ABIC Simple Works Contract (Melany) Flashcards
Define a ‘Business Day’
Any day other than a Saturday, Sunday, or Statutory public holiday in the State or Territory shown in item 35 of Schedule 35.
Define ‘Contract Price’
Is the ‘Cost of Building Work’ + GST.
Is a lump sum and the Contractor allows for:
- the *works
- provisional and prime cost sums
- installation of any item to be supplied by owner and installed by contractor
- rise and fall
- statutory charges
- exchange rates (5 days before closing of tenders)
- imports and tariffs (5 days before closing of tenders)
- industrial awards and workplace arrangements
- exchange rates (5 days before closing of tenders)
- GST
Define ‘Cost of Building Works’
Actual net cost of the *works, excluding GST
The Cost of Building Work + GST = Contract Price
Define a ‘Critical Construction Activity’
An activity which is part of the necessary work that if delayed will have direct effect on subsequent activities such that the contractor’s ability to achieve practical completion by the date for practical completion will be affected.
Define a ‘Defect’
Work that is:
- in breach of any warranties outlined in the contract documents
- not in accordance with the standard or quality of building work specified in the contract documents.
Define ‘Non-Working Days’
- Statutory public holidays
- rostered days off
- recognised industry shut-down days
Define ‘Site’
The place at which the *works are to be constructed and any other place mad available by the owner to the contractor under this contact (eg, a public area used for a bin skip).
Define ‘Valuable Item’
A valuable item includes minerals, money, treasure, fossils, archeological remains, historic objects or relics.
Define what an ‘Arete’ is in climbing
A small ridge-like feature or a sharp outward-facing corner on a steep rock face.
Define a ‘Working Day’
Monday to Friday, excluding *non-working days.
What are the the 3 insurances that Contractors generally are responsible for, as part of executing an ABIC SW contract?
At what point do they cease?
- Public liability
- Contract Works
- WorkCover
After Final Certificate is issued.
Are the ‘Adjustment of Time Costs’ (as noted in Item 18 Schedule 1) excl. or incl. GST?
Including GST.
Is the Rate for Liquidated Damages (as noted in Item 24 Schedule 1) excl. or incl. GST?
Including GST.
List the order of precedents for the *contract documents.
- The Special Conditions
- The owner occupier Special Conditions
- The Contract Schedules
- Specification
- Drawings
- All other drawings
After how many days of taking possession of the site must the Contractor begin the Works?
10 days.