adaptations to use with CM

Not for between employer or main contractor and specialist sub contractors

61
Q

What are the benefits of novation?

A

Client maintains early input from designer

Retain a single point of responsibility as contractor takes all rights and obligations

Consistency of design

62
Q

What are the disadvantages of novation?

A

Lack of control of design development - no longer Employer monitored

Employer loses contractual relations with novated party and therefore right to take action against breach in contract - usually a CW between Employer and Novated Party

63
Q

What are retention statements?

A

Statement showing which elements of work are subject to retention and which are not

64
Q

What is a relevant event?

A

Event causing delay to completion. Caused by client or neutral event

EoT

65
Q

What examples of Relevant Events are there?

A
  • Variations
  • Exceptionally adverse weather
  • Delay in giving contractor site possession
  • National strikes
  • Force majeure
66
Q

What is a relevant matter?

A

Matter that the client is responsible for and materially effects the progress of works.

Claim direct loss and expense

67
Q

What examples of Relevant Matters are there?

A
  • Failure to give access / possession to site
  • delays in receiving instructions
  • disruption from works carried out by client
  • Instructions relating to variations and expenditure of provisional sums
  • Issues relating to CDM
68
Q

What is the difference between a Performance Bond and Parent Company Guarantee?

A

PCG - covers defect liability period, don’t cap on value. If the wider business goes bust, then there is no guarantee

PB - usually a cost that is passed onto the client, default or on-demand bond, expiry date written into contract (typically PC or end of rectification period)

69
Q

What are joint name policies?

A

‘Joint name insurance policies include contractor and employer and are where the insurers have no right of recourse against any named insured

70
Q

What would be included in the contract documents for a traditionally procured project?

A
  • Articles of agreement and conditions of contract
  • Preliminaries
  • Pricing document i.e. bills of quantities
  • Drawings and specifications
  • Any bonds or warranties
  • Contractor’s Proposals if any contractor’s designed portion included
  • Pre-construction information
71
Q

What would be included in the contract documents for a design and build project?

A
  • Articles of agreement and conditions of contract
  • Employer’s Requirements
  • Contractor’s Proposals
  • Contract Sum Analysis