Tute 8 (Tara) Flashcards

1
Q

There is now Security of Payment legislation in New South Wales, Victoria, Western Australia, the Northern Territory, South Australia and Tasmania. Security of payment legislation in Queensland has been recently superseded with new legislation to take effect when?

A

January 2018.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what must be in place before the first progress cliam is paid?

A

Security set up, insurances, and the project program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

To what construction projects does the security-of-payments legislation apply?

A

The legislation applies to virtually all commercial construction contracts involving building work.
There are limited exceptions for:

the construction of single houses, generally where the house is for the client - “except ‘one off houses’ where the owner for the building contract is to be the occupier (most architect-designed houses). “

finance agreements for use in the building industry

in some states, construction contracts in the oil and gas and mining industries

Information for the particular state or territory in which the project is located will need to be checked for more detail about these exemptions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The security of Payment Act in each state establishes a procedure that enables:

A

contractors to make monthly payment claims to owners

owners to provide payment schedules to contractors

referral of disputed or unpaid progress claims, including those for ‘claimable variations’ to an independent adjudicator

payment of progress claims decided by the adjudicator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

You should always advise the owner to obtain immediate legal advice in dealing with security of payment claims because:

A

the time limits involved for compliance by the owner are tight

the procedures are complex and certain formalities must be observed to protect the owner’s rights

developing case law will progressively clarify some uncertainties, including what items are or are not covered by the legislation, and uncover others

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens if the owner fails to comply under the security of payment act?

A

Where the owner fails to comply with their obligations, the contractor is also entitled to serve a notice of intention to suspend work. The contractor can then suspend work two business days after serving the notice, if the payment claim is not paid or not paid in full.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How many days does the contractor have to wait until they suspend work after serving a notice of intention to suspend work due to such circumstances as the owner not complying with the security of payment? and what are they entitled to if suspension happens?

A

two days after serving a notice to suspend work, they can suspend work.

If the work is suspended, the contractor might be entitled to an extension of time under the contract for the period of the suspension.

(Acumen: Security of Payment - Victoria)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When should GST be applied to a claim?

A

After all other percentages are applied. For example, builders margins on Provisional sums etc are applied before any GST. GST is the last thing to be applied always.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the final certificate?

A

A final certificate is a certificate issued by the architect at the end of a construction contract to show the amount of the final payment due to the contractor and to certify that the works have been completed in accordance with the contract.

Some clients may require the contractor to sign a ‘release of all claims’ before the final payment is made. It is unlikely that this would avoid the exceptions identified above.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The responsibilities of an architect (as contract administrator) are set out in the ABIC contracts in the following clauses:

A
  1. The architect is appointed to administer this contract on behalf of the owner. The architect is the owner’s agent for giving instructions to the contractor. However, in acting as assessor, valuer or certifier, the architect acts independently, not as the agent of the owner.
  2. The owner must ensure that the architect, in acting as assessor, valuer or certifier, complies with the contract and acts fairly and impartially, having regard to the interests of both the owner and the contractor. The owner must not compromise the architects independence in acting as assessor, valuer or certifier.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In relation to payments made from principal to contract, Clause 42.1 of AS 4300–1995 (along with related Standards Australia contracts, such as AS2124–1992) (AS 4000, although drafted differently, is to similar effect) provides that:

A

…the Principal shall pay to the Contractor…if no payment certificate has been issued…the amount of the Contractor’s claim.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Regarding the late processing of Progress claims by the architect, The Daysea case decision confirms two very important lessons under Standards Australia contracts, such as AS 4300–1995:

A
  1. The architect must issue a certification strictly within the time required by clause 42.1 or expose the principal/owner to a liability to pay the full amount claimed
  2. Payment certificates (or progress claims if payable because no certificate has issued), although they have to be paid, can be revised by a properly issued final certificate.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

With standard lump sum form contracts, what pattern does the cashflow generally look like?

A

When represented graphically, this pa”ern is seen to be in the form of a lazy ‘S’. It is o$en referred to as the ‘S’ curve of payments.

In practice, the payments would be more likely to be shown as monthly amounts rather than percentage amounts and the periods would more likely be months. but the lazy ‘S’ would still be evident.

It is easily seen (and can be easily explained to a client) that the rate of payments is greater in the middle of the contract period than near the start or end of it. Usually, there is more building work in the middle months than in the first and last months.

Acumen, Progress Claims - Planning cash flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When is security released?

A

Most standard-form building contracts include provisions for the release of the security to the contractor usually 50 per cent at practical completion and the remaining 50 per cent at the end of the defects-liability period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the types of security?

A

retention fund (an amount retained progressively from each payment until a nominated limit is reached) or unconditional guarantees (usually two, each valued at half the total security)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who keeps the cash retention?

A

the owner must hold the cash retention …as trustee for the contractor in a separate bank account designated as a trust account.

17
Q

Who should hold the unconditional guarantees?

A

As unconditional guarantees are effectively negotiable currency, they are valuable and should be held by the owner, and the architect should retain copies only. The transmi”al and receipt of such guarantees should be clearly documented and recorded.

18
Q

Total project cost is impacted by a number of sometimes unforeseen non-general issues in addition to construction cost alone, such as:

A
  • land costs (separate the purchase price)
  • legal fees (VCAT etc)
  • interest rate charges and financing costs
  • development application and building approval fees and charges council contributions, fees and levies
  • escalation
  • consultant fees, project-management fees and charges
  • tenancy fit-out costs
  • infrastructure charges

Acumen, Cost Control

19
Q

When is Bill of Quantities usually established by the QS?

A

at the 90% to 95% stage of contract documentation.

20
Q

Signs that indicate that the contractor may be financially unstable include:

A

submission of a claim followed by a request for payment in a reduced period (maybe due to pressure from creditors)
overclaiming for work not yet complete or materials on-site but not fixed (particularly worrying where overclaiming occurs regularly)
subcontractors working more slowly than expected or not coming to site (perhaps they are not being paid)
job progress is generally unsatisfactory.

Acumen, Insolvent contractor

21
Q

The Institute also publishes documents to assist in the selection of architects. These are:

A

Quality based selection

Competition Guidelines

Client information notes (Acumen)

22
Q

What percentage is usual for contingency and does the architect need to give approval before using it?

A

Your architect may recommend that the tender documents include a contingency sum, usually equal to 5% to 10% of the total cost of the work and sometimes more for renovation projects. This sum of money can only be used with your approval, when variations become necessary or are requested.

Acumen, Client note: Variations to scope of work, Contingency sums

23
Q

What are the categories that make up the total end cost of the project budget?

A

At the commencement of a project, it is important for you to know the total end cost of your project. The net cost of construction can be established in a number of ways. There are, however, a number of additional costs that will arise, which must be allowed for when establishing the total project budget. These costs will vary depending on the type of project, from one project to another, and throughout the design and construction process.
The total end cost may be made up of:
- land costs
- the net construction cost of the building
- design fees, including all consultants statutory fees and charges
- project contingency sums
- legal, accounting and other fees financing
cost escalation
- furniture, furnishings and equipment

Acumen, Client note: Contingency sums

24
Q

The following is the usual process and your obligations for progress payments:

A

The following is the usual process and your obligations for progress payments:
1. The contractor presents a progress claim to the architect.
2. The architect assesses the claim, determines the monetary amount which the
contractor is entitled to under the contract and issues a progress certificate to the
contractor.
3. The contractor presents the progress certificate and a tax invoice to you for
payment.
4. The building contract usually states a limited time within which you must make the payment. It is important payment is made to the contractor within the time limits otherwise the contractor may claim interest on the outstanding payment amount.

Acumen, Client note: Progress payments during construction

25
Q

When you recieve a variation you should send a letter and advise your client of the following:

A

Advise:
your assessment that the quote is fair and reasonable;
nature of the variation;
reason for the variation;
impact of the variation on the cost and construction time for the project, if any; and implications of not accepting your recommendation.

26
Q

Different construction site insurances?

A

Site insurances - objects etc

Public liability - other people coming into site

Works compensation - workers on site

27
Q

What is an instruction to ‘open up’ and when would this be issued?
What are the consequences when this instruction is issued flippantly? Can the contractor claim this as a variation?

A

An instruction to open up is an instruction open up works on site to inspect something that cannot be seen without opening up.

This should only be issued if you are reasonably confident that the works underneath have not been built to the drawings/contract.

You have to be reasonably sure of an error as if the works are opened up and it is built perfectly to the drawings/contract then the contractor can claim a variation to make good the works again after opening up the works.

28
Q

What makes up the contract price?

A

Net cost of works + GST

29
Q

Can a QS assess a progress claim?

A

Acumen: yes

Nicole: no! A QS can not assess whether something is built to code and fixed properly to classify as now built. They can however walk around site with you and help you make your assessment.

30
Q

What happens if the bank (lending the client the money) disagrees with the amount you have approved for the progress claim and won’t give the full amount?

A

The client MUST pay the amount you have approved regardless.

You are making an independent assessment that should not be influenced later by the banks opinion.

31
Q

What should you do if the builder issues you a progress claim with the words invoice on it?

A

Legally, you can become liable if you respond or acknowledge a progress claim that states that it is an invoice.

A progress claim is not an invoice as it’s a claim that has not yet been approved.

Ask them to send you a corrected progress claim without the word invoice.

They can issue an official invoice for the progress claim that has been approved.

32
Q

What is the minimum amount of information the contractor has to include in their variation?

A

1800 Labour cost
500 Materials/equipment cost
300 Associated prelims

2600 Subtotal net cost ex GST

390 Builders margin (item 17) 15%

2990 Subtotal

299 GST at 10%

3289 Total Contract price adjustment

33
Q

With variations, can you negotiate builders margin percentage?

A

Only at tender time and then it’s signed into contract docs.

34
Q

What do you do with negative variations?

A

Same progress except you cannot claim back to builders margin as the builder is entitled to their margins they signed into with the contract.

35
Q

Is the constituency required to be disclosed in the contract?

A

It can be specified in the contract but they are not required to be stated. And it is not recommended to let the builder know what the contingency is.

36
Q

True or false: If the prime cost ends up being less, you can claim back the cost saving and in full?

A

False. You cannot claim back the builders margin.

The builder is entitled to all profit margin they signed into within the contract.

37
Q

What is ‘rise and fall’?

A

The construction industry term for inflation and deflation?

38
Q

What monetary consideration might you want to write into the contract if you are pretty sure there is asbestos in the site/builder?

A

Nicole and Jim: Write it in as a specific provisional sum.

The contingency is capped.

39
Q

How long does the client have before the contractor suspends work after giving notice of intent to suspend works?

A

2 business days.