Tute 9 (Tara) Flashcards
What should you do if the client pays the builder more than you have assessed the progress claim for?
Advise the client of their responsibilities under the contract
Remind them that the extra money they have paid is not insured to be included in the next claim
And process your assessed claim.
You are acting independently (top hat)
Reference: Tute 9 2020-07-27 19:35:00
If you are worried that the subcontractor is not building the joinery to the latest revision of drawings?
Contact the contractor immediately.
Never contract the sub-contractor directly.
Who’s responsibility is it to collect all certification for the Statutory compliance document to give to the building surveyor for certificate of occupation?
The contractor.
You can switch the responsibility to the owner in a section of the ABIC - sometimes happens in projects like prisons where the security isn’t done by the contractor and therefore the contractor cannot get full certification.
What is the difference between calendar days, business days and working days?
Calendar days are all days.
Business days are Monday-Friday.
Working days are the days that the site is operational often with union RDO’s excluded (usually every two weeks)
What falls under the construction days timeline under the contract?
Mobilising time (ABIC, 10 wd)
Net construction days
Weather delay days (ABIC, Item 20, 10 wd)
Other known delay days (nominated in Item 21 ABIC. E.g. site is on a public road that will be shut down for an event)
Time extension
Liquidated damages (item 24 ABIC)
When do the official construction days start and finish?
Official the construction days run from the signing of the contract until the date of Practical completion.
What happens when the client or the architect triggers the prevention principle with the contract and what does it mean to say the ‘clock is running’?
The prevention principle is when a party has caused the contractor to not be able to proceed at all as they normally would and therefore when the clock starts running means that the delay has now voided the end date and they can finish whenever they want.
ABIC-SW, Section L1.
Approved time delays that do not incur Time extensions costs?
Extra weather delays over the weather days slowed in the contract (ABIC item 20)
Other delays (known delays) that run over the nominated time under the contract (ABIC item 21)
What if the contractor is ahead of schedule and then put in a request for delay. Do you approve the delay and adjust the PC date?
It depends on the wording of the contract.
If the contract says the delay affects a critical element of construction then they will be entitled to delays.
What happens if a contractor submits a critical RFI does not follow it up and then submits an extension of time after the due date?
They could be entitled to the delay if the RFI was critical and affects the critical path.
However, if could be argued that the contract states something to the effect that they should do everything in their power to avoid delays and if they didn’t follow up the RFI and knew it was critical then they might not be entitled to the delay.
What does a concurrent delay mean?
It means a delay to a construction element whilst another element is happening and therefore does not affect the trades timeline.
Is the construction programme a contract document?
No!
You want to allow the contractor flexibility to change it otherwise they could claim a variation every time there’s a change as it’s bound to the contract.
In many cases, what aspects of the project is the architect responsible for? (Acumen, Project Control)
ALL.
Including design, the work of specialist consultants, project costs and time. A key responsibility is to maintain accurate project records that demonstrate how the project has been managed.
What is the formal response to viewing a program devised by a contractor?
Programs provided by contractors should not be accepted, approved or commented upon as this may be construed as an endorsement of the document and affirmation of the accuracy of its content.
Acumen, Program as a Contract
Should the construction program be part of the Contract?
Nicole recommends it not be included as a contract doc.
Acumen, Managing time during construction:
It is important that the program is a requirement of the contract and NOT PART OF THE CONTRACT documents, in case an instruction that causes the contractor to diverge from the construction program permits the contractor to claim an otherwise unjustifiable time extension.
Acumen, Program as a Contract:
Since the program is a management tool, it is o en in a state of flux as circumstances change. As a contract document, each update would require all parties to the contract to accept and endorse the new program as a variation to the terms of the original contract. The risk of dispute is high if an updated program were to be unacceptable to one of the parties.
When should the program be updated?
Regularly.
The program to be either regularly updated during the course of the contract, or when directed by the architect, if the contractor is behind program.
- Acumen, Managing time during construction
When does the contractor have to provide a up-to-date accurate program (not preliminary)?
The ABIC suite of contracts requires the contractor to provide the architect with a construction program within 10 working days aer possession of the site, and to provide an updated program when the date of practical completion has been adjusted by five working days or more or such other period as agreed.
- Acumen, Managing time during construction
with the contractor, what is falling behind schedule an indication of and how should the architect proceed if they have concerns about the contractor fulfilling the contract?
Insolvency.
The Contractor should be reminded that the job is to be completed on time or the owner will be entitled to liquidated damages. The contractor can also be asked to demonstrate how it is proposed to fulfill the contract.
The facts can be stated for example, ‘It is a week until the date for practical completion and the footings have not been poured yet.’
- Acumen, Managing time during construction
Should the client come to site meetings with the contractor?
Yes as its important to keep the client informed.
Invite the owner to a ttend or send a representative to site meetings to observe, but NOT NECESSARILY PARTICIPATE.
The owner can thus see the constructive role played by the architect in monitoring the progress of the work, in identifying work which is behind schedule, and in encouraging the contractor to reschedule work to regain lost time.
- Acumen, Managing time during construction
What should the contractor prepare for each site meeting?
The agenda should include a report from the contractor on progress and the likely date of completion.
- Acumen, Managing time during construction
how and when should a program be provided to tenderers?
For larger/complex projects.
Consult a programming consultant to set a realistic provisional program, related to the date for practical completion. This provisional program could be issued to tenderers for their INFORMATION ONLY in tendering and may, at the contractor’s discretion, form the basis for the construction program referred to above. Again, it should be made clear that whatever the source of the program may be, it DOES NOT form part of the contract.
- Acumen, Managing time during construction
If a program is to be provided to tenderers, what might also accompany it?
the program be accompanied by a cash-flow projection and a trade breakdown of the tender with both related to the program.
- Acumen, Managing time during construction
What is the critical path or critical activities in construction?
The critical path is the longest path through the project. The critical activities to progress are those which determine the critical path and are the activities that must be completed (or at least started) before subsequent activities can commence.
What are claims for delay assessed against?
Claims for delay are assessed against the critical path.
Delay, beyond the contractor’s control, to activities on the critical path would normally be agreed and the date for practical completion would be adjusted. Delays to activities not on the critical path may be agreed with or without an adjustment to the date for practical completion.
- Acumen, Managing time during construction
Does the architect have authority to give instruction of the program or construction timeline?
The architect cannot legitimately interfere with the contractor’s programming and sequencing of the works unless the contract allows the owner to instruct this through its agent, the architect. Generally it is the contractor’s obligation to execute the works within the contract time or else be liable for payment to the owner of liquidated and ascertained damages.
- Acumen, Managing time during construction