types of procurements Flashcards

1
Q

What are the four main types of procurement?

A

Traditional, design and build, management contracting, construction management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a traditional contract?

A

Client gives out work through tendering procedure, contracted chosen and begins work onsite with design brief from the design team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is design bid build?

A

A procurement method where the client hires a designer and then a contractor to build based on the design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who shares commercial risk in traditional contracts?

A

Designers and contractors share commercial risk, with contractors typically taking more risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the main advantage of design and build procurement?

A

Gives single point of responsibility for the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In a single stage design and build, what happens?

A

Contractors are appointed under a single agreement to design then build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a two-stage design and build contract?

A

Contractors selected on a basis of agreement, then work with the design team, reducing commercial risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a key advantage of the two-stage design and build approach?

A

Work can start before design is finished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a disadvantage of the design and build method?

A

Contractors can compromise to keep costs down, lack of design control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does construction management involve?

A

Works are constructed by a number of trade contractors, with the contractor not having full control of trades

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the advantages of construction management for the client?

A

Client involved more, direct contact with smaller contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a major disadvantage of construction management?

A

High client risk as the client must involve themselves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What distinguishes management contracting from construction management?

A

Client maintains ultimate control and management contractor assumes full control of trade contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fill in the blank: The procurement route where the main contractor is appointed and the design team is eliminated is called _______.

A

[design and build]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

True or False: Traditional contracts are commonly used in lump sum agreements.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What types of contracts are included under other types of procurement?

A
  • Custom build
  • Emerging cost contracts
  • Fast track construction
  • Guaranteed maximum price
  • Lump sum contract